This document discusses the relevance of systems thinking to project management, specifically in the context of the Brisbane Airport Parallel Runway project. It explores the objectives of the project, the master plan, and the benefits it will bring to Brisbane and the region. The document also includes mandatory and optional readings, as well as supporting documentation for further study.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
(Insert Student Name) / (Insert Student Number) - PPMP20013 Unit Portfolio for Week 1
Week 1 Topic: Explain the relevance of systems thinking to PM.
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
Project
Development
Procedures;
Download and
study the
1. Review using clear
terminology the
key areas and
processes of
project, program
and portfolio
management
practices as applies
to asset rich
organisations.
There are several fundamental objectives of the Brisbane Airport Parallel
Runway’s master plan. It includes establishment of the strategic direction
of the airport, showing the development for the extra use of the airport
site, setting out the future forecasts of the airport and passenger
increment, plans for specific operations, roads and aviation
infrastructure investment. It even includes the commitment engagement
of community demonstration, update strategy of the Airport
Environment and the Ground Transport Plan.
The new runway of Brisbane is going to be the largest project of aviation
construction in the country Australia. The project is witnesses to have
been started in the year 2012 with a number of major construction levels
and is clearly and well planned for its opening by the year 2020. After the
completion of the project, Brisbane is going to have the system which
will be best for the runway in the world. The new framework or the
structure of the project is responsible for delivering numerous benefits
to Brisbane, Australia and Queensland and will help in continuing with its
benefits soon after the year 2020. Recently, the stakeholder’s
consultation is considered to be underway with the development and
the establishment of different reference groups with numerous
representatives of both the industry and the community. The public
consultation is going to be commenced within the mid of the year 2019.
The final submission draft of the mentioned master plan is to be done
soon to the federal government of Australia by the year 2020. During the
starting or the beginning phase of the construction during the 1980s, a
space was reserved for the development of a parallel runway in the
Coughlan, P., 2016.
Brisbane's
New Parallel
Runway.
Glasby, T., Day, J.,
Genrich, R.
and Aldred,
J., 2015. EFC
geopolymer
concrete
aircraft
pavements at
Brisbane
West
Wellcamp
Airport. Conc
rete, 2015,
pp.1-9.
Tangri, K., 2018.
Planning and
delivering
Brisbane
Airport’s new
runway. Jour
1 of 8
Week 1 Topic: Explain the relevance of systems thinking to PM.
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
Project
Development
Procedures;
Download and
study the
1. Review using clear
terminology the
key areas and
processes of
project, program
and portfolio
management
practices as applies
to asset rich
organisations.
There are several fundamental objectives of the Brisbane Airport Parallel
Runway’s master plan. It includes establishment of the strategic direction
of the airport, showing the development for the extra use of the airport
site, setting out the future forecasts of the airport and passenger
increment, plans for specific operations, roads and aviation
infrastructure investment. It even includes the commitment engagement
of community demonstration, update strategy of the Airport
Environment and the Ground Transport Plan.
The new runway of Brisbane is going to be the largest project of aviation
construction in the country Australia. The project is witnesses to have
been started in the year 2012 with a number of major construction levels
and is clearly and well planned for its opening by the year 2020. After the
completion of the project, Brisbane is going to have the system which
will be best for the runway in the world. The new framework or the
structure of the project is responsible for delivering numerous benefits
to Brisbane, Australia and Queensland and will help in continuing with its
benefits soon after the year 2020. Recently, the stakeholder’s
consultation is considered to be underway with the development and
the establishment of different reference groups with numerous
representatives of both the industry and the community. The public
consultation is going to be commenced within the mid of the year 2019.
The final submission draft of the mentioned master plan is to be done
soon to the federal government of Australia by the year 2020. During the
starting or the beginning phase of the construction during the 1980s, a
space was reserved for the development of a parallel runway in the
Coughlan, P., 2016.
Brisbane's
New Parallel
Runway.
Glasby, T., Day, J.,
Genrich, R.
and Aldred,
J., 2015. EFC
geopolymer
concrete
aircraft
pavements at
Brisbane
West
Wellcamp
Airport. Conc
rete, 2015,
pp.1-9.
Tangri, K., 2018.
Planning and
delivering
Brisbane
Airport’s new
runway. Jour
1 of 8
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
(Insert Student Name) / (Insert Student Number) - PPMP20013 Unit Portfolio for Week 1
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Engineers
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
future by the Australian government whenever needed. This Brisbane
Airport Corporation project has several partners dealing with it including
the contractors of CPB, groups of BMD and the constructors of
McConnell Dowell (Aust.) Pty Ltd to provide the new runway. The project
also comprises of about 675 workers during the peak period along with
90% of them belonging to the south east part of Queensland. The project
is considered to be a well-planned one and is performed in two main
phases. The first phase being the construction phase involves the works
of improvement on the ground, whereas the second phase is the main
construction of the system of runway and the airfield infrastructure. The
master plan of the project is designed properly for stating the objectives
clearly with the help of proper planning thinking about the future of the
Brisbane airport. The master plan of the project is also designed by
defining proper forecasting factor like growth of the passengers, aircraft
movements and the on-transport traffic. The Australian government
approved this master plan in the year 2015. The upcoming new runway
which is going to be developed by the year 2020 is going to create more
than seven thousand new jobs and also contribute an extra $5 billion in
the benefit of the economy of the region yearly. This particular project
also leads to a larger choice in the airlines, flight times and destinations.
The runway is also going to be such a beautiful infrastructure allowing
the increasing growth of Brisbane and the region of it. It will enable the
Brisbane airport for meeting the demands of the community which
serves for now and generations in future.
According to the case study, there are several standards of Australia with
the tendering code. The standards are scope, definition and ethics. The
scope standard mainly sets out all kinds of ethics and obligations of both
tenderers and principal during tendering in the construction industry.
The standard of application is equally applied upon the contractors,
nal of Airport
Management,
12(2),
pp.169-185.
2 of 8
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Engineers
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
future by the Australian government whenever needed. This Brisbane
Airport Corporation project has several partners dealing with it including
the contractors of CPB, groups of BMD and the constructors of
McConnell Dowell (Aust.) Pty Ltd to provide the new runway. The project
also comprises of about 675 workers during the peak period along with
90% of them belonging to the south east part of Queensland. The project
is considered to be a well-planned one and is performed in two main
phases. The first phase being the construction phase involves the works
of improvement on the ground, whereas the second phase is the main
construction of the system of runway and the airfield infrastructure. The
master plan of the project is designed properly for stating the objectives
clearly with the help of proper planning thinking about the future of the
Brisbane airport. The master plan of the project is also designed by
defining proper forecasting factor like growth of the passengers, aircraft
movements and the on-transport traffic. The Australian government
approved this master plan in the year 2015. The upcoming new runway
which is going to be developed by the year 2020 is going to create more
than seven thousand new jobs and also contribute an extra $5 billion in
the benefit of the economy of the region yearly. This particular project
also leads to a larger choice in the airlines, flight times and destinations.
The runway is also going to be such a beautiful infrastructure allowing
the increasing growth of Brisbane and the region of it. It will enable the
Brisbane airport for meeting the demands of the community which
serves for now and generations in future.
According to the case study, there are several standards of Australia with
the tendering code. The standards are scope, definition and ethics. The
scope standard mainly sets out all kinds of ethics and obligations of both
tenderers and principal during tendering in the construction industry.
The standard of application is equally applied upon the contractors,
nal of Airport
Management,
12(2),
pp.169-185.
2 of 8
(Insert Student Name) / (Insert Student Number) - PPMP20013 Unit Portfolio for Week 1
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
principals, suppliers as well as the professional organizations.
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
Project
Development
Procedures;
Download and
study the
Engineers
2. Discuss the
relevance of tools
and techniques for
investigating and
describing project
process related to
developing new
workings, facilities,
equipment, plant
and processes for
justifying,
designing,
developing, or
maintaining
existing facilities
and equipment
within the context
of their
technological and
asset lifecycle
status.
The objective of this week’s topic [Week 1: Define project management for
operators of mines, plants and owners of large assets] is to make sure you have
a broad understanding of
The unit’s fundamental objectives;
Projects and Project Management, particularly as applied to a project like
the Brisbane Airport Parallel Runway;
Value Management, particularly as applied to a project like the Brisbane
Airport Parallel Runway;
Other perspectives such as how major organisations like the Australia
National Audit Office, undertake planning and approving of projects;
The contents of AS 4120-1994 Code of tendering.
Note: some of these readings are quite long. You are not expected to read
everything, rather to gain an overview and be able to reflect on the material and
case study using your own thoughts.
In this portfolio please reflect on the readings (1st column) and the learning
outcome (2nd column). Ask yourself in what way does the readings provide
insights into the learning outcome? Maybe they don’t! What are your
thoughts?
Are there other insights that you can make from other units that you have
studied? Or your work and life experience?
PPMP20013 Unit Profile
PPMP20013 Moodle
Web site
Have you any insights
you can add from other
units you have studies or
readings you’ve made?
3 of 8
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
principals, suppliers as well as the professional organizations.
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
Project
Development
Procedures;
Download and
study the
Engineers
2. Discuss the
relevance of tools
and techniques for
investigating and
describing project
process related to
developing new
workings, facilities,
equipment, plant
and processes for
justifying,
designing,
developing, or
maintaining
existing facilities
and equipment
within the context
of their
technological and
asset lifecycle
status.
The objective of this week’s topic [Week 1: Define project management for
operators of mines, plants and owners of large assets] is to make sure you have
a broad understanding of
The unit’s fundamental objectives;
Projects and Project Management, particularly as applied to a project like
the Brisbane Airport Parallel Runway;
Value Management, particularly as applied to a project like the Brisbane
Airport Parallel Runway;
Other perspectives such as how major organisations like the Australia
National Audit Office, undertake planning and approving of projects;
The contents of AS 4120-1994 Code of tendering.
Note: some of these readings are quite long. You are not expected to read
everything, rather to gain an overview and be able to reflect on the material and
case study using your own thoughts.
In this portfolio please reflect on the readings (1st column) and the learning
outcome (2nd column). Ask yourself in what way does the readings provide
insights into the learning outcome? Maybe they don’t! What are your
thoughts?
Are there other insights that you can make from other units that you have
studied? Or your work and life experience?
PPMP20013 Unit Profile
PPMP20013 Moodle
Web site
Have you any insights
you can add from other
units you have studies or
readings you’ve made?
3 of 8
(Insert Student Name) / (Insert Student Number) - PPMP20013 Unit Portfolio for Week 1
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
3. Present and
interpret major
processes that are
based on sound
policy, information,
and research that
enable project
justification,
tenders, contracts,
and selection
criteria to occur in
an asset rich
organisation.
The objective of this week’s topic [Week 1: Define project management for
operators of mines, plants and owners of large assets] is to make sure you have
a broad understanding of
The unit’s fundamental objectives;
Projects and Project Management, particularly as applied to a project like
the Brisbane Airport Parallel Runway;
Value Management, particularly as applied to a project like the Brisbane
Airport Parallel Runway;
Other perspectives such as how major organisations like the Australia
National Audit Office, undertake planning and approving of projects;
The contents of AS 4120-1994 Code of tendering.
Note: some of these readings are quite long. You are not expected to read
everything, rather to gain an overview and be able to reflect on the material and
case study using your own thoughts.
PPMP20013 Unit Profile
PPMP20013 Moodle
Web site
Have you any insights
you can add from other
units you have studies or
readings you’ve made?
4 of 8
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
3. Present and
interpret major
processes that are
based on sound
policy, information,
and research that
enable project
justification,
tenders, contracts,
and selection
criteria to occur in
an asset rich
organisation.
The objective of this week’s topic [Week 1: Define project management for
operators of mines, plants and owners of large assets] is to make sure you have
a broad understanding of
The unit’s fundamental objectives;
Projects and Project Management, particularly as applied to a project like
the Brisbane Airport Parallel Runway;
Value Management, particularly as applied to a project like the Brisbane
Airport Parallel Runway;
Other perspectives such as how major organisations like the Australia
National Audit Office, undertake planning and approving of projects;
The contents of AS 4120-1994 Code of tendering.
Note: some of these readings are quite long. You are not expected to read
everything, rather to gain an overview and be able to reflect on the material and
case study using your own thoughts.
PPMP20013 Unit Profile
PPMP20013 Moodle
Web site
Have you any insights
you can add from other
units you have studies or
readings you’ve made?
4 of 8
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
(Insert Student Name) / (Insert Student Number) - PPMP20013 Unit Portfolio for Week 1
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
Project
Development
Procedures;
Download and
study the
Engineers
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
In this portfolio please reflect on the readings (1st column) and the learning
outcome (2nd column). Ask yourself in what way does the readings provide
insights into the learning outcome? Maybe they don’t! What are your
thoughts?
Are there other insights that you can make from other units that you have
studied? Or your work and life experience?
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
4. Critically analyse
management
strategies and
operational
The objective of this week’s topic [Week 1: Define project management for
operators of mines, plants and owners of large assets] is to make sure you have
a broad understanding of
The unit’s fundamental objectives;
PPMP20013 Unit Profile
PPMP20013 Moodle
Web site
Have you any insights
5 of 8
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
Project
Development
Procedures;
Download and
study the
Engineers
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
In this portfolio please reflect on the readings (1st column) and the learning
outcome (2nd column). Ask yourself in what way does the readings provide
insights into the learning outcome? Maybe they don’t! What are your
thoughts?
Are there other insights that you can make from other units that you have
studied? Or your work and life experience?
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
4. Critically analyse
management
strategies and
operational
The objective of this week’s topic [Week 1: Define project management for
operators of mines, plants and owners of large assets] is to make sure you have
a broad understanding of
The unit’s fundamental objectives;
PPMP20013 Unit Profile
PPMP20013 Moodle
Web site
Have you any insights
5 of 8
(Insert Student Name) / (Insert Student Number) - PPMP20013 Unit Portfolio for Week 1
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
Project
Development
Procedures;
Download and
study the
Engineers
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
activities from a
broad perspective
to ensure safety
and quality, to
avoid overruns or
rework, to manage
variations and
claims, and to make
decisions to
discontinue or
close projects.
Projects and Project Management, particularly as applied to a project like
the Brisbane Airport Parallel Runway;
Value Management, particularly as applied to a project like the Brisbane
Airport Parallel Runway;
Other perspectives such as how major organisations like the Australia
National Audit Office, undertake planning and approving of projects;
The contents of AS 4120-1994 Code of tendering.
Note: some of these readings are quite long. You are not expected to read
everything, rather to gain an overview and be able to reflect on the material and
case study using your own thoughts.
In this portfolio please reflect on the readings (1st column) and the learning
outcome (2nd column). Ask yourself in what way does the readings provide
insights into the learning outcome? Maybe they don’t! What are your
thoughts?
Are there other insights that you can make from other units that you have
studied? Or your work and life experience?
you can add from other
units you have studies or
readings you’ve made?
6 of 8
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
Project
Development
Procedures;
Download and
study the
Engineers
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
activities from a
broad perspective
to ensure safety
and quality, to
avoid overruns or
rework, to manage
variations and
claims, and to make
decisions to
discontinue or
close projects.
Projects and Project Management, particularly as applied to a project like
the Brisbane Airport Parallel Runway;
Value Management, particularly as applied to a project like the Brisbane
Airport Parallel Runway;
Other perspectives such as how major organisations like the Australia
National Audit Office, undertake planning and approving of projects;
The contents of AS 4120-1994 Code of tendering.
Note: some of these readings are quite long. You are not expected to read
everything, rather to gain an overview and be able to reflect on the material and
case study using your own thoughts.
In this portfolio please reflect on the readings (1st column) and the learning
outcome (2nd column). Ask yourself in what way does the readings provide
insights into the learning outcome? Maybe they don’t! What are your
thoughts?
Are there other insights that you can make from other units that you have
studied? Or your work and life experience?
you can add from other
units you have studies or
readings you’ve made?
6 of 8
(Insert Student Name) / (Insert Student Number) - PPMP20013 Unit Portfolio for Week 1
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
5. Demonstrate an
effective,
professional level
of teamwork and
communication and
support
collaborative peer
group learning.
The objective of this week’s topic [Week 1: Define project management for
operators of mines, plants and owners of large assets] is to make sure you have
a broad understanding of
The unit’s fundamental objectives;
Projects and Project Management, particularly as applied to a project like
the Brisbane Airport Parallel Runway;
Value Management, particularly as applied to a project like the Brisbane
Airport Parallel Runway;
Other perspectives such as how major organisations like the Australia
National Audit Office, undertake planning and approving of projects;
The contents of AS 4120-1994 Code of tendering.
Note: some of these readings are quite long. You are not expected to read
everything, rather to gain an overview and be able to reflect on the material and
case study using your own thoughts.
In this portfolio please reflect on the readings (1st column) and the learning
outcome (2nd column). Ask yourself in what way does the readings provide
insights into the learning outcome? Maybe they don’t! What are your
thoughts?
Are there other insights that you can make from other units that you have
studied? Or your work and life experience?
PPMP20013 Unit Profile
PPMP20013 Moodle
Web site
Have you any insights
you can add from other
units you have studies or
readings you’ve made?
7 of 8
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
Mandatory Readings
Smith Chapters 1
& 2;
Australia National
Audit Office -
Planning and
Approving
Projects
AS 4120-1994
Code of tendering;
Optional Readings
Locate your
company internal
Project
Development
Manuals (if it
exists and
available);
You can also study
the Californian
Government
Department of
Transportation
5. Demonstrate an
effective,
professional level
of teamwork and
communication and
support
collaborative peer
group learning.
The objective of this week’s topic [Week 1: Define project management for
operators of mines, plants and owners of large assets] is to make sure you have
a broad understanding of
The unit’s fundamental objectives;
Projects and Project Management, particularly as applied to a project like
the Brisbane Airport Parallel Runway;
Value Management, particularly as applied to a project like the Brisbane
Airport Parallel Runway;
Other perspectives such as how major organisations like the Australia
National Audit Office, undertake planning and approving of projects;
The contents of AS 4120-1994 Code of tendering.
Note: some of these readings are quite long. You are not expected to read
everything, rather to gain an overview and be able to reflect on the material and
case study using your own thoughts.
In this portfolio please reflect on the readings (1st column) and the learning
outcome (2nd column). Ask yourself in what way does the readings provide
insights into the learning outcome? Maybe they don’t! What are your
thoughts?
Are there other insights that you can make from other units that you have
studied? Or your work and life experience?
PPMP20013 Unit Profile
PPMP20013 Moodle
Web site
Have you any insights
you can add from other
units you have studies or
readings you’ve made?
7 of 8
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
(Insert Student Name) / (Insert Student Number) - PPMP20013 Unit Portfolio for Week 1
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Project
Development
Procedures;
Download and
study the
Engineers
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
References
8 of 8
Reading samples Learning
outcomes of the
unit
Learnings from your weekly study, experience, this and
prior unit readings and assignments
Supporting
documentation
including any
prior learning
Project
Development
Procedures;
Download and
study the
Engineers
Australia
Infrastructure
Report Card for
your State;
Case Study
Brisbane Airport's
New Parallel
Runway;
YouTube:
Brisbane's New
Parallel Runway –
Overview;
Brisbane Airport
2014 Approved
Master Plan.
References
8 of 8
1 out of 8
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.