PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik Research in project management: Investigating The Cause of Labour Productivity on Context of Construction Projects in India. Name of the student: Name of the university: CQUniversity|PPMP20015Research Proposal Template1 INSTRUCTIONS This proposalis effectively your business case and project management plan for the execution and closing phases of your research project. As such, it must be written in a clear language so anyone can use this document to complete the project. You must submit both Draft Proposal and Final Proposal in Word format. Please strictly adhere to word limits in each section. You are highly encouraged to consult Studiosity, ALC and/or Turnitin before submitting your draft or final version. Due date for the Draft Proposal is Monday, 20 May 2018, 5:00 pm. Due date for the Final Proposal isSunday, 3 June 2018, 11:55 pm Dot points are not to be used except where noted as acceptable. Youare encouraged to include relevant diagrams in any part of this submission to more clearly illustrate ideas,including the research design. Youmust refer to Moodle Site to learn about the criteria by which your research proposals will be assessed. Please include the following sections in the proposal (allblue textis for guidance only andis to be replacedby appropriately formatted text).For draft proposal, include all sections except the research project management which will only be needed in the final submission
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik RESEARCH PROPOSAL CHECKLIST (If you answer any question in this checklist with NO, Highlight that question in RED and include this checklist in your submission) The research topic Does it summarize the main idea of my proposed research in an exciting way in no less than10- 12words? Can it stand alone? Is it fullyexplanatory? Rationale andSignificance DoIprovideabriefdescriptionofmyproposedresearch? Do I explain how the results of my research will advance the general understanding ofthis topic? Do I explain how the results of my research fill a knowledgegap? Research questions and objectives Do I have a formal and clear statement of my proposed research questions and objectives? Are my research questions developed aligned with the rationale and relevant reviewedliterature? Do my research questions and objectives connect? Are they logical, researchable,achievable, andethical? Preliminary Literaturereview Does my literature review justify my research questions? Does my literature review identify gaps, shortcomings, and limitations in existing researchgiving context to mystudy? Do I demonstrate a thorough and current understanding of the peer-reviewed literaturerelating to mytopic? Research approach, methods, ethics and limitations. Do I explain the approach I intend to use to solve the challenge in my study? Is it explicitand well thoughtout? Are both my research approach and methods tied to my research questions and objectives? Does both my approach and methods show an understanding of relevantreviewedliterature? Are my procedures well organized and clearlydescribed? Do I discuss how confidentiality of participants and their responses will be maintained?(if applicable) Have I explained the scope boundaries and exclusions of my research? Project management Does my project schedule name all key activities and milestones for specific CQUniversity|PPMP20015Research Proposal Template2
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik achievements? And does it pertain to the objectives Ihave set out toachieve? Is my schedule manageable and realistic? Do I allow adequate time for completion of eachactivity? Is the sequence for completionlogical? Are all resource requirements assigned to project activities? Are the key risks well identified and analyzed? Are the key stakeholders well identified and analyzed? Are my procedures for data management clearly described? Have I provided a shared link to my Endone library and project data folder? References and Presentation Have I provided cover page and abstract as per requirements? Have I had my work checked by Studiosity and ALC before submission? Is my language clear enough and free from typos and grammatical errors? Do I provide a list of cited references that are current andrelevant? Am I using Harvard style in the reference list and in-text referencing? Have I followed all other instructions for submissions? CQUniversity|PPMP20015Research Proposal Template3
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik Research Project Topic Abstract Most of the construction activities are labour intensive and labour productivity is one of the key area in the construction industry of any nation. Construction activities in India contribute 10% to its GDP (dmg events, 2015). Hence, enhancing labour productivity will contribute to the overall project success. This research mainly aims to investigate the cause labour productivity in India. For this 30 Factors are considered which negatively effect the labour productivity in India. Out of these 30 factors 8 most significant factors are considered and Total interpretive structural modelling system (TISM) is used as an methodology to identify the relationship between these problems. In this research both quantitative and qualitative analysis is done. Interviews are conducted with the stakeholders of 3 construction companies located in different parts of India to find 30 factors. During this interview each person is asked to rate the impact of these factors on the productivity and based on these rating 8 most significant factors are considered and TISM is applied to these 8 factors. This research shall be conducted in 3 months of duration (July 2018 – October 2018) and it is accordance with the CQU policies and protocol. CQUniversity|PPMP20015Research Proposal Template4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik 1.The rationale of the study Labour productivity has always been a matter of concern in the construction industry. Due to low labour wages, Indian construction economy is more dependent on manpower rather than the new technological advanced equipment’s. Productivity is the measurement between the input and output. Therefore, it is a matter of concern to every profit-oriented construction organisation. Hence improving labour productivity contributes a lot to the economic growth of the construction industry in India. Construction activities contributes 10% to the country’s GDP (dmg events, 2015). According to the news article published by ‘The Economic Times’ in 11 February 2016 India needs a rise of 7.3% in labour productivity to get a growth of 9% in the GDP (The Economic Times, 2016). This research mainly focuses on finding the significant factors influencing the labour productivity in construction industry of India and finding the relationship between these significant factors using Total interpretive Structural modelling (TISM). In this research interviews and sampling methods will be used to find the factors influencing the labour productivity. The list of factors will then be arranged in to order of their significance and then Total interpretive structural modelling is applied to the top 8 significant factors. The data will be collected form the 3 major construction company’s located in the major construction oriented cities of India. This research is mainly based on the limitation of the previous research which was done in Cambodia (Durdyev and Mbachu 2017). This research aims to do the similar research to verify the results lies same with the construction industry of India. Furthermore, this research aims to apply Total Interpretive Structural modelling to find the relationship between the factors influencing the labour productivity. 2.Significance of the study The research will analyse the factors influencing the labour productivity in India. India is a labour- intensive market and improving the labour productivity will help in reducing the cost and time of the project and contributes to the overall success of the project. Almost every construction activity requires labour and finding the key factors reducing the labour productivity will help in minimizing or eliminating its bad effect. Most of the companies specially the small-scale companies neglect this issue as they don’t want to spend huge money in proper scheduling tools and techniques. According to the news article published by ‘The Economic Times’ in 11 February 2016 India needs a rise of 7.3% in labour productivity to get a growth of 9% in the GDP (The Economic Times, 2016). Hence this research can find the significant factors influencing the labour productivity and with the application of TISM can help to analyse the situation and improve the performance by taking the necessary corrective actions. The results of this research can be used by many companies specially the small-scale companies to take the corrective measures in improving the labour productivity. 3.Preliminary literature review According toSandbhor and Botre (2014), the Indian construction industry is mostly even always been dependent on the manpower over advanced technologies. Thus, the productivity from the project is in most of the cases party or fully dependent on productivity from the labours. The key success of the construction projects depends on the contribution of the labours to the projects. In order to identify and summarize the relationship between the factors that are affecting the labours and the productivity are measures with the help of a methodology called total structural modelling factors (TSMF). A construction project can either be lead towards success or towards failure with the activities of the labours associated to the project. According toSayaliShrikrishnaSandbhoret CQUniversity|PPMP20015Research Proposal Template5
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik al(2014) material storage, equipment storage, drawing, alteration specifications are the tools that may drive a construction project towards success. Walker (2015) states that, lack of experience of the labours and lack of labour surveillance may impact any project either positively or negatively. In order to facilitate improvement of the overall productivity on the construction site are done by the labours associated to the construction project. As the construction industry is completely labour oriented thus, it puts huge influence on the successful implementation of any project. Before allocating any resource to a particular activity of the construction project it is necessary for the project manager to understand their skills and knowledge regarding the activity (Grover and Froese 2016). Besides the labours the project manager is also responsible to improve the performance of the labours with the help of on job trainings. It has been found that, the construction labour productivity is influenced with work level variation in management efficiency and work level conditions. It is the role of the project manager and the project team members to understand the individual parameter’s nature and its impact on the construction productivity. Productivity is referred to as a ratio between the given input and the generated output. Different external factors can be avoided with cost variance, operational activities and labour productivity as well as reliable measurements. Productivity loss may impact the ultimate outcome of the construction project. According toKerzner and Kerzner (2017) in these current days the labour productivity is decreasing everyday and thus the labour productivity and the expected outcome from the construction are getting impacted negatively. The key constraints of the construction projects are necessary to be identified by the construction project managers. There are four major principles those are affecting the construction project outcomes in terms of good quality leadership, better management abilities, adequate cash flow and minimizing work defects. From the application context, the construction productivity is being interrupted each time due to improper labour measures and improper capital productivity.Banihashemet al. (2017) stated that, one of the most commonly used productivity measure is labour productivity as this is the easiest input to the construction industry. It has been found that there are many constraints that help to investigate the labour productivity. The main roles of the construction project managers are to identify the factors that are constraining the labours productivity mainly in the residential building projects within the Cambodian construction industry. Apart from this, it is the role of the construction project managers to establish the principle factors from the identified sets of variable constraints. There are different constraints such as poor leadership, late payment, defective workmanship, financial defect of the owners, under resource utilization are the constraints that affect the labour productivity. Site management constraints and workforce constraints are the other components that affect the regular expectation of the construction managers from the construction projects. Through wider survey it has been found that, operation context is the most important thing that minimizes the risk profiles and the other operational contexts accordingly. From the literature or secondary information analysis it has been found that, the principle labour productivity inhibits all the factors those are majorly extracted from the constraints variables in terms of site management, work force and resource management. Poor leadership and lack of influence from the construction industry can lead a construction project towards failure. If the construction manager fails to incorporate the necessary change activities then project decision making will be also eventually interrupted. New emerging critical factors are required to be considered by the construction project heads (Varajãoet al. 2014). The construction productivity always acts as a main factor that influences the timely completion of the construction project. In order to achieve the aimed requirement level the project manager is required to evaluate the labour productivity apparently. In order to measure the highly variable labour productivity proper sampling method is needed to be evaluated accordingly. The instantaneous observation allows the construction project managers to determine the activity amounts (Sandbhor and Botre 2014). The labour construction is dependent on the fundamental probability law. CQUniversity|PPMP20015Research Proposal Template6
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik Another issue is waiting for the instruction or for the inspection (Durdyev and Mbachu 2017). Without the instruction from the construction supervisor the labours cannot work for to meet the construction objectives. Including the manager the labours must have co ordination among each other. With proper motivation and usage of construction tools and techniques the issues associated to labour performance can be avoided. Different values can be added to the labour productivity, if the research gaps are minimized accordingly. 4.Research question(s) and objectives Research questions What are the different 30 factors that negatively impact the outcome of the construction company? What are the 3 well known construction based companies in India? What are the different construction activities that interrupt the expected outcome of the construction companies? Objectives To identify all the 30 factors that negatively impacts the outcome of the construction industry To identify 3 major India based construction companies To identify the construction activity that interrupts the expected outcome from the construction company 5.Research Methodology 5.1Research Approach In order to conduct the research work it is the responsibility of the researcher to consider all necessary research aspects in terms of research design, philosophy, and data collection method and data techniques. For this particular research the positivism research philosophy, deductive research approach and descriptive research design are selected. There are two different types of data collection methods such as primary and secondary. In order to collect data through primary data collection questionnaire and survey are required on the other hand, secondary data resources are journals, books, blogs etc. From these resources the secondary data can be eventually collected by the researcher. For this particular research topic secondary data collection and mixed data such as quantitative and qualitative data are collected from the resources. It has been found that, in order to conduct the construction research total interruptive structural modelling is needed to be considered. 5.2Data collection methods and analysis There are two different data collection methods are there such as primary and secondary. It is the responsibility of the researcher to collect data through the secondary data approach. In order to conduct this research work the, secondary data collection approach has been selected. No such survey questionnaire is prepared for collecting data from the participants. In order to collect data from this particular topic secondary data collection approach is selected. Whenever the information are gathered by someone else to meet the purpose that is other than researcher’s current project and has already gone through the statistical analysis is known as secondary data analysis. Secondary data are easily available from different resources and there is no such specific method for collecting data. The researchers are capable of gathering data from the resources both internal to the business organization. The internet sources those are used for collecting data for this particular research work are as follows: CQUniversity|PPMP20015Research Proposal Template7
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik Financial statement Indian construction based reports Construction company information Management information system There are many other external sources also those are used for successfully conducting the research work. The external sources of the secondary data are as follows: Constriction level organizational journals Social books on Indian construction and labour engagement programs Data from other governments Indian government censuses The secondary data can be either quantitative or qualitative. The qualitative data for this particular research topic are gathered from transcripts, journals, books, articles etc. whereas; the qualitative data can be gathered from different financial statements and statistical information set also. The main advantage of the secondary data is that it can be collected very easily. Thus, secondary data collection is neither time consuming nor costly. However, this is much expensive than the primary data. The only issue that may negatively impact the researcher and the research topic is that secondary data are not specific. In order to collect specific data the primary data are much effective. The authenticity of the research results may be sceptical. The profits makes secondary data sources much interesting mainly for the statistical productions. For detail longitudinal studies also this timely delivery and secondary sources are very much effective. For this topic, the primary data collection method is avoided. 5.3Ethics Statement While developing any project it is the role of the project manager and the project team members to make sure that no such unethical approaches are taking place. Data application: The data those have been collected from the secondary data analysis should be used considering all ethical aspects. None of the data application process should be violated by the project managers and the rest of the project team members. Involvement of the respondents: The people who are associated to the project should not violate any ethical standards. None of the project team members should be pressurized or influenced. 6.Research project management Risk register including analysis and response strategy No.RiskProbability (1 very low, 5 very high) Impact (1very low, 5 very high) Assessment (impact x probability) Response strategy 1Physical risks53MediumIn order to avoid the physical risks proper safety equipments are needed to be adopted. 2Economical54HighThe researcher CQUniversity|PPMP20015Research Proposal Template8
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik risksshould design budget of the research based on its requirements. It is the role of the researcher to make a feasibility study so that to make sure whether the estimated budget is feasible or not. 3Legal risk55 Very high All legal standards and legal aspects are required to be adopted by the researcher. 4Loss of confidentiality 55Very highProper security approaches should be considered to avoid data assaults and data hijack. Stakeholder analysis: StakeholderInfluence (ability to effect changes) Impacted by projectInformation neededOutcome desired Project sponsorsHighHighThe project objectives To deliver a successfully constructed site to the consumers and to meet the project outcome within the investment. Project managerHighMediumThe project objectives and assumptions To deliver the project within the estimated time and estimated budget. Finance managerHighMediumThe project objectives and assumptions To estimate accurate project budget so that no commercial loss is faced. Operation managerHighLowThe project objectives and assumptions To implement all the operational activities to the project activities ContractorsHighHighThe project objectives and assumptions To deliver a decorated and comfortable constructed plot to the consumers CQUniversity|PPMP20015Research Proposal Template9
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik Data management In order to develop the construction project different data are collected from the secondary resources. It is necessary for the project managers to secure all the data from the external and unauthenticated users. A computerized information management system is used by the project managers to store all the necessary information. In order to keep the secured from the external attackers the stored information should keep encoded those cannot be even decoded by the unwanted people. Computerized record keeping system increases the overall management of the construction projects. The information can be retrieved by the contractors and the project managers easily with the automated data management system. In addition to this, data encoding another important security mechanism that should be incorporated is encryption. Without the key nine of the external users will be able to access information from the server. Application firewall should also be used by the construction manager so that the while transmitting information from the sender to the receiver none of the external can access the information. CQUniversity|PPMP20015Research Proposal Template10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PPMP20015: Assignment 2 - Research Proposal Unit Coordinator: Dr Samer Skaik 7.References List Banihashemi, S., Hosseini, M.R., Golizadeh, H. and Sankaran, S., 2017. Critical success factors (CSFs) for integration of sustainability into construction project management practices in developing countries.International Journal of Project Management,35(6), pp.1103-1119. Durdyev, S. and Mbachu, J., 2017. Key constraints to labour productivity in residential building projects: Evidence from Cambodia.International Journal of Construction Management, pp.1-9. Eroshkin, S.Y., Koryagin, N.D., Kovkov, D.V., Panov, D.V. and Sukhorukov, A.I., 2017. The paradigm of the integration of different types of management information systems in investment and construction company implementing the project approach.Procedia Computer Science,103, pp.605-608. Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute. Grover, R. and Froese, T.M., 2016. Knowledge management in construction using a SocioBIM platform: A case study of AYO smart home project.Procedia Engineering,145, pp.1283-1290. Hogan, M., 2015. A Case Study for Improving Construction Project Management. Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Mok, K.Y., Shen, G.Q. and Yang, J., 2015. Stakeholder management studies in mega construction projects: A review and future directions.International Journal of Project Management,33(2), pp.446-457. Mubarak, S.A., 2015.Construction project scheduling and control. John Wiley & Sons. Oakland, J. and Marosszeky, M., 2017.Total Construction Management: Lean Quality in Construction Project Delivery. Routledge. Ogunde, A., Olaolu, O., Afolabi, A.O., Owolabi, J. and Ojelabi, R., 2017. Challenges confronting construction project management system for sustainable construction in developing countries: Professionals perspectives (a case study of Nigeria).Journal of Building Performance,8(1), pp.1-11. Rozali, N.H.A., 2015.To Review the Effectiveness of Project Management in Construction Process(Doctoral dissertation, UMP). Sandbhor, S.S. and Botre, R.P., 2014. Applying total interpretive structural modeling to study factors affecting construction labour productivity.Construction Economics and Building,14(1), pp.20-31. SayaliShrikrishnaSandbhor and Rohan P. Botre, 2014. Applying total interpretive structural modeling to study factors affecting construction labour productivity.Construction Economics and Building, 14(1), pp.20–31. Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015.Construction project management. John Wiley & Sons. Sebastian, L. and Raghavan, V.S., 2015. Constraints on labour productivity-A case study. Taylor, S.J., Bogdan, R. and DeVault, M., 2015.Introduction to qualitative research methods: A guidebook and resource. John Wiley & Sons. The Economic Time, 2016. “India needs 7.3% labour productivity rise for 9% GDP growth, viewed 20- May-2018,https://economictimes.indiatimes.com/news/economy/policy/india- needs-7-3-labour-productivity-rise-for-9-gdp-growth/articleshow/50948924.cms Varajão, J., Dominguez, C., Ribeiro, P. and Paiva, A., 2014. CRITICAL SUCCESS ASPECTS IN PROJECT MANAGEMENT: SIMILARITIES AND DIFFERENCES BETWEEN THE CONSTRUCTION AND THE SOFTWARE INDUSTRY.Tehnicki Vjesnik/Technical Gazette,21(3). Walker, A., 2015.Project management in construction. John Wiley & Sons. Zheng, X., Le, Y., Chan, A.P., Hu, Y. and Li, Y., 2016. Review of the application of social network analysis (SNA) in construction project management research.International journal of project management,34(7), pp.1214-122. CQUniversity|PPMP20015Research Proposal Template11