Restaurant Management System Project Plan
VerifiedAdded on 2020/04/21
|10
|1964
|62
AI Summary
This document outlines a comprehensive project plan for developing a restaurant management system. It details the project phases, including requirements gathering, design, development, testing, implementation, and maintenance. The plan includes cost estimations, resource allocation, risk assessment, and mitigation strategies. The project aims to create an efficient and user-friendly system to manage various restaurant operations.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
HOW TO USE THIS TEMPLATE:
Introduction
The template reflects the steps set out in the PRINCE2 Method and is designed to
prompt the Project Sponsor and Manager to help in the creation of the Business
Case. To use it, follow the prompts (in [...] brackets.
Deleting the [....] text
When the template is complete, the Business Case document can be saved and
submitted via Turnitin. Prior to submission, you should delete all [....] prompt text.
Introduction
The template reflects the steps set out in the PRINCE2 Method and is designed to
prompt the Project Sponsor and Manager to help in the creation of the Business
Case. To use it, follow the prompts (in [...] brackets.
Deleting the [....] text
When the template is complete, the Business Case document can be saved and
submitted via Turnitin. Prior to submission, you should delete all [....] prompt text.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT DOCUMENTATION
BUSINESS CASE
Project:
Release:
Date:
PRINCE2
Author(s):
Owner:
Client:
Document Ref:
Version No:
BUSINESS CASE
Project:
Release:
Date:
PRINCE2
Author(s):
Owner:
Client:
Document Ref:
Version No:
Insert Project Name
Business Case
Date: 15 August 2024
1 Business Case History
1.1 Document Location
This document is only valid on the day it was printed.
The source of the document will be found at this location – [insert folder structure]
1.2 Revision History
Date of this revision:
Date of next revision:
Revision
date
Previous
revision date
Summary of Changes Changes
marked
First issue
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing system.
Name Signature Title Date of
Issue
Version
1.4 Distribution
This document has been distributed to:
Name Title Date of Issue Version
Page 1
Business Case
Date: 15 August 2024
1 Business Case History
1.1 Document Location
This document is only valid on the day it was printed.
The source of the document will be found at this location – [insert folder structure]
1.2 Revision History
Date of this revision:
Date of next revision:
Revision
date
Previous
revision date
Summary of Changes Changes
marked
First issue
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing system.
Name Signature Title Date of
Issue
Version
1.4 Distribution
This document has been distributed to:
Name Title Date of Issue Version
Page 1
Insert Project Name
Business Case
Date: 15 August 2024
2 Table of Contents
Page
1 Business Case History 1
1.1 Document Location 1
1.2 Revision History
1.3 Approvals
1.4 Distribution
2 Table of Contents
3 Executive Summary
4 Reasons
5 Business Options
6 Expected Benefits
7 Expected Dis-benefits
8 Timescales
9 Costs
10 Investment Appraisal
11 Major Risks
12 References
Page 2
Business Case
Date: 15 August 2024
2 Table of Contents
Page
1 Business Case History 1
1.1 Document Location 1
1.2 Revision History
1.3 Approvals
1.4 Distribution
2 Table of Contents
3 Executive Summary
4 Reasons
5 Business Options
6 Expected Benefits
7 Expected Dis-benefits
8 Timescales
9 Costs
10 Investment Appraisal
11 Major Risks
12 References
Page 2
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Insert Project Name
Business Case
Date: 15 August 2024
3 Executive Summary
The paper reflects on the project “international expansion of food and drink delivery
business in a restaurant of UK. The restaurant utilizes telephonic method for taking
orders and they also does not have proper e-commerce website which limits the business
of the restaurant. In order to enhance revenue, the higher authority of the organization
wants to expand their food and drink delivery business in the international market with the
development of e-commerce website. It is identified that with the development of e-
commerce website, the foods as well as drinks of the restaurant are promoted and the
restaurant can also facilitate the online ordering system. In addition to this it is analyzed
that the development of e-commerce website also helps in providing number of other
benefits that includes improving customer convenience, menu management, productivity
as well as online promotion. The project will not only improve as well as expand the food
and drink delivery business but also assists in gaining high ROI.
4 Reasons
The project “international expansion of food and drink delivery business” is
undertaken in order to improve the delivery business of a restaurant in UK. The
restaurant does not have an e-commerce website and thus it takes delivery through
mobile phones and as a result the business of the restaurant is generally limited only to a
small region of area in UK. The higher authorities of the restaurant wants to expand their
business as well as food and drink delivery business in order to enhance the yearly
revenue that will be mainly collected through different Omni sales channel. It is identified
that the development of e-commerce website for online ordering of food can be helpful for
the business of the restaurant in order to grab the international market. In addition to this,
the organization will achieve other benefits that include improving customer convenience,
menu management, productivity as well as online promotion.
5 Business Options
The business option that is available for the business is to do the minimal
approach. According to the approach the project must do the minimal that is generally
required in order to achieve the respective project objectives as well as goals. The project
manager helps in developing the e-commerce website as well as an online ordering
system in order to expand the business of food and drink delivery in the international
market properly. The other needs of the project like proper maintenance, proper
scheduling, proper management as well as budgeting is done in order to achieve
success.
6 Expected Benefits
The expected benefits from the project against the situation that exists prior to the
project are as follows:
Increase number of customers: Due to the project “expansion of food and drink
delivery business” the number of customers of the restaurant increases as the business
covers all the international markets.
Page 3
Business Case
Date: 15 August 2024
3 Executive Summary
The paper reflects on the project “international expansion of food and drink delivery
business in a restaurant of UK. The restaurant utilizes telephonic method for taking
orders and they also does not have proper e-commerce website which limits the business
of the restaurant. In order to enhance revenue, the higher authority of the organization
wants to expand their food and drink delivery business in the international market with the
development of e-commerce website. It is identified that with the development of e-
commerce website, the foods as well as drinks of the restaurant are promoted and the
restaurant can also facilitate the online ordering system. In addition to this it is analyzed
that the development of e-commerce website also helps in providing number of other
benefits that includes improving customer convenience, menu management, productivity
as well as online promotion. The project will not only improve as well as expand the food
and drink delivery business but also assists in gaining high ROI.
4 Reasons
The project “international expansion of food and drink delivery business” is
undertaken in order to improve the delivery business of a restaurant in UK. The
restaurant does not have an e-commerce website and thus it takes delivery through
mobile phones and as a result the business of the restaurant is generally limited only to a
small region of area in UK. The higher authorities of the restaurant wants to expand their
business as well as food and drink delivery business in order to enhance the yearly
revenue that will be mainly collected through different Omni sales channel. It is identified
that the development of e-commerce website for online ordering of food can be helpful for
the business of the restaurant in order to grab the international market. In addition to this,
the organization will achieve other benefits that include improving customer convenience,
menu management, productivity as well as online promotion.
5 Business Options
The business option that is available for the business is to do the minimal
approach. According to the approach the project must do the minimal that is generally
required in order to achieve the respective project objectives as well as goals. The project
manager helps in developing the e-commerce website as well as an online ordering
system in order to expand the business of food and drink delivery in the international
market properly. The other needs of the project like proper maintenance, proper
scheduling, proper management as well as budgeting is done in order to achieve
success.
6 Expected Benefits
The expected benefits from the project against the situation that exists prior to the
project are as follows:
Increase number of customers: Due to the project “expansion of food and drink
delivery business” the number of customers of the restaurant increases as the business
covers all the international markets.
Page 3
Insert Project Name
Business Case
Date: 15 August 2024
Profit: Due to the increase in the number of customers, the entire yearly revenue
of the restaurant increases and as a result the profit that is achieved on the yearly basis
by the restaurant is high.
Expansion: Due to the development of website, the business of the food and
drink delivery expanded and thus more people get attracted to the website.
7 Expected Dis-benefits
The expected dis-benefits of the project are as follows:
Huge investment: The investment that is required in this project is quite high and
therefore the project stakeholders found it risky.
Security issues: The project manager found that development of ecommerce
website can face number of problems including security issues. The misuse of sensitive
as well as confidential information can be hacked and thus proper protection is required.
Management issues: The project managers founds that if project are not
managed properly then number of budget as well as time related issues will occur.
8 Timescale
Task Name Duration Start Finish
Development of e-commerce website for
international expansion of food and drink
delivery business system
60 days Wed 08-
11-17
Tue 30-
01-18
Project planning 22 days Wed 08-
11-17
Thu 07-
12-17
Proper conversation with the team members 5 days Wed 08-
11-17
Tue 14-
11-17
Preparation of project proposal 7 days Wed 15-
11-17
Thu 23-
11-17
Identification of stakeholders 9 days Wed 15-
11-17
Mon 27-
11-17
Project agreement 10 days Fri 24-11-
17
Thu 07-
12-17
Approval of project plan 2 days Tue 28-
11-17
Wed 29-
11-17
Design of web application 21 days Tue 28-
11-17
Tue 26-
12-17
Initial design concepts 12 days Tue 28-
11-17
Wed 13-
12-17
Client review 14 days Tue 28-
11-17
Fri 15-12-
17
Revising design 8 days Fri 08-12-
17
Tue 19-
12-17
Feasibility study of the project 8 days Thu 30-
11-17
Mon 11-
12-17
Financial design 10 days Fri 08-12-
17
Thu 21-
12-17
Project kick off meeting 9 days Thu 14- Tue 26-
Page 4
Business Case
Date: 15 August 2024
Profit: Due to the increase in the number of customers, the entire yearly revenue
of the restaurant increases and as a result the profit that is achieved on the yearly basis
by the restaurant is high.
Expansion: Due to the development of website, the business of the food and
drink delivery expanded and thus more people get attracted to the website.
7 Expected Dis-benefits
The expected dis-benefits of the project are as follows:
Huge investment: The investment that is required in this project is quite high and
therefore the project stakeholders found it risky.
Security issues: The project manager found that development of ecommerce
website can face number of problems including security issues. The misuse of sensitive
as well as confidential information can be hacked and thus proper protection is required.
Management issues: The project managers founds that if project are not
managed properly then number of budget as well as time related issues will occur.
8 Timescale
Task Name Duration Start Finish
Development of e-commerce website for
international expansion of food and drink
delivery business system
60 days Wed 08-
11-17
Tue 30-
01-18
Project planning 22 days Wed 08-
11-17
Thu 07-
12-17
Proper conversation with the team members 5 days Wed 08-
11-17
Tue 14-
11-17
Preparation of project proposal 7 days Wed 15-
11-17
Thu 23-
11-17
Identification of stakeholders 9 days Wed 15-
11-17
Mon 27-
11-17
Project agreement 10 days Fri 24-11-
17
Thu 07-
12-17
Approval of project plan 2 days Tue 28-
11-17
Wed 29-
11-17
Design of web application 21 days Tue 28-
11-17
Tue 26-
12-17
Initial design concepts 12 days Tue 28-
11-17
Wed 13-
12-17
Client review 14 days Tue 28-
11-17
Fri 15-12-
17
Revising design 8 days Fri 08-12-
17
Tue 19-
12-17
Feasibility study of the project 8 days Thu 30-
11-17
Mon 11-
12-17
Financial design 10 days Fri 08-12-
17
Thu 21-
12-17
Project kick off meeting 9 days Thu 14- Tue 26-
Page 4
Insert Project Name
Business Case
Date: 15 August 2024
12-17 12-17
Approval of final design 3 days Mon 18-
12-17
Wed 20-
12-17
Coding 25 days Tue 12-
12-17
Mon 15-
01-18
Construction of prototype 8 days Wed 20-
12-17
Fri 29-12-
17
Database development 15 days Mon 18-
12-17
Fri 05-01-
18
Code validation 17 days Tue 12-
12-17
Wed 03-
01-18
Cross-browser testing 17 days Fri 22-12-
17
Mon 15-
01-18
Optimization 14 days Wed 27-
12-17
Mon 15-
01-18
Web-content build 18 days Thu 21-
12-17
Mon 15-
01-18
Site content pages 18 days Thu 21-
12-17
Mon 15-
01-18
Navigation structure 12 days Thu 21-
12-17
Fri 05-01-
18
User experience 22 days Mon 01-
01-18
Tue 30-
01-18
Project update for login and order 11 days Tue 16-
01-18
Tue 30-
01-18
Project details update 9 days Tue 16-
01-18
Fri 26-01-
18
Display of program presentation 12 days Mon 01-
01-18
Tue 16-
01-18
Project requirement 15 days Mon 01-
01-18
Fri 19-01-
18
Web application accessing 2 days Mon 01-
01-18
Tue 02-
01-18
Estimation of software and hardware needs 8 days Mon 08-
01-18
Wed 17-
01-18
Review and testing 10 days Mon 08-
01-18
Fri 19-01-
18
Project closure 18 days Thu 04-
01-18
Mon 29-
01-18
Risk assessment 11 days Thu 04-
01-18
Thu 18-
01-18
Planning for quality management 10 days Tue 16-
01-18
Mon 29-
01-18
Final review 3 days Tue 16-
01-18
Thu 18-
01-18
9 Costs
Task Name Cost
Page 5
Business Case
Date: 15 August 2024
12-17 12-17
Approval of final design 3 days Mon 18-
12-17
Wed 20-
12-17
Coding 25 days Tue 12-
12-17
Mon 15-
01-18
Construction of prototype 8 days Wed 20-
12-17
Fri 29-12-
17
Database development 15 days Mon 18-
12-17
Fri 05-01-
18
Code validation 17 days Tue 12-
12-17
Wed 03-
01-18
Cross-browser testing 17 days Fri 22-12-
17
Mon 15-
01-18
Optimization 14 days Wed 27-
12-17
Mon 15-
01-18
Web-content build 18 days Thu 21-
12-17
Mon 15-
01-18
Site content pages 18 days Thu 21-
12-17
Mon 15-
01-18
Navigation structure 12 days Thu 21-
12-17
Fri 05-01-
18
User experience 22 days Mon 01-
01-18
Tue 30-
01-18
Project update for login and order 11 days Tue 16-
01-18
Tue 30-
01-18
Project details update 9 days Tue 16-
01-18
Fri 26-01-
18
Display of program presentation 12 days Mon 01-
01-18
Tue 16-
01-18
Project requirement 15 days Mon 01-
01-18
Fri 19-01-
18
Web application accessing 2 days Mon 01-
01-18
Tue 02-
01-18
Estimation of software and hardware needs 8 days Mon 08-
01-18
Wed 17-
01-18
Review and testing 10 days Mon 08-
01-18
Fri 19-01-
18
Project closure 18 days Thu 04-
01-18
Mon 29-
01-18
Risk assessment 11 days Thu 04-
01-18
Thu 18-
01-18
Planning for quality management 10 days Tue 16-
01-18
Mon 29-
01-18
Final review 3 days Tue 16-
01-18
Thu 18-
01-18
9 Costs
Task Name Cost
Page 5
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Insert Project Name
Business Case
Date: 15 August 2024
Development of e-commerce website for
international expansion of food and drink delivery
business system
106,880.00₹
Project planning 16,880.00₹
Proper conversation with the team members 3,600.00₹
Preparation of project proposal 2,800.00₹
Identification of stakeholders 2,880.00₹
Project agreement 6,800.00₹
Approval of project plan 800.00₹
Design of web application 20,080.00₹
Initial design concepts 2,880.00₹
Client review 3,920.00₹
Revising design 2,560.00₹
Feasibility study of the project 3,200.00₹
Financial design 3,200.00₹
Project kick off meeting 3,600.00₹
Approval of final design 720.00₹
Coding 31,200.00₹
Construction of prototype 4,160.00₹
Database development 4,200.00₹
Code validation 8,840.00₹
Cross-browser testing 9,520.00₹
Optimization 4,480.00₹
Web-content build 7,920.00₹
Site content pages 5,040.00₹
Navigation structure 2,880.00₹
User experience 8,520.00₹
Project update for login and order 2,640.00₹
Project details update 2,520.00₹
Display of program presentation 3,360.00₹
Project requirement 11,280.00₹
Web application accessing 480.00₹
Estimation of software and hardware needs 4,800.00₹
Review and testing 6,000.00₹
Project closure 11,000.00₹
Risk assessment 6,600.00₹
Planning for quality management 3,200.00₹
Final review 1,200.00₹
10 Investment Appraisal
The project will be funded by utilizing the method of partnership. T is identified that
partnership is considered as one of the best way for funding a restaurant because
business it helps in making the procedure of investment easier and also assists in
Page 6
Business Case
Date: 15 August 2024
Development of e-commerce website for
international expansion of food and drink delivery
business system
106,880.00₹
Project planning 16,880.00₹
Proper conversation with the team members 3,600.00₹
Preparation of project proposal 2,800.00₹
Identification of stakeholders 2,880.00₹
Project agreement 6,800.00₹
Approval of project plan 800.00₹
Design of web application 20,080.00₹
Initial design concepts 2,880.00₹
Client review 3,920.00₹
Revising design 2,560.00₹
Feasibility study of the project 3,200.00₹
Financial design 3,200.00₹
Project kick off meeting 3,600.00₹
Approval of final design 720.00₹
Coding 31,200.00₹
Construction of prototype 4,160.00₹
Database development 4,200.00₹
Code validation 8,840.00₹
Cross-browser testing 9,520.00₹
Optimization 4,480.00₹
Web-content build 7,920.00₹
Site content pages 5,040.00₹
Navigation structure 2,880.00₹
User experience 8,520.00₹
Project update for login and order 2,640.00₹
Project details update 2,520.00₹
Display of program presentation 3,360.00₹
Project requirement 11,280.00₹
Web application accessing 480.00₹
Estimation of software and hardware needs 4,800.00₹
Review and testing 6,000.00₹
Project closure 11,000.00₹
Risk assessment 6,600.00₹
Planning for quality management 3,200.00₹
Final review 1,200.00₹
10 Investment Appraisal
The project will be funded by utilizing the method of partnership. T is identified that
partnership is considered as one of the best way for funding a restaurant because
business it helps in making the procedure of investment easier and also assists in
Page 6
Insert Project Name
Business Case
Date: 15 August 2024
reducing the risks related with the business by sharing the future loss as well as profit.
The ability of raising the funds will be enhanced as both the partners will contribute in the
business.
11 Major Risks
Risks Cause Consequence Likelihood Mitigation
Improper
estimation of
budget
If the cost of
the project
requirements
are not properly
analyzed then
the budget
estimation may
be incorrect
It may cause
obstruction in
the path of the
project
High The cost of the
project
requirements
must be
analyzed
properly before
budget
estimation
Security
issues
If proper
authentication
and security
measures are
not taken then
security related
issues can
occur
Sensitive data
and information
of the
customers can
be hacked or
misused.
Medium Proper security
measures must
be taken for
avoiding
security related
issues.
Technical
problems
Due to
inaccurate
programming
the data of the
customers are
not properly
gathered in the
database.
The orders of
the customers
are
interchanges
and that can
create huge
problem
Medium The
programming
that is tested
must be tested
properly so that
it does not have
any negative
impact.
Improper time
estimation
If the project
manager are
not
experienced
then they face
difficulty in
assuming the
time-period for
the project
Due to
improper
estimation of
time, the
budget of the
project
enhances
which creates
number of
financial issues
for the
restaurant.
High Experienced
project
managers
should be hired
for the project
so that they can
be able to
estimate the
project time.
12 References
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS
Project. McGraw-Hill.
Lock, M.D., 2014. The essentials of project management. Ashgate Publishing, Ltd..
Page 7
Business Case
Date: 15 August 2024
reducing the risks related with the business by sharing the future loss as well as profit.
The ability of raising the funds will be enhanced as both the partners will contribute in the
business.
11 Major Risks
Risks Cause Consequence Likelihood Mitigation
Improper
estimation of
budget
If the cost of
the project
requirements
are not properly
analyzed then
the budget
estimation may
be incorrect
It may cause
obstruction in
the path of the
project
High The cost of the
project
requirements
must be
analyzed
properly before
budget
estimation
Security
issues
If proper
authentication
and security
measures are
not taken then
security related
issues can
occur
Sensitive data
and information
of the
customers can
be hacked or
misused.
Medium Proper security
measures must
be taken for
avoiding
security related
issues.
Technical
problems
Due to
inaccurate
programming
the data of the
customers are
not properly
gathered in the
database.
The orders of
the customers
are
interchanges
and that can
create huge
problem
Medium The
programming
that is tested
must be tested
properly so that
it does not have
any negative
impact.
Improper time
estimation
If the project
manager are
not
experienced
then they face
difficulty in
assuming the
time-period for
the project
Due to
improper
estimation of
time, the
budget of the
project
enhances
which creates
number of
financial issues
for the
restaurant.
High Experienced
project
managers
should be hired
for the project
so that they can
be able to
estimate the
project time.
12 References
Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS
Project. McGraw-Hill.
Lock, M.D., 2014. The essentials of project management. Ashgate Publishing, Ltd..
Page 7
Insert Project Name
Business Case
Date: 15 August 2024
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O.,
2015. Construction project management. John Wiley & Sons.
Serra, C.E.M. and Kunc, M., 2015. Benefits realisation management and its influence on
project success and on the execution of business strategies. International Journal of
Project Management, 33(1), pp.53-66.
Shields, P.M. and Rangarajan, N., 2013. A playbook for research methods: Integrating
conceptual frameworks and project management. New Forums Press.
Turner, R., 2016. Gower handbook of project management. Routledge.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Page 8
Business Case
Date: 15 August 2024
Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O.,
2015. Construction project management. John Wiley & Sons.
Serra, C.E.M. and Kunc, M., 2015. Benefits realisation management and its influence on
project success and on the execution of business strategies. International Journal of
Project Management, 33(1), pp.53-66.
Shields, P.M. and Rangarajan, N., 2013. A playbook for research methods: Integrating
conceptual frameworks and project management. New Forums Press.
Turner, R., 2016. Gower handbook of project management. Routledge.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Page 8
1 out of 10
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.