Infrastructure Management for Kosciuszko Bridge Project

Verified

Added on  2023/06/10

|13
|3233
|210
AI Summary
This report discusses the planning, appraisal, and environment impact assessment of the Kosciuszko Bridge project. It also covers the different alternatives and procurement methods used in the project. The report provides a brief background of the construction project and discusses various project procedures and methodologies.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: INFRASTRUCTURE MANAGEMENT
INFRASTRUCTURE MANAGEMENT
Name of the Student
Name of the University
Author Note:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1INFRASTRUCTURE MANAGEMENT
Table of Contents
Introduction..........................................................................................................................2
Discussion............................................................................................................................2
Project location and background.....................................................................................2
Different alternatives.......................................................................................................4
Project goals and objectives.............................................................................................5
Planning and appraisal.....................................................................................................6
Environment Impact assessment......................................................................................7
Public scoping..................................................................................................................7
Procurement.....................................................................................................................8
Conclusion...........................................................................................................................8
References..........................................................................................................................10
Document Page
2INFRASTRUCTURE MANAGEMENT
Introduction
Kosciuszko Bridge has been completed in the year of 1939 and carries around 1.1-mile
segment which connects Green point in Brooklyn to Maspeth in Queens. U.S Department of
Transport Federation Highway Administrative (FHWA) and NYDSDOT is planning to replace
the current bridge in two phases (Cohen, 2017). The construction of the first phase of the bridge
is expected to begin soon. After that two parallel bridges are expected to be built on the east side
of the existing bridge. The bridges will be designed in such a way that it can easily carry six
lanes of traffic. After the competition of the bridge, new connecting roadways are needed to
build which would be connecting Brooklyn-Queens Expressway (BQE) into new bridges. Then
the current bridges will be demolished (Saska et al., 2016). Later on, in phase II a new bridge
will be constructed which would be built in this place. After the competition of the second phase,
three new bridge is required which is used for carrying five lanes of traffic in eastbound and four
lanes of traffic in westbound.
In the coming pages of the report, an idea has been provided regarding the location and
background of the Kosciuszko Bridge project. After the various alternatives with respect to the
Kosciuszko Bridge project has been discussed in brief. Planning and appraisal of Kosciuszko
Bridge have been discussed. An environment impact assessment has been done on Kosciuszko
Bridge. At the end of the report, public scoping and procurement have been done with respect to
the given project.
Document Page
3INFRASTRUCTURE MANAGEMENT
Discussion
Project location and background
The project of Kosciuszko Bridge will be dealing with a possible solution with its
rehabilitation or replacement (Sankaran et al., 2018). The project mainly focuses on a 1.1-mile
segment of BQE expressway. The north side of the bridge is connected to LIE which is known as
Grand Central Parkway (GCP). The south of the bridge is connected to Williamsburg, Manhattan
and lastly Brooklyn bridges along with the tunnel (Moran & Odeh, 2016). This particular project
will check three major issues like traffic congestion, traffic safety, and structural condition.
Traffic congestion: In the year of 1930, Kosciuszko Bridge was built, so it cannot safely
carry the present volume of traffic. The short distance near the ramps does not meet with the
current standard of the highway. The delay in traffic encourages various drivers to look for an
alternative route.
Traffic safety: The design flow mainly focuses on the problem which can easily affect
the traffic flow. It mainly focuses on traffic safety conditions on the bridge which ultimately
affect the safety condition at the bridge and adjacent highways (Surowiecki, Machelski & Saska,
2016). These problems ultimately resulted in higher accident rates which are in New York.
Structural Condition: With the passage of time the structural changes at the bridge is
deteriorating day by day. Some of the recent inspection has focused on the fact that despite the
aggressive effort by NYSDOT the deficiencies in the bridge are increasing day by day.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4INFRASTRUCTURE MANAGEMENT
Fig 1: Kosciuszko Bridge (New York City)
(Source: Landers, 2015, pp-68)
There is an ongoing construction for replacing the Kosciuszko Bridge which comes up
with the nine-lane bridge. It mainly comprises of two eastbound spans, one westbound span, a
path for bike and lastly a walkway (Surowiecki, Machelski & Saska, 2016). Two new cable-
stayed suspension bridge will easily replace the existing span of steel truss. 104 meters long
cable strayed bridge design have made it first of its types in the existing model. NYSDT (New
York State Department of Transport) is planning to build a six-lane highway which is next to the
present bridge. It is mainly used for connecting Brooklyn Queens Expressway is to build a new
kind of bridge before the previous bridge is torn out (Duchaczek & Skorupka, 2017). On 23 May
2014, the first phase of the project that its design phase was given to a various organization like
Skanska, Kiewit and ECCO III. This particular project is considered to be a largest single
contract which was awarded by NYSDT. The first phase of the bridge will be erected to the
south side of the existing bridge and is expected to be opened up in late 2016. After the
completion of the first phase of the building, all the BEQ traffic will be shifted into it and
followed by demolishing of the old bridge (Haimerl, 2015). The second phase of the building is
Document Page
5INFRASTRUCTURE MANAGEMENT
expected to be completed by 2019. Some extra lanes are required because Kosciuszko Bridge is
considered to be the bottleneck of traffic.
Different alternatives
Draft Environment Impact Statement (DEIS) is all about to have a proper review of the
various alternatives which is needed for meeting Kosciuszko Bridge project goals and objectives
(Duchaczek & Skorupka, 2016). The design criteria are mainly used for developing various
project alternatives like NYSDOT structure of the design. The criteria are generally inclusive of
various parameters like design speed, the width of the lane and lastly sight distances.
No build alternatives: Under the regulation of NEPA (National Environment Policy
Act) and SEQRA (State environment quality review Act), DEIS is generally required to include
various kinds of things like “No build” and “No action”. No alternative mainly focuses on “Do
Nothing” except for continuing the process of current maintenance and efforts for its repairing
(Duchaczek & Mańko, 2015).
Transport System management (TSM): An alternative to TSM can be easily used for
accessing low-cost operation which will be used for accessing the transportation needs.
Rehabilitation of Bridge: In this particular category major rehabilitation of the current
bridge is required on daily basis (Duchaczek & Mańko, 2017). It mainly requires various phases
which can be used for incorporation of use of temporary bridge which can be easily used for
incorporating traffic during the construction phase of the given of the project.
Rehabilitation with additional capacity: Under this particular alternative, the bridge
can be used for rehabilitation to the similar above but in the competition phase of the project
Document Page
6INFRASTRUCTURE MANAGEMENT
mainly deals with associated roadways which can be easily used for additional capacity and
improvement of safety.
Bridge replacement: This particular alternative analysis process is mainly used in a wide
range of concepts which can be easily used in the construction or replacement of the current
bridge (Kobielak, Hutnik & Zamiar, 2015). A proper kind of replacement facility is required
which is located parallel to the current structure which is built on alignment.
Project goals and objectives
During the process of EIS, some kinds of alternatives are required for traffic capacity,
safety and various kinds of structural needs of the Kosciuszko Bridge project. NYSDOT while
working with elected officials and goals has come with elected officials which can be used for
placing various goals and objectives. Any kind of alternative which is considered at this phase
required for seeking into various goals and objective of the given project that is Kosciuszko
Bridge (Duchaczek & Mańko, 2016). Along with these, it requires a proper balancing of needs of
the project with a wide range that is social, economic and environmental needs. There is a certain
number of goals and objectives which needs to be developed for this Kosciuszko Bridge project.
Transportation Goal
There is a certain number of transportation goals which can be achieved by this project:
It is will improve the various traffic operation, reduce delay along with increasing
efficiency and reliability.
It will be helpful in minimizing the diversion of auto and truck traffic to the
various local street in both cases that is construction and in long-term.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
7INFRASTRUCTURE MANAGEMENT
Planning and appraisal
Under the national policy, it is the duty to give special effort for preserving the natural
beauty of both countryside, public park, recreation land and historic beauty sites. Under the US
Department of Transportation Act 1996, a special provision was adopted which can be easily
used for the protection of these resources (Mahmoud, 2017). This particular act is known as
section 4(f) and it mainly stipulates the FHWA which does not improve any program or project
which requires any kind of public space like wildlife or public park. Any kind of land from the
historic site, local place is not considered to be feasible to use for the construction of this bridge.
All kind of possible planning is done which can be done for minimizing any kind of harm which
can result from such use have been discussed in details.
Environment Impact assessment
Depending on the review and potential impact of Kosciuszko Bridge project, various
bodies like FHWA and NYSDOT have concluded the fact that appropriate method can be easily
used for preparing EIS (Environment Impact statement) for Kosciuszko Bridge project. This is
mainly inclusive of previous studies which have been completed for the given project (Lee &
Sternberg, 2015). Draft and final document of EIS is needed to be completed in proper
compliance with the regulation of NEPA and SEQRA. NYSDOT and other agencies need to
consider various kinds of environmental concerns during the time of decision making. The
above-mentioned documents can easily serve as a proper kind of public discloser which can be
used for the discloser of the environmental effects of the project.
Public Scoping
Scoping process is considered to be the earliest kind of opportunity platform which is
needed for the preparation of DEIS (Duchaczek, 2016). It various kinds of public process which
Document Page
8INFRASTRUCTURE MANAGEMENT
is used for confirmation of various goals and objectives of the effort of DEIS. The ultimate goal
of scoping is to easily identify various kinds of concern and ideas which can be used which can
be easily used for DEIS analysis (Sivakumar et al., 2017). Scoping can be considered to be a
well-known opportunity which can be used for public review. Recommendation for proper
consideration and alternatives needs to be addressed in the DEIS.
Prior to the starting of the public scoping method, NYSDOT comes up with various kinds
of open houses which are based in Brooklyn and Queens (Landers, 2015). It aims in meeting
with community boards along with other agencies and various elected officials. From the various
efforts, NYSDOT has gained some of the initial understanding which is considered to various
community members, business group and other kinds of stakeholders.
Procurement
Procurement can be easily stated as a well-known method which repeats itself for certain
kinds of methods. Procuring is all about consuming resource which can be used for converting
available inputs into desired or required outputs (Sykutera et al., 2018). Kosciuszko Bridge
project comes up with various kinds of opportunities for different local business and
disadvantaged business enterprise (DBE). More than 70 million dollars were offered to
Kosciuszko Bridge project which has been allocated to various small business as a part of
Disadvantage Business (DBE) Enterprise program (Yuan et al., 2018). The project team of
Kosciuszko Bridge is actively making recruiting of DBE certified business. There are some work
areas which needs to be identified as
Furnishing and installation of reinforcement steel.
Furnishing and proper delivery of various filling materials for this project.
Document Page
9INFRASTRUCTURE MANAGEMENT
Proper electrical materials for supply.
Designing services as per the recruitment.
Supply of various concrete materials.
Landscaping of various materials.
Conclusion
From the above discussion, it can be easily concluded that this report is all about
Kosciuszko Bridge. FHWA (Federal Highway Administration) in cooperation with NYSDOT
(New York State Department of Transport) will easily prepare a document which will help in
analyzing various required improvement in Kosciuszko Bridge. This particular bridge is
considered to be a 1.1-mile segment which runs on Brooklyn- Queen Expressway. With the joint
venture between the National Environment Policy Act (NEPA) and New York State Quality
Review Act (SEQRA) a public scoping will be conducted on this project. This method will be
helpful for understanding the social, environmental issues which are provided in the Draft
environment impact statement (DEIS). This particular process aims at ensuring the fact that
DEIS is concise in nature. A comprehensive document generally tends to provide all concern
related to public issues. Draft scoping is taken to be the first step which can be used for the
preparation of DEIS of Kosciuszko Bridge project. In the above pages of the report, a brief
background of the construction project has been provided. After that different types of
alternatives which should have considered in the project has been discussed in detail. Various
kinds of project procedure and methodologies have been discussed in detail which can be easily
used for taking consideration of DEIS. In the above pages of the report, a proper location and
background of the Kosciuszko Bridge project have been provided. Different aspects of the

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10INFRASTRUCTURE MANAGEMENT
project like alternatives, planning, and appraisal, environmental impact assessment, public
scoping/ involvement, procurement have been discussed in detail.
References
Cohen, P. (2017). Jobless Rate at 10-Year Low, as Hiring Grows and Wages Rise. The New York
Times, 5.
Duchaczek, A. (2016, June). The impact of cross beam on stresses of girders in low water
bridges. In International Conference on Renewable Energy Sources-Research and
Business (pp. 139-147). Springer, Cham.
Duchaczek, A., & Mańko, Z. (2015). Determination of the value of stress intensity factor in
fatigue life of steel military bridges. European Journal of Environmental and Civil
Engineering, 19(8), 1015-1032.
Duchaczek, A., & Mańko, Z. (2016). The influence of a cracking mode on fatigue crack
propagation in steel girders in military bridges. European Journal of Environmental and
Civil Engineering, 20(1), 1-18.
Duchaczek, A., & Mańko, Z. (2017). Influence of the holes spacing in bolted connections on
propagation of fatigue cracks in steel bridge girders. KSCE Journal of Civil
Engineering, 21(3), 838-850.
Duchaczek, A., & Skorupka, D. (2016). A Risk Assessment Method of Bridge Facilities Damage
in the Aspect of Potential Terrorist Attacks. Periodica Polytechnica Civil
Engineering, 60(2), 189-198.
Document Page
11INFRASTRUCTURE MANAGEMENT
Duchaczek, A., & Skorupka, D. (2017). Risk assessment as a safety element in temporary bridge
exploitation. European Journal of Environmental and Civil Engineering, 21(10), 1253-
1269.
Haimerl, A. (2015). The fastest growing group of entrepreneurs in America. Fortune The Fastest
Growing Group of Entrepreneurs in America Comments, 29.
Kobielak, S., Hutnik, E., & Zamiar, Z. (2015). Failures of building constructions caused by
design errors. Zeszyty Naukowe/Wyższa Szkoła Oficerska Wojsk Lądowych im. gen. T.
Kościuszki.
Landers, J. (2015). Accelerating Innovation. Civil Engineering Magazine Archive, 85(9), 66-71.
Lee, G. C., & Sternberg, E. (2015). Bridges: Their engineering and planning. SUNY Press.
Mahmoud, K. M. (2017). Asset Management of Bridges: Proceedings of the 9th New York
Bridge Conference, August 21-22, 2017, New York City, USA. CRC Press.
Moran, R., & Odeh, I. (2016). Design-Build Mega Bridge Projects in New York and Best
Practices in Procurement. In Construction Research Congress 2016 (pp. 361-370).
Sankaran, B., Nevett, G., O'Brien, W. J., Goodrum, P. M., & Johnson, J. (2018). Civil Integrated
Management: Empirical study of digital practices in highway project delivery and asset
management. Automation in Construction, 87, 84-95.
Saska, P., Ryczyński, J., Surowiecki, A., & Duchaczek, A. (2016). The Operational Safety of the
Railway Track in the Area of a Bridge Structure Made of Corrugated Sheets. Logistics
and Transport, 32.
Document Page
12INFRASTRUCTURE MANAGEMENT
Sivakumar, B., Lauzon, C., Decorges, G., & D’Ambrosio, P. (2017). Design-Build replacement
of the I-278 Kosciuszko Bridge Phase 1—approaches and connectors. In Asset
Management of Bridges (pp. 97-112). CRC Press.
Surowiecki, A., Machelski, C., & Saska, P. (2016). Numerical modelling of engineering soil
shell structure. Zeszyty Naukowe/Wyższa Szkoła Oficerska Wojsk Lądowych im. gen. T.
Kościuszki.
Sykutera, D., Czyżewski, P., Kościuszko, A., Szewczykowski, P., Wajer, Ł., & Bieliński, M.
(2018). Monitoring of the injection and holding phases by using a modular injection
mold. Journal of Polymer Engineering, 38(1), 63-71.
Yuan, C., Park, J., Xu, X., Cai, H., Abraham, D. M., & Bowman, M. D. (2018). Risk-Based
Prioritization of Construction Inspection. Transportation Research Record,
0361198118782025.