Kimble Building Bachelors Walk, Dundalk, Co Louth. A91 P8Y4 O’Hanlon International Ltd. Preliminary Safety & Health Plan Ref: NMH/300100 Date: 30thOctober 2018 Niall McHugh D00187344
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
O’Hanlon International Ltd., Kimble Building, Bachelors Walk, Dundalk. TABLE OF CONTENTS PREFACE..........................................................................................................................1 PROJECT TEAM..............................................................................................................2 1.GENERAL DESCRIPTION OF PROJECT.........................................................22 1.1 PROJECT DESCRIPTION.................................................................................22 1.2 SITE LOCATION...............................................................................................22 1.3 APPOINTMENT OF PROJECT SUPERVISOR FOR THE CONSTRUCTION STAGE (PSCS)..............................................................................................................23 1.4 ESTIMATED TIMESCALE/ PHASING OF PROJECT....................................23 1.5 THE PROJECT SAFETY & HEALTH PRINCIPLES.......................................24 1.6 MONITORING & REVIEW OF SAFETY.........................................................24 1.7 DRAWINGS / SPECIFICATIONS.....................................................................24 1.8 EXISTING SAFETY FILE / EXISTING RECORDS........................................24 2. INFORMATION REGARDING THE PROPOSED SITE.....................................24 2.1 RELEVANT ADJOINING LAND USES...........................................................24 2.2 RESTRICTIONS ON WORKING HOURS.......................................................24 2.3 Noise/Dust /Vibration..........................................................................................25 2.4 SITE RESTRICTIONS AND RESTRICTIONS ON ACCESS..........................25 2.5 Method Statements..............................................................................................25 2.6 OTHER WORK ACTIVITIES NEARBY..........................................................25 2.7 EXISTING SITE ACTIVITIES..........................................................................25 2.8 KNOWN EXISTING SERVICES.......................................................................25 2.9 LOCAL EMERGENCY PROCEDURES...........................................................26 2.10 LOCATION OF WELFARE FACILITIES – CONNECTIONS FOR WATER, ELECTRICITY, SEWER..............................................................................................26 2.11 ANY PARTICULAR SITE RULES.................................................................26
O’Hanlon International Ltd., Kimble Building, Bachelors Walk, Dundalk. 3. PARTICULAR RISKS................................................................................................26 3.1 THER HAZARDS / RISKS.................................................................................29 4. CONTINUING LIAISON...........................................................................................29 4.1 PROCEDURES REQUIRED DURING THE CONSTRUCTION PERIOD.....30 5. RELEVANT PRELIMINARY TRAFFIC MANAGEMENT PLAN.....................30 6. THE SAFETY FILE....................................................................................................30 6.1 ARRANGEMENTS FOR GATHERING INFORMATION FOR THE SAFETY FILE30 6.2 CONTENTS OF THE SAFETY FILE................................................................30 7. COMPLIANCE WITH GENERAL SAFETY REQUIREMENTS........................31 8. FINAL COMMENT....................................................................................................31 APPENDIX A...................................................................................................................32 APPENDIX B...................................................................................................................33 APPENDIX C...................................................................................................................33 REFERENCES................................................................................................................35
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. PREFACE The Safety & Health Plan report has been prepared in compliance with the Safety, Health & Welfare at Work Regulations 2013 (SI No. 291 of 2013). It also includessubsequentamendments.Thisdocumentprovidesnecessary information needed in the Project Supervisor Construction Stage (PSCS) and is based on project information available at the time. The client must retain a copy of the report. 1
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. PROJECT TEAM The project team shall compose of the various heads from all the side of the client, contactors, designers as per the regulations and legislations. 2
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. 1.GENERAL DESCRIPTION OF PROJECT 1.1 PROJECT DESCRIPTION This section is not part of the contract since it only provides the necessary INFORMATION. Therefore, the entire work scope and contractor obligations are verified by referring to the set of contract documents. It includes: ï‚·Also, the roof cover needs to be repaired or replaced where possible while the floor also needs reconfiguration and extension. ï‚·The Scope of Works consequently consist of roof replacement and repair. ï‚·The lighting and heating systems, floor coverings and decoration need to be upgraded. 1.2 SITE LOCATION The Kimble building is an old 1800s three story building located in Dundalk town centre. Although the building is not protected, it is of historically significant due to its age and therefore must be approached with the greatest care. The building was initially used as the main office for Fyffes bananas. The site is well situated since it has a street access to the front, a car access to the back and a large carpark accessible across the road. The building also has a downstairs arcade, middle floor workshop and offices. The second floor comprises of a small head office and a large open plan office. Currently, the top two floors are undergoing some renovations despite being in use. At the back of the is a yard with some old ruins of buildings. 22
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. Figure 1 Kimble building front elevation 1.3 APPOINTMENT OF PROJECT SUPERVISOR FOR THE CONSTRUCTION STAGE (PSCS) The PSCS is appointed by the client and it is charged with sole responsibility of managing, controlling, coordinating the construction work as well as implementing the health and safety requirements during the project development phases. This appointment shall be made and accepted in writing. Before the construction works commences, the Health and Safety Authority shall be notified on the AF2 Form. 1.4 ESTIMATED TIMESCALE/ PHASING OF PROJECT The timescale of the project is to be carried out in linewith the Clients requirements. The safety, health and welfare of those persons directly or indirectly involved in the project should not be affected by the project schedule. This will allow the project to meet the desired requirements and should be overseen by the Project Supervisor for the Construction Stage. 23
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. 1.5 THE PROJECT SAFETY & HEALTH PRINCIPLES The objectives for this project are to: ï‚·Prevent fatalities and injuries. ï‚·Eliminate dangerous occurrences ï‚·Avoid unsafe and unhealthy work practices ï‚·Ensure adherence to the set legislation and Codes of Practice. 1.6 MONITORING & REVIEW OF SAFETY The PSCS manages, monitors and reviews health and safety implementation and performance on an ongoing work. A copy of the reports to is also submitted to the design team as well as the PSDP Supervisor. 1.7 DRAWINGS / SPECIFICATIONS A full set of existing and proposed drawings are provided together with the tender documentation. Drawings:Site Location Map2018 - 001 Plan for the site2018 - 002 First Floor Plan2018 - 003 Second Floor Plan2018 - 004 Third Elevation2018 - 005 1.8 EXISTING SAFETY FILE / EXISTING RECORDS We are not aware of any existing safety file or records at this time. 2. INFORMATION REGARDING THE PROPOSED SITE 2.1 RELEVANT ADJOINING LAND USES The Kimble building is a 1800s three story building situated in Dundalk town centre. 2.2 RESTRICTIONS ON WORKING HOURS The project team will agree with client t determine the working hours. An example of working hours schedule is shown below. 24
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. 07:00 - 18:00 Week days (Monday to Friday) 09:00 - 14:00 Saturday No work shall take place on Sundays or public holidays. 2.3 Noise/Dust /Vibration The PSCS is to ensure noise, dust and vibrations are kept to a minimum. 2.4 SITE RESTRICTIONS AND RESTRICTIONS ON ACCESS The PSCS and the contractor must adhere some set restrictions during the project development phases. They include: The work area must be secured to ensure that the of public do not accidentally enter the site. This is especially to the construction works next to commercial and residential buildings. All the debris and other work materials to be removed from the adjoining street(s). Heavy and noisy works must be completed within normal working hours for minimal disruption to the neighbouring people and properties. This must be ensured by the contractor through proper planning and observation of any restrictions. 2.5 Method Statements Shall be submitted by PSCS in a detailed writing. It covers the sequence of work operations and the temporary works where required before start of the work. 2.6 OTHER WORK ACTIVITIES NEARBY The PSCS is to satisfy themselves concerning the activities adjacent to the working cite. 2.7 EXISTING SITE ACTIVITIES Currently, the site is a residential home for tenants. 2.8 KNOWN EXISTING SERVICES Before beginning any work, PSCS must ensure that all the electrical power lines are safe to avoid dangerous occurrences. 2.9 LOCAL EMERGENCY PROCEDURES 25
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. The PSCS should include the emergency procedures for normal operation hours and odd hours. These procedures will further include the names and contact of the emergency organisations and people. These people should be capable of dealing with emergency situations at any time. 2.10 LOCATION OF WELFARE FACILITIES – CONNECTIONS FOR WATER, ELECTRICITY, SEWER With approval from the client, the PSCS shall arrange the compound location with minimal disruption. 2.11 ANY PARTICULAR SITE RULES Safety provisions as well as site rules and requirements shall be provided for safe working conditions. They are covered in the report appendix. 3. PARTICULAR RISKS Particular may be covered within the risks, as provided by the Project Supervision for Design Process are outlined in this section. However, it does not include foreseeable risks that are managed by the contractor and PSCS since the two are competent and will take up control measures as per the SHWW (Construction) Regulations 2013. The control requires a Safety System of Work. The images show the building orientations and surroundings including the interior(Blue Sky Property Dundalk - Serving Your Property Needs, 2019) and (Google.com, 2019). 26
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. Figure 3: Rear view of the building Figure 4: Renovations in the second floor 28
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. Figure 5: Walls requiring innovations. 3.1 THER HAZARDS / RISKS The following is an additional list of risks which may affect the safety and health of persons. The contractor shall, in the developed Construction Stage Health & Safety Plan, outline specific control measures to deal with the possible risks. 4. CONTINUING LIAISON 29
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. 4.1 PROCEDURES REQUIRED DURING THE CONSTRUCTION PERIOD Procedures for dealing with unforeseen and emerging issues during project implementation will be put in place. This may include changes in the design that may somehow compromise resources demand and project completion duration. In the event of design changes during the Construction phase, existing Design Risk Assessments must be reviewed or new Risk Assessments generated. It is the Designers responsibility to ensure that they inform the PSDP of any changes in their design and that the appropriate Design Risk Assessments are completed and notified to the PSDP and PSCS. 5. RELEVANT PRELIMINARY TRAFFIC MANAGEMENT PLAN As the project is being carried out in a busyDundalk town centre,the contractors Construction Management Plan must include traffic management plan which is to be implemented for the duration of the project. The traffic management plan must consider as a minimum: ï‚·Site Parking arrangements ï‚·How/ when site deliveries and collections will be handled ï‚·Storage of materials and waste ï‚·Safe access & egress from site for vehicular traffic ï‚·Removal of waste & debris from the site, including demolition waste 6. THE SAFETY FILE 6.1 ARRANGEMENTS FOR GATHERING INFORMATION FOR THE SAFETY FILE The PSDP Co-Ordinator and client must about the format to be sued for the Health and Safety File after which its requirements will be detailed in a meeting with the appointed contactor in attendance. All the necessary information regarding the Health and Safety File shall be collected by the PSCS are requested by the PSDP Co-Ordinator. 30
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. 6.2 CONTENTS OF THE SAFETY FILE A non-exhaustive list of the suggested contents for the safety file has been included within the appendices section to the rear of this Plan. 7. COMPLIANCE WITH GENERAL SAFETY REQUIREMENTS The various Contractors shall comply with all relevant statutory requirements. They include Welfare at Work Act and Safety Health, 2005, various regulations and subsequent amendments, legislation and guidelines. The contactor must extend the safety requirements to the client and project supervisors. 8. FINAL COMMENT It is a good practice to prepare information regarding the project like the one contained in the preliminary section before the actual commencement of the project.However,itdoesnotaccountforemergingissuesduringproject implementation stages. 31
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. APPENDIX A GENERAL SAFETY PROVISIONS, SITE REQUIREMENTS & SITE RULES (NON-EXHAUSTIVE) They include just to mention but a few. PROVISIONSLEGAL REQUIREMENT (OUTLINE) Duties of EmployersIt is the duty of the Contractor engaged in this project to comply in every respect with the relevant procedures, guidelines and regulations. This also covers the relationship with the employer. CompetenceThe Contractor must ensure that everybody engaged in this project for the purposes of construction are competent as per the SHWW Act 2005 Systems of WorkIt is the duty of the Contractor to plan organise, maintain and revise all the work systems to ensure work satiety without health risk. Plant Equipment & Machinery It is the duty of the Contractor to provide safe equipment and machinery for use during the project. They should be appropriately maintained. Personal Protective Equipment The Contractor must provide and maintain appropriate protective clothing and equipment at all times depending on the nature of the work. Principles of PreventionThe Contractor must eliminate hazards and reduce risks to an acceptable level. SITE SPECIFIC RULES TO BE IMPLEMENTED: 1.All site visitors, personnel and contractors must comply with the Health and Safety Policy set by the Main Contractors as well as those of the and the specific construction stages. 2.Sub-contractors must submit to the main contractor their Health and Safety Policy and procedures before starting the allocated work. 3.All risks identified risks must be identified and addressed individually 32
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. 4.All site personnel and Health and Safety Personnel are advised on an ongoing basis of any revisions to the Safety Plan. 5.Smoking is not permitted within the designated working areas. 6.Eating and drinking is not allowed in the designated working area. APPENDIX B THE GENERAL PREVENTION PRINCIPLES: The Contractor must consider the Prevention Principles and purpose to reduce risks by the use of alternative and safer work practices. All those involved in the planning of the works must put in place collective protective measures in favour of personal protective measures. General principles of prevention specified in the Schedule 3 of the 2005 Safety include: 1.Risks prevention. 2.Proper evaluation of the unavoidable risks. 3.Combating of risk especially at the source 4.The technical issues and progress and how to adapts to the place. 5.Providing adequate employee training and instructions. APPENDIX C HEALTH & SAFETY PLAN (NON-EXHAUSTIVE LIST OF ITEMS FOR INCLUSION) The Preliminary Health & Safety Plan shall be developed as per the 2013 Construction Regulations. Items to be addressed in the plan include: 1.General 2.First Aid Emergency Procedures and provisions 3.Management 4.Procedures 5.Site Rules 6.Health & Safety Risks 33
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. 7.Particular Risks to Health & Safety 8.Welfare Provisions 34
ODM Surveyors, Kimble Building, Bachelors Walk, Dundalk. REFERENCES Blue Sky Property Dundalk - Serving Your Property Needs. (2019).26 Bachelors Walk DundalkCoLouth.[online]Availableat: https://www.blueskyproperty.ie/for-sale/g2j2ktu7w3tj70hrq9dt11t5iyijlb[Accessed1 Jan. 2019]. Google.com. (2019).Kimble building, bachelors walk, Dundalk, co louth, Ireland - Google Search.[online]Availableat:https://www.google.com/search?q=kimble+building, +bachelors+walk,+Dundalk,+co+louth, +ireland&tbm=isch&tbo=u&source=univ&sa=X&ved=2ahUKEwjt3paGuczfAhXVQxUIHb9j CJUQsAR6BAgDEAE&biw=1517&bih=730 [Accessed 1 Jan. 2019]. 35