Running head: ICT PROJECT MANAGEMENT
ICT Project Management
“I-Crop Project”
Name of the Student:
Student ID:
Name of the University:
Author’s note:
ICT Project Management
“I-Crop Project”
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1ICT PROJECT MANAGEMENT
Introduction
The following assignment is a project charter document developed for integrating the analysis of
the mobile application and website development for I-Crop project. The purpose of the charter is
to form an initial requirement document for the stakeholders so that they can understand the
project more easily.
Purpose
The purpose of the report is to develop a project charter that can be used as an initial document
containing all required documents for getting an overview of the mobile application and website
development for I-Crop project.
The objectives of the report are,
To develop an initial document comprising of information about the project schedule and
budgetary information
To enhance the management of the successful development by passing on the information
to its stakeholders
Project Description
Project Details
The website and mobile application would be effectively helpful in managing the project
objectives. The orders and services would be increased and managed easily with the help of the
improved communication plan development.
Introduction
The following assignment is a project charter document developed for integrating the analysis of
the mobile application and website development for I-Crop project. The purpose of the charter is
to form an initial requirement document for the stakeholders so that they can understand the
project more easily.
Purpose
The purpose of the report is to develop a project charter that can be used as an initial document
containing all required documents for getting an overview of the mobile application and website
development for I-Crop project.
The objectives of the report are,
To develop an initial document comprising of information about the project schedule and
budgetary information
To enhance the management of the successful development by passing on the information
to its stakeholders
Project Description
Project Details
The website and mobile application would be effectively helpful in managing the project
objectives. The orders and services would be increased and managed easily with the help of the
improved communication plan development.
2ICT PROJECT MANAGEMENT
Project Background
The Globex has decided to implement a new mobile application and website development and
named it ‘I-Crop Project’. It would help them in managing the customers and getting active
feedbacks from their customer.
Part one: MOV – Measurable Organizational Value
Social: The social media platform would be responsible for the development of the successful
management of the activities and aligning the formation of the increased management
operations. The utilization of the improved functional development would be helpful for aligning
the completion of the activities.
Operational: The operational development would be implied for easing the management of the
successful development of activities. It is largely responsible for the continuation of the activities
and forming management of the functional development.
Customer: The customer focus on the website development for I-Crop project would be
effectively aligned with the independent management of the activities. The customer
involvement would be effectively deployed for listing the evaluation of the functions for taking
care of actions.
Financial: The financial operations of the I-Crop project would be held responsible for the
completion of the activities and aligning development model.
Values
Project Background
The Globex has decided to implement a new mobile application and website development and
named it ‘I-Crop Project’. It would help them in managing the customers and getting active
feedbacks from their customer.
Part one: MOV – Measurable Organizational Value
Social: The social media platform would be responsible for the development of the successful
management of the activities and aligning the formation of the increased management
operations. The utilization of the improved functional development would be helpful for aligning
the completion of the activities.
Operational: The operational development would be implied for easing the management of the
successful development of activities. It is largely responsible for the continuation of the activities
and forming management of the functional development.
Customer: The customer focus on the website development for I-Crop project would be
effectively aligned with the independent management of the activities. The customer
involvement would be effectively deployed for listing the evaluation of the functions for taking
care of actions.
Financial: The financial operations of the I-Crop project would be held responsible for the
completion of the activities and aligning development model.
Values
3ICT PROJECT MANAGEMENT
Better- the implementation of the I-Crop project would be effectively deployed for integrating
the utilization and formation of the successful continuation of the projects.
Faster- the faster completion of the projects would be implied for forming the cohesive
management of the activities.
Cheaper- the overall cost required for the completion of the activities of Globex can be reduced
by the help of the automatic activities due to the I-Crop project.
Do more- the applications of I-Crop project would be implied for taking care of the prominent
development of the operations like communication and information transfer.
Rank Impact Metrics Timeframe (in months)
1 Financial Profit Margin 3
2 Customer Feedbacks and Orders 4
3 Operational Processing Time 2
4 Strategy Effective Implication 1
5 Social Feedbacks on social media web 5
Part Two: Project Scope
In scope- The in scope items of the project of website and mobile application for I-Crop include
the development of the project plan, initiation documents, design, website development, mobile
application development, UX development, testing activities, and final documentation.
Out of scope- the out of scope items of the project include the transportation requirements,
change management, and communication plan.
Better- the implementation of the I-Crop project would be effectively deployed for integrating
the utilization and formation of the successful continuation of the projects.
Faster- the faster completion of the projects would be implied for forming the cohesive
management of the activities.
Cheaper- the overall cost required for the completion of the activities of Globex can be reduced
by the help of the automatic activities due to the I-Crop project.
Do more- the applications of I-Crop project would be implied for taking care of the prominent
development of the operations like communication and information transfer.
Rank Impact Metrics Timeframe (in months)
1 Financial Profit Margin 3
2 Customer Feedbacks and Orders 4
3 Operational Processing Time 2
4 Strategy Effective Implication 1
5 Social Feedbacks on social media web 5
Part Two: Project Scope
In scope- The in scope items of the project of website and mobile application for I-Crop include
the development of the project plan, initiation documents, design, website development, mobile
application development, UX development, testing activities, and final documentation.
Out of scope- the out of scope items of the project include the transportation requirements,
change management, and communication plan.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4ICT PROJECT MANAGEMENT
Assumptions- It has been assumed for the project of website and mobile application for I-Crop
that,
Project would be completed in the estimated time and budget
Uses of the provident development factors can be implied for successful alignment
development
Resources required for the completion of the project would be done cohesively
Constraints- the factors of time, budget, and resource usage are the primary constraints for the
project of website and mobile application for I-Crop
Scope Management plan
Resources: Analyst, Application Designer, Application Developer, Documenter, Engineer,
Planner, Programmer, Project Manager, Website Designer, and Website Developer
Technology: Design Development, Mobile Application Development, Mobile Application UI
Development, Testing technology, and Website Development
Facilities: UI simulation environment and Testing facility is required for the completion of the
project of website and mobile application for I-Crop
Part Three: Work Breakdown structure
Milestones
WBS Milestone Name Duration Start Finish
1.5 Signing off 0 days Fri 10/12/18 Fri 10/12/18
Assumptions- It has been assumed for the project of website and mobile application for I-Crop
that,
Project would be completed in the estimated time and budget
Uses of the provident development factors can be implied for successful alignment
development
Resources required for the completion of the project would be done cohesively
Constraints- the factors of time, budget, and resource usage are the primary constraints for the
project of website and mobile application for I-Crop
Scope Management plan
Resources: Analyst, Application Designer, Application Developer, Documenter, Engineer,
Planner, Programmer, Project Manager, Website Designer, and Website Developer
Technology: Design Development, Mobile Application Development, Mobile Application UI
Development, Testing technology, and Website Development
Facilities: UI simulation environment and Testing facility is required for the completion of the
project of website and mobile application for I-Crop
Part Three: Work Breakdown structure
Milestones
WBS Milestone Name Duration Start Finish
1.5 Signing off 0 days Fri 10/12/18 Fri 10/12/18
5ICT PROJECT MANAGEMENT
2.5 Approving Complete Plan 0 days Mon 10/29/18 Mon 10/29/18
3.1.5 Approving Website 0 days Tue 11/13/18 Tue 11/13/18
3.2.5 Approving Mobile Application 0 days Wed 11/28/18 Wed 11/28/18
5.5 Closure 0 days Thu 1/31/19 Thu 1/31/19
Activities / Tasks
WBS Task Name
0 I-Crop Project
1 Initial Phase
1.1 Analyzing requirements
1.2 Making Project Charter Documents
1.3 Making Project Initiation Documents
1.4 Submitting documents
1.5 Signing off
2 Planning Phase
2.1 Selecting Plan Methodology
2.2 Making Plan Outline
2.3 Reviewing Plan Outline
2.4 Making Complete Plan
2.5 Approving Complete Plan
2.5 Approving Complete Plan 0 days Mon 10/29/18 Mon 10/29/18
3.1.5 Approving Website 0 days Tue 11/13/18 Tue 11/13/18
3.2.5 Approving Mobile Application 0 days Wed 11/28/18 Wed 11/28/18
5.5 Closure 0 days Thu 1/31/19 Thu 1/31/19
Activities / Tasks
WBS Task Name
0 I-Crop Project
1 Initial Phase
1.1 Analyzing requirements
1.2 Making Project Charter Documents
1.3 Making Project Initiation Documents
1.4 Submitting documents
1.5 Signing off
2 Planning Phase
2.1 Selecting Plan Methodology
2.2 Making Plan Outline
2.3 Reviewing Plan Outline
2.4 Making Complete Plan
2.5 Approving Complete Plan
6ICT PROJECT MANAGEMENT
3 Designing Phase
3.1 Website Designing
3.1.1 Selecting Design Platform
3.1.2 Making Website Outline
3.1.3 Reviewing Website Outline
3.1.4 Making Complete Website
3.1.5 Approving Website
3.2 Mobile Application Designing
3.2.1 Selecting Design Platform
3.2.2 Making Mobile Application Outline
3.2.3 Reviewing Mobile Application Outline
3.2.4 Making Complete Mobile Application
3.2.5 Approving Mobile Application
4 Development Phase
4.1 Website Development
4.1.1 Buying Website Domain
4.1.2 Developing Website Interface
4.1.3 Aligning Functions of Website
4.1.4 Making Programs for Website
4.1.5 Checking Mobile Compatibility
4.1.6 Completion of Website Development
4.2 Mobile Application Development
4.2.1 Developing Application Interface
4.2.2 Making Programs for Mobile Application
4.2.3 Integrating Mobile Applications
3 Designing Phase
3.1 Website Designing
3.1.1 Selecting Design Platform
3.1.2 Making Website Outline
3.1.3 Reviewing Website Outline
3.1.4 Making Complete Website
3.1.5 Approving Website
3.2 Mobile Application Designing
3.2.1 Selecting Design Platform
3.2.2 Making Mobile Application Outline
3.2.3 Reviewing Mobile Application Outline
3.2.4 Making Complete Mobile Application
3.2.5 Approving Mobile Application
4 Development Phase
4.1 Website Development
4.1.1 Buying Website Domain
4.1.2 Developing Website Interface
4.1.3 Aligning Functions of Website
4.1.4 Making Programs for Website
4.1.5 Checking Mobile Compatibility
4.1.6 Completion of Website Development
4.2 Mobile Application Development
4.2.1 Developing Application Interface
4.2.2 Making Programs for Mobile Application
4.2.3 Integrating Mobile Applications
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7ICT PROJECT MANAGEMENT
4.2.4 Completion of Mobile Application Development
5 Closure Phase
5.1 Making Closure Reports
5.2 Making Evaluation Checklist
5.3 Submitting Report Documents
5.4 Signing off
5.5 Closure
Resource Assignments
ID Resource Name Work
1 Analyst 16 hrs
2 Documenter 104 hrs
3 Planner 72 hrs
4 Project Manager 56 hrs
5 Website Designer 72 hrs
6 Application Designer 72 hrs
7 Engineer 72 hrs
8 Website Developer 96 hrs
9 Programmer 72 hrs
10 Application Developer 80 hrs
11 Documents 3
12 Design Tools 4
13 Domain Cost 1
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
T W T M S S F T W T M S
Sep 23, '18 Oct 21, '18 Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19
16h
40h 24h 16h 24h
40h 32h
8h 8h 40h
32h 40h
24h 48h
16h 32h 24h
56h 40h
16h 8h 48h
24h 56h
1.67 0.33 0.67 0.33
1 2 1
1
Estimates for Each Activity / Task
WBS Task Name Resource Names Cost
0 I-Crop Project $80,005.00
1 Initial Phase $4,670.00
1.1 Analyzing requirements Analyst $160.00
1.2 Making Project Charter Documents Documenter, $1,735.00
4.2.4 Completion of Mobile Application Development
5 Closure Phase
5.1 Making Closure Reports
5.2 Making Evaluation Checklist
5.3 Submitting Report Documents
5.4 Signing off
5.5 Closure
Resource Assignments
ID Resource Name Work
1 Analyst 16 hrs
2 Documenter 104 hrs
3 Planner 72 hrs
4 Project Manager 56 hrs
5 Website Designer 72 hrs
6 Application Designer 72 hrs
7 Engineer 72 hrs
8 Website Developer 96 hrs
9 Programmer 72 hrs
10 Application Developer 80 hrs
11 Documents 3
12 Design Tools 4
13 Domain Cost 1
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
T W T M S S F T W T M S
Sep 23, '18 Oct 21, '18 Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19
16h
40h 24h 16h 24h
40h 32h
8h 8h 40h
32h 40h
24h 48h
16h 32h 24h
56h 40h
16h 8h 48h
24h 56h
1.67 0.33 0.67 0.33
1 2 1
1
Estimates for Each Activity / Task
WBS Task Name Resource Names Cost
0 I-Crop Project $80,005.00
1 Initial Phase $4,670.00
1.1 Analyzing requirements Analyst $160.00
1.2 Making Project Charter Documents Documenter, $1,735.00
8ICT PROJECT MANAGEMENT
Documents[1]
1.3 Making Project Initiation Documents Documenter,
Documents[1] $1,735.00
1.4 Submitting documents Documenter $1,040.00
1.5 Signing off $0.00
2 Planning Phase $7,200.00
2.1 Selecting Plan Methodology Planner $1,120.00
2.2 Making Plan Outline Planner $1,680.00
2.3 Reviewing Plan Outline Project Manager $2,160.00
2.4 Making Complete Plan Planner $2,240.00
2.5 Approving Complete Plan $0.00
3 Designing Phase $25,760.00
3.1 Website Designing $12,880.00
3.1.1 Selecting Design Platform Website Designer,
Design Tools[1] $3,400.00
3.1.2 Making Website Outline Website Designer $2,400.00
3.1.3 Reviewing Website Outline Engineer $2,080.00
3.1.4 Making Complete Website Website Designer,
Design Tools[1] $5,000.00
3.1.5 Approving Website $0.00
3.2 Mobile Application Designing $12,880.00
3.2.1 Selecting Design Platform Application Designer,
Design Tools[1] $3,400.00
3.2.2 Making Mobile Application Outline Application Designer $2,400.00
Documents[1]
1.3 Making Project Initiation Documents Documenter,
Documents[1] $1,735.00
1.4 Submitting documents Documenter $1,040.00
1.5 Signing off $0.00
2 Planning Phase $7,200.00
2.1 Selecting Plan Methodology Planner $1,120.00
2.2 Making Plan Outline Planner $1,680.00
2.3 Reviewing Plan Outline Project Manager $2,160.00
2.4 Making Complete Plan Planner $2,240.00
2.5 Approving Complete Plan $0.00
3 Designing Phase $25,760.00
3.1 Website Designing $12,880.00
3.1.1 Selecting Design Platform Website Designer,
Design Tools[1] $3,400.00
3.1.2 Making Website Outline Website Designer $2,400.00
3.1.3 Reviewing Website Outline Engineer $2,080.00
3.1.4 Making Complete Website Website Designer,
Design Tools[1] $5,000.00
3.1.5 Approving Website $0.00
3.2 Mobile Application Designing $12,880.00
3.2.1 Selecting Design Platform Application Designer,
Design Tools[1] $3,400.00
3.2.2 Making Mobile Application Outline Application Designer $2,400.00
9ICT PROJECT MANAGEMENT
3.2.3 Reviewing Mobile Application Outline Engineer $2,080.00
3.2.4 Making Complete Mobile Application Application Designer,
Design Tools[1] $5,000.00
3.2.5 Approving Mobile Application $0.00
4 Development Phase $34,200.00
4.1 Website Development $16,520.00
4.1.1 Buying Website Domain Engineer,
Domain Cost[1] $3,080.00
4.1.2 Developing Website Interface Website Developer $3,520.00
4.1.3 Aligning Functions of Website Website Developer $2,640.00
4.1.4 Making Programs for Website Programmer $2,880.00
4.1.5 Checking Mobile Compatibility Website Developer $1,760.00
4.1.6 Completion of Website Development Website Developer $2,640.00
4.2 Mobile Application Development $17,680.00
4.2.1 Developing Application Interface Application Developer $2,640.00
4.2.2 Making Programs for Mobile Application Programmer $5,760.00
4.2.3 Integrating Mobile Applications Engineer $3,120.00
4.2.4 Completion of Mobile Application
Development Application Developer $6,160.00
5 Closure Phase $8,175.00
5.1 Making Closure Reports Documenter,
Documents[1] $1,735.00
5.2 Making Evaluation Checklist Project Manager $3,240.00
5.3 Submitting Report Documents Documenter $1,040.00
5.4 Signing off Project Manager $2,160.00
5.5 Closure $0.00
3.2.3 Reviewing Mobile Application Outline Engineer $2,080.00
3.2.4 Making Complete Mobile Application Application Designer,
Design Tools[1] $5,000.00
3.2.5 Approving Mobile Application $0.00
4 Development Phase $34,200.00
4.1 Website Development $16,520.00
4.1.1 Buying Website Domain Engineer,
Domain Cost[1] $3,080.00
4.1.2 Developing Website Interface Website Developer $3,520.00
4.1.3 Aligning Functions of Website Website Developer $2,640.00
4.1.4 Making Programs for Website Programmer $2,880.00
4.1.5 Checking Mobile Compatibility Website Developer $1,760.00
4.1.6 Completion of Website Development Website Developer $2,640.00
4.2 Mobile Application Development $17,680.00
4.2.1 Developing Application Interface Application Developer $2,640.00
4.2.2 Making Programs for Mobile Application Programmer $5,760.00
4.2.3 Integrating Mobile Applications Engineer $3,120.00
4.2.4 Completion of Mobile Application
Development Application Developer $6,160.00
5 Closure Phase $8,175.00
5.1 Making Closure Reports Documenter,
Documents[1] $1,735.00
5.2 Making Evaluation Checklist Project Manager $3,240.00
5.3 Submitting Report Documents Documenter $1,040.00
5.4 Signing off Project Manager $2,160.00
5.5 Closure $0.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10ICT PROJECT MANAGEMENT
Project Budget
Resource Name Work Standard Rate Cost
Analyst 16 hrs $10.00/hr $160.00
Documenter 104 hrs $65.00/hr $6,760.00
Planner 72 hrs $70.00/hr $5,040.00
Project Manager 56 hrs $135.00/hr $7,560.00
Website Designer 72 hrs $100.00/hr $7,200.00
Application Designer 72 hrs $100.00/hr $7,200.00
Engineer 72 hrs $130.00/hr $9,360.00
Website Developer 96 hrs $110.00/hr $10,560.00
Programmer 72 hrs $120.00/hr $8,640.00
Application Developer 80 hrs $110.00/hr $8,800.00
Documents 3 $175.00 $525.00
Design Tools 4 $1,800.00 $7,200.00
Domain Cost 1 $1,000.00 $1,000.00
Total Budget $80,005.00
Project Budget
Resource Name Work Standard Rate Cost
Analyst 16 hrs $10.00/hr $160.00
Documenter 104 hrs $65.00/hr $6,760.00
Planner 72 hrs $70.00/hr $5,040.00
Project Manager 56 hrs $135.00/hr $7,560.00
Website Designer 72 hrs $100.00/hr $7,200.00
Application Designer 72 hrs $100.00/hr $7,200.00
Engineer 72 hrs $130.00/hr $9,360.00
Website Developer 96 hrs $110.00/hr $10,560.00
Programmer 72 hrs $120.00/hr $8,640.00
Application Developer 80 hrs $110.00/hr $8,800.00
Documents 3 $175.00 $525.00
Design Tools 4 $1,800.00 $7,200.00
Domain Cost 1 $1,000.00 $1,000.00
Total Budget $80,005.00
11ICT PROJECT MANAGEMENT
Part Four: Risk Management Plan
Assumption made:
Project would be completed in the estimated budget
Uses of the resources have been done considering the alignment of functions.
Resources required for the completion of the project would be done cohesively
Risk Identification
Delay in completion: It is resulted due to the major or minor problems in execution of the
operations of project resulting in untimely completion of the project
Shortage of resources: It is resulted due to the lack of adequate resources in the project or due
to misuses of the resources by the project team
Design flaws: It is resulted due to the flaws in the design of the website and mobile application
that needed to be corrected by the designer
Functional errors: It is the issues in the website and mobile application due to the functions not
working properly or programming errors
Part Four: Risk Management Plan
Assumption made:
Project would be completed in the estimated budget
Uses of the resources have been done considering the alignment of functions.
Resources required for the completion of the project would be done cohesively
Risk Identification
Delay in completion: It is resulted due to the major or minor problems in execution of the
operations of project resulting in untimely completion of the project
Shortage of resources: It is resulted due to the lack of adequate resources in the project or due
to misuses of the resources by the project team
Design flaws: It is resulted due to the flaws in the design of the website and mobile application
that needed to be corrected by the designer
Functional errors: It is the issues in the website and mobile application due to the functions not
working properly or programming errors
12ICT PROJECT MANAGEMENT
Human mistakes: It is the probable mistakes of minor type that is occurred by the project team
members and results in forming issues in completion of the project
Risk Assessment Matrix
Risk Factor Responsible Person Probability
(1-5)
Impact
(1-5)
Rating
Probability*Impact
Delay in completion Project Manager 5 2 10
Shortage of resources HR Manager 3 3 9
Design flaws Designer 2 4 8
Functional errors Engineer 3 5 15
Human mistakes Team Members 4 3 12
Part Five: Verification and Validation Activities
Verification Activities: The identification of the coding requirements, programming platform,
and verification of the effective management.
Validation Activities: The correction of the bugs, go live functions, and phase development
would be helpful for defining the role of successful integration and development.
Part Six: Project Evaluation and closure checklist
Annotated Bibliography
Article: The impact of project management (PM) and benefits management (BM) practices on
project success: Towards developing a project benefits governance framework
Human mistakes: It is the probable mistakes of minor type that is occurred by the project team
members and results in forming issues in completion of the project
Risk Assessment Matrix
Risk Factor Responsible Person Probability
(1-5)
Impact
(1-5)
Rating
Probability*Impact
Delay in completion Project Manager 5 2 10
Shortage of resources HR Manager 3 3 9
Design flaws Designer 2 4 8
Functional errors Engineer 3 5 15
Human mistakes Team Members 4 3 12
Part Five: Verification and Validation Activities
Verification Activities: The identification of the coding requirements, programming platform,
and verification of the effective management.
Validation Activities: The correction of the bugs, go live functions, and phase development
would be helpful for defining the role of successful integration and development.
Part Six: Project Evaluation and closure checklist
Annotated Bibliography
Article: The impact of project management (PM) and benefits management (BM) practices on
project success: Towards developing a project benefits governance framework
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13ICT PROJECT MANAGEMENT
Journal: International Journal of Project Management
Author(s): Badewi, A.
Summary: According to Badewi (2016), the impact of project management and benefit
management practices have been largely deployed for adjusting the analysis of the operations
and defining of the successful management operations. The project management has been
holding considerable role for the evaluation of the existing operations and aligning the imitation
of the effective operations. The evaluation of the methodologies of development and execution
had been largely employed for forming the management of the successive development. The
combination of the practices of development had been implied for listing the management of the
operations and definite increment of the successful project execution. The framework for the
smart alignment model would be helpful for listing the evolution of the project management and
alignment of the smart project execution. The analysis of the functions for benefit management
and project management practices for the completion of the project structural framework.
Article: An empirical study into identifying project complexity management strategies
Journal: Procedia Engineering
Author(s): Kermanshachi, S., Dao, B., Shane, J., and Anderson, S.
Summary: According to Kermanshachi, Dao, Shane & Anderson (2016), the analysis of the
complex project management is a major factor for defining the influence for the development
modelling. The study was conducted for understanding the significance of the factors of project
management and the utilization and development using the innovative and effective project
management. The alignment of the probable management process for the listing of the
Journal: International Journal of Project Management
Author(s): Badewi, A.
Summary: According to Badewi (2016), the impact of project management and benefit
management practices have been largely deployed for adjusting the analysis of the operations
and defining of the successful management operations. The project management has been
holding considerable role for the evaluation of the existing operations and aligning the imitation
of the effective operations. The evaluation of the methodologies of development and execution
had been largely employed for forming the management of the successive development. The
combination of the practices of development had been implied for listing the management of the
operations and definite increment of the successful project execution. The framework for the
smart alignment model would be helpful for listing the evolution of the project management and
alignment of the smart project execution. The analysis of the functions for benefit management
and project management practices for the completion of the project structural framework.
Article: An empirical study into identifying project complexity management strategies
Journal: Procedia Engineering
Author(s): Kermanshachi, S., Dao, B., Shane, J., and Anderson, S.
Summary: According to Kermanshachi, Dao, Shane & Anderson (2016), the analysis of the
complex project management is a major factor for defining the influence for the development
modelling. The study was conducted for understanding the significance of the factors of project
management and the utilization and development using the innovative and effective project
management. The alignment of the probable management process for the listing of the
14ICT PROJECT MANAGEMENT
contemporary management has been helpful for co-ordinating the development of the innovation
and smart project development. The management of the complex projects would be aligned for
implying the renovation development and implication of the innovative technology. The
integration for the successive management would be implied for innovation the prospect of smart
project development. The alignment of the successive introduction management would be
implied for operations. The usefulness of the project integration development would be listed for
aligning with the cohesive management development.
Article: Key factors of sustainability in project management context: A survey exploring the
project managers' perspective
Journal: International Journal of Project Management
Author(s): Martens, M. L., and Carvalho, M. M.
Summary: As stated by Martens and Carvalho (2017), the key factors for the successful
sustainability of the project management operations. The context of project management has
been largely implied for listing the utilization of the smart innovation formation. The
sustainability of the project activities had been largely responsible for innovation of the activities
and integrating the alignment and development. The deployment would be aligned for successful
integration and utilization of the factors for easing the management process. The integration and
implication of the effective project management development would be helpful for innovating
the consideration and development. The exploration of the activities for implying the
management of the operations for the operational development of the operations has been
implied for implying the successful development model. The identification of the key factors for
contemporary management has been helpful for co-ordinating the development of the innovation
and smart project development. The management of the complex projects would be aligned for
implying the renovation development and implication of the innovative technology. The
integration for the successive management would be implied for innovation the prospect of smart
project development. The alignment of the successive introduction management would be
implied for operations. The usefulness of the project integration development would be listed for
aligning with the cohesive management development.
Article: Key factors of sustainability in project management context: A survey exploring the
project managers' perspective
Journal: International Journal of Project Management
Author(s): Martens, M. L., and Carvalho, M. M.
Summary: As stated by Martens and Carvalho (2017), the key factors for the successful
sustainability of the project management operations. The context of project management has
been largely implied for listing the utilization of the smart innovation formation. The
sustainability of the project activities had been largely responsible for innovation of the activities
and integrating the alignment and development. The deployment would be aligned for successful
integration and utilization of the factors for easing the management process. The integration and
implication of the effective project management development would be helpful for innovating
the consideration and development. The exploration of the activities for implying the
management of the operations for the operational development of the operations has been
implied for implying the successful development model. The identification of the key factors for
15ICT PROJECT MANAGEMENT
using the successful integration and management activities was implied for innovation
development.
Closure checklist
The project closure checklist is managed for the involvement of the improved
management and development. The closure checklist would be accordingly developed
considering the innovation and implication management. The following is the closure checklist
for the project,
Checklist Item Checked?
Is the project plan sustainable for the developing mobile application and website?
Have all the initiation documents made successfully for alignment of activities?
Are the outputs of design simulation positive for users?
Is Program Development for the project aligned with the completion plan?
Are the final project report been made cohesively?
Project Evaluation
The evaluation of the project is aligned with the consideration and evaluation of the
factors for integrating the successful innovation and development. The evaluation of the project
integration and management can be implied for integrating the utilization and management
process. The evaluation of the activities had been integrating the management process. The
evaluation of the activities has been largely responsible for aligning management of the
activities. The evaluation factors are,
Project plan sustainable for the developing mobile application and website
using the successful integration and management activities was implied for innovation
development.
Closure checklist
The project closure checklist is managed for the involvement of the improved
management and development. The closure checklist would be accordingly developed
considering the innovation and implication management. The following is the closure checklist
for the project,
Checklist Item Checked?
Is the project plan sustainable for the developing mobile application and website?
Have all the initiation documents made successfully for alignment of activities?
Are the outputs of design simulation positive for users?
Is Program Development for the project aligned with the completion plan?
Are the final project report been made cohesively?
Project Evaluation
The evaluation of the project is aligned with the consideration and evaluation of the
factors for integrating the successful innovation and development. The evaluation of the project
integration and management can be implied for integrating the utilization and management
process. The evaluation of the activities had been integrating the management process. The
evaluation of the activities has been largely responsible for aligning management of the
activities. The evaluation factors are,
Project plan sustainable for the developing mobile application and website
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16ICT PROJECT MANAGEMENT
Initiation documents made successfully for alignment of activities
Outputs of design simulation positive for users
Program development for the project aligned with the completion plan
Final project report been made cohesively
Initiation documents made successfully for alignment of activities
Outputs of design simulation positive for users
Program development for the project aligned with the completion plan
Final project report been made cohesively
17ICT PROJECT MANAGEMENT
Bibliography
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), 761-778.
Binder, J. (2016). Global project management: communication, collaboration and management
across borders. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project
Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Greene, J., & Stellman, A. (2018). Head First PMP: A Learner's Companion to Passing the
Project Management Professional Exam. O'Reilly Media.
Harris, E. (2017). Strategic project risk appraisal and management. Routledge.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kermanshachi, S., Dao, B., Shane, J., & Anderson, S. (2016). An empirical study into identifying
project complexity management strategies. Procedia Engineering, 145, 603-610.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Bibliography
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), 761-778.
Binder, J. (2016). Global project management: communication, collaboration and management
across borders. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project
Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Greene, J., & Stellman, A. (2018). Head First PMP: A Learner's Companion to Passing the
Project Management Professional Exam. O'Reilly Media.
Harris, E. (2017). Strategic project risk appraisal and management. Routledge.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kermanshachi, S., Dao, B., Shane, J., & Anderson, S. (2016). An empirical study into identifying
project complexity management strategies. Procedia Engineering, 145, 603-610.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
18ICT PROJECT MANAGEMENT
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Liu, S. (2016). How the user liaison's understanding of development processes moderates the
effects of user-related and project management risks on IT project
performance. Information & Management, 53(1), 122-134.
Lock, D. (2017). The essentials of project management. Routledge.
Martens, M. L., & Carvalho, M. M. (2017). Key factors of sustainability in project management
context: A survey exploring the project managers' perspective. International Journal of
Project Management, 35(6), 1084-1102.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and
technology. Routledge.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Liu, S. (2016). How the user liaison's understanding of development processes moderates the
effects of user-related and project management risks on IT project
performance. Information & Management, 53(1), 122-134.
Lock, D. (2017). The essentials of project management. Routledge.
Martens, M. L., & Carvalho, M. M. (2017). Key factors of sustainability in project management
context: A survey exploring the project managers' perspective. International Journal of
Project Management, 35(6), 1084-1102.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and
technology. Routledge.
1 out of 19
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.