Integrated Management Report: Refurbishment Programme of Riverside Shopping Mall
Verified
Added on 2022/12/28
|16
|3164
|41
AI Summary
This report undertakes project management activities related to refurbishment programme of Riverside Shopping Mall. Tasks identified are related to Riverside Multi-Storey Car Park, Riverside NHS Practice, and resource management and smoothing of security and surveillance environments CCTV.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Integrated management report 1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Executive Summary This report undertakes project management activities related to refurbishment programme of RiversideShoppingMall. In thereport, threeprojecttaskshavebeen identifiedand information out of them have been analysed to make recommendations in accordance with the operationalorprojectmanagementperformancerequired.Tasksidentifiedarerelatedto Riverside Multi-Storey Car Park for which planning and critical path analysis has been drawn, Riverside NHS Practice for which planning, budgets and optimisation have been taken care of and finally resource management and smoothing of security and surveillance environments CCTV has been undertaken. 2
Table of Contents Executive Summary.........................................................................................................................2 Introduction......................................................................................................................................4 Main Body.......................................................................................................................................4 Project Task 1: Planning and Critical Path Analysis Riverside Multi-Storey Car Park.........4 Project Task 2: Planning, Budgets and Optimisation Riverside NHS Practice and Walk-in Centre.....................................................................................................................................7 ProjectTask3:ResourcemanagementandsmoothingSecurityandSurveillance Environments CCTV............................................................................................................12 Conclusion.....................................................................................................................................15 References......................................................................................................................................16 3
Introduction Project management is undertaking all the activities that are related to managing a project (Heldman, 2018). In this report, projects related to Riverside Shopping Mall are considered. Mall is undergoing a refurbishment programme and context provided is that management of mall and several other current and prospective tenants are looking for related consultancy. Three projects have been undertaken and various planning and operational activities have been considered to draw up conclusions, that can form basis of the project being considered for management. Main Body Project Task 1: Planning and Critical Path Analysis Riverside Multi-Storey Car Park Task Scenario:A new multi-storey car park is being considered to be constructed in order to meet the demand of additional on-site parking from car users. Said new multi-storey car park will be constructed as the part of the current ground level car park, with a new covered link into the centre. 1. Network diagram Network diagram is a tool that is used to map out the schedule and work sequence for the project being undertaken as well as enable tracking its progress through each stage from beginning up to and including completion(Kerzner, 2018). In the multi-storey car park project, it can be illustrated that in the early feasibility study, a sequence of the tasks to complete the project has been drawn which bifurcates the task into fifteen steps that starts from site clearance and set-up to completion. Below mentioned is the related network diagram of the project: 4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
2. Critical path and planned duration of the project Critical path refers to that longest sequence of tasks that is necessary to be completed in order to successfully conclude a project from start to finish(Kerzner, 2019). Based on the sequencing provided of the project, below mentioned is the critical path of the multi-storey car drive project: Project duration refers to the total time taken to compete a project. It is measured in either working period like working days, working hours or work weeks.Below mentioned is the calculation of project duration according to the working days in the project sequence mentioned: 5
3. Gantt Chart Gantt chart is a project management tool that is aimed at assisting in planning and scheduling of project(Nicholas and Steyn, 2017). It is used to simplify complex project planning activities sequence. Below mentioned is the Gantt chart for the multi-story car drive project. 4. Initial Project Budget Project budget refers to the statement that combines costs of all activities, tasks and milestones that the project is required to fulfil(Meredith and et. al., 2020). In other words, it contains information about total amount of money or finances required to finish the project. It must be in agreement with all the stakeholders of the project. However, this is always a risk of the unknown. Therefore, to set aside an emergency fund is a good idea. In the car park project, a contingency risk of 5% is taken to account for the unexpected delays or intermediate changes in 6
theprojectwhichrequiresbudgetrevisions.Leasttheprojectteamrequirestotakeup contingency reserve, more successful the project will be known as. Initial Budget (Riverside Multi-Storey Car Park) Capital Cost£675,000 Other Cost: Project Management team (£5750 per week) =5750*34 £195,500 Piling and concrete rig hire (£75000 per week) = 75000*4 £300,000 Road Paving Machine Hire (£15000 per week) =15000*4 £60,000 Piling rig crew (£900 per day) =900*5*4 £18,000 Road Paving crew (£500 per day) =500*5*4 £10,000 Total other costs£583,500 Estimated Project cost£1,258,500 Project contingency @5%£62,925 Total project cost£1,321,425 Project Task 2: Planning, Budgets and Optimisation Riverside NHS Practice and Walk-in Centre Task scenario: The present building of the Riverside NHS Practice is currently based in a very old building which is dilapidated and not to fit to use anymore. Therefore, practice wants to move into one of the larger units in Riverside mall. In addition, practice manager wants to install a new Patient Record System (PRS) which would require an IT project. This project would require to undertake analysis, designing and implementation of a new system. For it, a budget of £100,000 maximum has been approved. In a discussion with concerned people, it was decided 7
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
that purchase of customised off-the-shelf package solution would be best approach. Rather than going the way of inviting the quotes, practice manager decided to buy the hardware from suppliers themselves and undertake development work using a small team of developers by themselves according to a project plan drawn up by Head of IT at the practice. 1. Calculation of cost under initial project plan In the initial project plan drawn up, the project was divided into eleven tasks which ranged from one week taken up to decide requirement definition to 6 weeks taken up for application configuration. It is considered that team of developers would be paid according to the number of days they have worked(Padalkar and Gopinath, 2016). Below mentioned is the network diagram and Gantt chart for the initial project plan to understand the project planning and sequencing. 8
From the above activity chart, it can be seen that working days under initial project planning is going up to 120 days which comes to more than 17 weeks (17.14 weeks ~ 18 weeks in working). Further, below mentioned is the statement of cost under initial project planning: Statement of cost Patient Record System, Riverside NHS Practice ParticularsCost per weekTotal weeksAmount (in £) Fixed cost of PRS package34,500 Fixed cost of hardware upgrade6,000 Cost of IT manpower5,0001890,000 9
Total130,500 2. Calculation of revised project duration and cost statement Board members have provided budget for£100,000 and in order to avoid incurring extra maintenance cost wanted the project to be completed within 12 weeks. However, it can be seen from above statement of forecasted cost that it surpasses the budget provided of£100,000 and the project duration is crossing 17 weeks. Therefore, it becomes mandatory to revisit the project plan and determine the options that are capable of saving either time, money or both. Certain options were considered to re-design the project plan with an aim to either save cost or decrease activity time and the following options were finalised to be taken up. OptionDetailsCost changesTime saving A Creation of simpler user guide and system referencemanualwhilefulfilling documentation. No cost savingTime saving of 2 weeks on Task 10 BHiring of a specialist consultant to help with the configuration work. Extrafixed cost of £5,500 Time saving of 3 weeks on Task 3 C Thesystemtobeconstructedasa standalone system without the benefit of an internet connection. Savingof £3,800. No time saving D Second hand desktopcomputersfroma localschooltobeusedinsteadofthe hardware upgrades specified by the PRS supplier. Savingof £5,000 Timesavingofone week on Task 6 There was one more option of performing works of Task 8 as over-timing, out of normal working hours which would have incurred extra cost of £2,500 but would had been able to save one-week time in return. However, in this option cost incurred outweighs the benefits therefore, it has not been considered(Kerzner, 2017). Based on the above developments, revised project plan, project duration and statement of cost is drawn up below: IDTaskDuration (weeks)Predecessor/s 1Requirements definition1w- 2Systems analysis2w1 3Application configuration3w2 4User workshops2w3 5Unit testing2w2 6Hardware upgrades2w5 7Data migration1w5 8Integration work2w4,6,7 10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
9System testing/handover1w8 10Documentation2w1 11Project completion0d9,10 It can be seen further that revised project duration comes to 90 days which still exceeds period of 12 weeks by six days making the revised project period 13 weeks of working. However, in the revised duration, project would be able to be completed by August as desired by board members. Below mentioned is the revised statement of forecasted cost based on revised project duration. Statement of cost Patient Record System, Riverside NHS Practice ParticularsCost per weekTotal weeksAmount (in £) Fixed cost of PRS package34,500 Fixed cost of hardware upgrade6,000 Fixed cost of specialist consultant5,500 Cost of IT manpower5,0001365,000 11
Total cost incurred111,000 Less: Cost saved on constructing standalone system (3,800) Less: Cost saved on using second-hand desktop computers (5,000) Total101,700 After carrying out the suggested modifications in the cost statement, it can be observed that overall cost has been reduced from earlier but still the project fails to be carried out under £100,000 and exceeds the budgeted cost by £1,700. Hence, it can be concluded that project cannot be completed under the budget of £100,000 in 12 weeks(Cicmil and et. al., 2017). Project Task 3: Resource management and smoothing Security and Surveillance Environments CCTV Task scenario:Upgradation of CCTV surveillance and security system is another project that has been decided to be undertaken as part of refurbishment of Riverside Mall. This project has been allocated to the Security and Surveillance Environments (SSE) company under the tender process. In the tender submitted, company has submitted Gantt chart which had supposed delivery of project at the end of the 13thweek. It had divided the project in 7 tasks which were to be performed by different engineers in the number as shown below: However, as the company was preparing to start work, two engineers got injured and were not expected to return in the planned project period. This left the company with maximum five engineers available for the Riverside project. 12
1.Planned resource requirement by means of resource histogram Above histogram illustrates the allocation of human resource i.e. engineers as proposed under the initial tendor submitted. An immediate analysis shows a frequent variance in the quantity of engineers required throughout the duration of the project, which may have a negative impact on the project, as frequently changing levels of staff on a project may discourage productivity and commitment. Moreover, due to unfortunate incident of injury of two engineers, company would be facing shortage of resources in completing the project on time and as per the cost structure determined. One option in front of company is that it hires extra engineers for the project temporarily but it would unncessarily increase the cost for the company which is assumed that it wants to avoid. Therefore, for the project which requires maximum of 9 engineers at a time in week 3 as determined in histogram, company has to undergo the project with only 5 engineers available. This render previous Gantt chart not useful and require re-scheduling of project plan in accordance with the resources available(Lientz and Rea, 2016). 2.Re-scheduled CCTV project According to the original plan, Go-live task has to be launched at the end of 13thweek which requires maximum of 9 engineers at the peak of the project work. However, since only 5 engineers are available at maximum, project activities have to be revised. Now, unlike earlier, activities cannot be started together and will have to follow each other as per the availability of 13
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
the resources. For example, activity of system control module has to be launched first and requires availability of 3 engineers for 9 weeks which leaves only 2 engineers behind to take up other activities. External control module requires availability of 2 engineers for 3 weeks. Therefore, it can be taken up together with the air control module. But, with no engineers left behind, no more activities can be taken up. It means that internal surveillance module which was originally planned to be started in 2nd week for next 4 weeks and passive detection module which was slated to be started in 3rdweek for next 4 weeks cannot be started as planned originally as both of them also requires 2 engineers each. Now, in the present condition, internal surveillance module can be taken up post completion of external tracking module and passive detection module can only be taken up post completion of internal surveillance module. But this would shift project plan further by 2 weeks and now go-live activity can only be taken at the end of 15thweek. However, if the company hires or is provided with four more engineers, time and cost of these two weeks can be saved(Teslia and et. al., 2016). Below mentioned is the resources planning under the revised situation: Below mentioned is the Gantt chart under the revised situation which shows that project can only Go-live at the end of 13thweek and the extra cost and time incurred can be saved by employing extra resources: 3.Revised dates for system testing Company planned to start the project in January and have to make things work with only 5 engineers. Therefore, it needs to make Task NameStarting dateFinishing date System Control Module11-Jan12-Mar 14
External Tracking module11-Jan29-Jan Internal Surveillance Module01-Feb26-Feb Passive detection module01-Mar26-Mar Communication module29-Mar16-Apr System Testing19-Apr23-Apr Go-live26-Apr-- According to the above table, project is expected to be completed by 16thApril. Client can track system from 19thApril to 23rdApril and will therefore be able to Go-live on 26thApril. EngineersStarting dateFinishing date 5 engineers11-Jan12-Mar 4 engineers29-Mar16-Apr 3 engineers19-Apr23-Apr 2 engineers15-Mar26-Mar From the above table, it can be observed that five engineers worked only for 9 weeks, four engineers only for 3 weeks, three engineers for 1 week only and two engineers for 2 weeks only, out of the total project period of 15 weeks. This shows that there have almost 6 weeks when resources were not being optimally utilised. Since, this is also an option that if company hires additional engineers for the lag period as per the original project plan, it will be able to save both additional time and additional cost of two extra weeks (Martínez-Rojas, Marín and Vila, 2016). Conclusion From the report above, it can be deduced that planning, budgeting, resource management and other operational activities are connected and required to be performed properly to draw up accurate recommendations that can become basis of conducting and completing underlined project.Recommendationsrelatedtovariousoperationalactivitiesperformedhavebeen provided in the report with an aim to increase profitability of the client seeking consultation for the said project being under management. 15
References Books and Journal Cicmil, S. and et. al., 2017, April. Exploring the complexity of projects: Implications of complexity theory for project management practice. Project Management Institute. Heldman, K., 2018.Project management jumpstart. John Wiley & Sons. Kerzner, H., 2017.Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons. Kerzner, H., 2018.Project management best practices: Achieving global excellence. John Wiley & Sons. Kerzner, H., 2019.Using the project management maturity model: strategic planning for project management. John Wiley & Sons. Lientz, B. and Rea, K., 2016.Breakthrough technology project management. Routledge. Martínez-Rojas, M., Marín, N. and Vila, M.A., 2016. The role of information technologies to address data handling in construction project management. Journal of Computing in Civil Engineering. 30(4). p.04015064. Meredith, J.R. and et. al., 2020.Project management in practice. John Wiley & Sons. Nicholas,J.M.andSteyn,H.,2017.Projectmanagementforengineering,businessand technology. Taylor & Francis. Padalkar, M. and Gopinath, S., 2016. Six decades of project management research: Thematic trends and future opportunities.International Journal of Project Management.34(7) pp.1305-1321. Teslia, Y. and et. al., 2016, August. Control of informational Impacts on project management. In2016 IEEE First International Conference on Data Stream Mining & Processing (DSMP)(pp. 387-391). IEEE. 16