Executive Summary 1 Part 1 1 1.0 BASIC PROJECT PARAMETERS OF LABUAN SQUARE PEOJECT 1 1.1 PROJECT STAKEHOLDERS 1 1.2 TIME FRAMES 2 1.3 PROJECT RESOURCES PROCUREMENT 11 1.4 COST 12 2.0 PROPOSED PROJECT MANAGEMENT PRACTICE/METHODOLOGY 18 2.6 3.0 PROPOSED APPROPRIATE PROJECT MANAGEMENT TECHNIQUES/TOOLS 19 4.0 PROPOSED PMBOK TOOLS 21 References 23 LIST OF FIGURES Figure 1:

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
LABUAN SQUARE REDEVELOPEMENT
ADVANCED PROJECT MANAGEMENT
ASSIGNMENT -2
SRM752
Name: *******
ID: ******

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Executive Summary
A redevelopment of Labuan Square (LSr) is described in this report, whose main purpose is to
demonstrate an individual’s ability of critical examination associated to the project management’s
impacts on LSr project. Further, the report will present the evaluation of Project Management
practice/methodologies and different Project Management techniques, where the PMBOK tools utilized
during the LSr project lifecycle are discussed. Finally, the necessary feasible techniques that can be
applied are recommended.
Document Page
Table of Contents
Executive Summary...................................................................................................................................................... 1
Part 1............................................................................................................................................................................... 1
1.0 BASIC PROJECT PARAMETERS OF LABUAN SQUARE PEOJECT............................................................1
1.1 PROJECT STAKEHOLDERS...................................................................................................................1
1.2 TIME FRAMES.......................................................................................................................................... 2
1.3 PROJECT RESOURCES PROCUREMENT...........................................................................................11
1.4 COST....................................................................................................................................................... 12
2.0 PROPOSED PROJECT MANAGEMENT PRACTICE/METHODOLOGY.......................................................18
3.0 PROPOSED APPROPRIATE PROJECT MANAGEMENT TECHNIQUES/TOOLS.......................................19
4.0 PROPOSED PMBOK TOOLS.........................................................................................................................21
References................................................................................................................................................................... 23
LIST OF FIGURES
Figure 1: Resource Cost............................................................................................................................................... 17
Figure 2: Total project cost............................................................................................................................................ 18
LIST OF TABLES
Table 1: Project plan of LSr............................................................................................................................................. 2
Table 2: Cost of each task............................................................................................................................................. 12
Table 3: PMBOK............................................................................................................................................................ 19
Table 4: Proposed tasks................................................................................................................................................ 21
Document Page

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Part 1
1.0 BASIC PROJECT PARAMETERS OF LABUAN SQUARE PEOJECT
This is a project of redevelopment of Labuan Square (LSr), a community containing various retail shops.
LSr is located in Norlane suburb in Victoria-3214. Project management plan helps to effectively achieve
this construction project and their methods, along with the management of resources. A project
management plan for the LSr project will be developed, including the effective project management
practice/methodology and techniques.
The basic parameters/boundaries of Labuan square project are the following (Howard, 2013):
1) Project stakeholders
2) Time Frames
3) Project Resources Procurement
4) Cost
1.1 PROJECT STAKEHOLDERS
The project stakeholders of LSr project are (Pampliega, 2013):
Stakeholders Duties
Client
To provide necessary information to help
the designers and the contractors.
To select professional Architect/designer.
To select good contractor.
To make sure that the project will be
completed in sufficient time and resources.
To notify appropriate authority about
specific projects.
Project manager
To manage the project’s various activities.
To supervise and monitor the project
activities.
To cross-check the progress, budget and
resources of the project.
To follow the building and safety codes.
Contractor and subcontractors
To set the deadlines and budget for the
project.
To coordinate with their subcontractors,
along with the plumbers, interior
1
Document Page
designers, electricians, and managing
employees.
To arrange the required materials.
Team members
To implement the activities of the project and
communicate the task’s progress information.
Laborers and employees
To follow the instructions of their higher
authorities to meet the goals.
Services suppliers
To facilitate high-quality products from the
manufacturers at a reasonable price.
Architect/designer
To provide an effective design of the building.
1.2 TIME FRAMES
This project is planned to be completed within 408 days. The time frame provides all
the necessary tasks to be covered in this project, including the responsible person
for the respective tasks. Each task has been set with a respective time limit to meet
the deadline of the project. The following table represents the project plan.
Table 1: Project plan of LSr
WBS Task Names Duration Start Finish Resource Names
0 Project Plan of Labuan Square 408 days February
14, 2020
September 7,
2021
1 Basic Conditions 7 days February
14, 2020
February 24,
2020
1.1 Getting notice to proceed and
sign the project contract 1 day February 14,
2020
February 14,
2020 General Management
1.2 Submission of bond and insurance
documents 1 day February 17,
2020
February 17,
2020
Project Manager,General
Management[25%]
1.3 Preparation and submission of
project schedule 1 day February 18,
2020
February 18,
2020
Project
Manager[25%],Scheduler
1.4 Preparation and submission of
values’ schedule 1 day February 19,
2020
February 19,
2020
General
Management[10%],Project
Manager
1.5 Getting approval to build 1day February 20,
2020
February 20,
2020
Project
Manager[50%],Procuremen
t[50%]
1.6 Submission of the preliminary 1day February 21, February 21, Project
2
Document Page
drawings of the shops 2020 2020 Manager[50%],Procuremen
t[50%]
1.7 Submission of monthly payment
request 1day February 24,
2020
February 24,
2020
2 Long Lead Procurement 7days February
25, 2020
March 4,
2020
2.1
Submission of shop’s drawings
and giving the order of long lead item
like steel
1 day February 25,
2020
February 25,
2020
Steel Erection Contractor
Management
2.2
Submission of shop’s drawings
and giving the order of long lead item
like roofing
1 day February 26,
2020
February 26,
2020
Roofing Contractor
Management
2.3
Submission of shop’s drawings
and giving the order of long lead item
like elevator
1 day February 27,
2020
February 27,
2020
Elevator Contractor
Management
2.4
Submission of shop’s drawings
and giving the order of long lead item
like plumbing
1 day February 28,
2020
February 28,
2020
Plumbing Contractor
Management
2.5
Submission of shop’s drawings
and giving the order of long lead item
like electric
1 day March 2,
2020
March 2,
2020
Electric Contractor
Management
2.6
Submission of shop’s drawings
and giving the order of long lead item
like HVAC
1 day March 3,
2020
March 3,
2020
HVAC Contractor
Management
2.7 Designing, fabrication and
delivery of steel 1 day March 4,
2020
March 4,
2020
Steel Erection Contractor
Management [50%], Steel
Erection Contractor [50%]
3 Site’s Mobilization 10 days March 5,
2020
March 18,
2020
3.1 Installing temporary power 2days March 5,
2020
March 6,
2020 Electric Contractor
3.2 Installing service of temporary
water 2days March 9,
2020
March 10,
2020 Plumbing Contractor
3.3 Site office Set up 2days March 11,
2020
March 12,
2020
Superintendent, Labor
Crew [10%]
3.4 Set up line & benchmark grading 2 days March 13,
2020
March 16,
2020 Survey Crew
3.5 Preparation of site-lay down yard
and temporary fencing 2days March 17,
2020
March 18,
2020
Site Grading
Contractor,Labor
Crew[10%]
4 Grade Site & its utilities 31days March 19,
2020
April 30,
2020
4.1 Cleaning the site and completing
digging work 5days March 19,
2020
March 25,
2020 Site Grading Contractor
4.2 Accessibility of stone site & 5days March 26, April 1, 2020 Site Grading Contractor
3

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
arranging the temporary space for
parking 2020
4.3 Rough grading of site (cut & fills) 5days April 2nd,
2020 April 8, 2020 Site Grading Contractor
4.4 Installation of storm drainage 5 days April 9, 2020 April 15,
2020 Site Grading Contractor
4.5 Install exterior fire line as well as
the building the fire riser 5days April 16,
2020
April 22,
2020 Plumbing Contractor
4.6 Completing final site’s grades 5days April 23,
2020
April 29,
2020 Site Grading Contractor
4.7 Erect the building batter boards &
building layout 1 day April 30,
2020
April 30,
2020 Survey Crew
5 Demolition process 69 days May 1, 2020 August 5,
2020
5.1 Removing the hazardous
materials 3 days May 1, 2020 May 5, 2020 Site Grading Contractor
5.2 Hazardous materials, PCBs, SMFs,
ODS and lead paint 3 days May 6, 2020 May 8, 2020 Concrete Crew,Site Grading
Contractor
5.3
Removing and disposing the
hazardous materials that are
identified from “'Hazardous Material
Survey & Management Plan” Robson
Intrusive report
3 days May 11,
2020 May 13, 2020 Site Grading Contractor
5.4 Monitoring of air 3 days May 14,
2020 May 18, 2020 Site Grading Contractor
5.5 Environmental Clearances to
continue the work of demolition 3 days May 19,
2020 May 21, 2020 Site Grading Contractor
5.6 UST (Underground Fuel Storage
Tank) 3 days May 22,
2020 May 26, 2020 Site Grading Contractor
5.7
Establishing & maintaining the
environmental control associated to
RAP
3 days May 27,
2020 May 29, 2020 Site Grading Contractor
5.8 UST (Excavating & stockpiling the
spoil at AEC) 3 days June 1st,
2020 June 3, 2020 Site Grading Contractor
5.9
Removing & disposing the valves,
vent lines and pipes associated to
UST
3 days June 4, 2020 June 8, 2020 Site Grading Contractor
5.10 Removing & disposing UST 3 days June 9, 2020 June 11,
2020 Site Grading Contractor
5.11 Validating the stockpile sampling
(1 round) 3 days June 12,
2020
June 16,
2020 Site Grading Contractor
5.12 Removing & disposing the
stockpile spoil, along with fees 3 days June 17,
2020
June 19,
2020 Site Grading Contractor
5.13 Extra validation sampling 3 days June 22,
2020
June 24,
2020 Site Grading Contractor
4
Document Page
5.14 Extra spoil disposal 3 days June 25,
2020
June 29,
2020 Site Grading Contractor
5.15 Uncertain Funds 3 days June 30,
2020 July 2, 2020 Site Grading Contractor
5.16 Demolition Work 3 days July 3, 2020 July 7th, 2020 Site Grading Contractor
5.17 Building demolition 3 days July 8th,
2020 July 10, 2020 Site Grading Contractor
5.18 Minor structure demolition work 3 days July 13,
2020 July 15, 2020 Site Grading Contractor
5.19 Wall work retaining (Brick) 3 days July 16,
2020 July 20, 2020 Site Grading Contractor
5.20 Courtyard Walls (Brick) 3 days July 21,
2020 July 23, 2020 Site Grading Contractor
5.21 Concrete Stairs 3 days July 24,
2020 July 28, 2020 Site Grading Contractor
5.22 Light Bollards, Light Poles, signs,
log barriers and so on 3 days July 29,
2020 July 31, 2020 Site Grading Contractor
5.23 Enclosing the gas meter brick 3 days August 3,
2020
August 5,
2020 Site Grading Contractor
6 Foundation work 56 days August 6,
2020
October 22,
2020
6.1 Excavation for foundation 4 days August 6,
2020
August 11,
2020
Site Grading
Contractor[50%]
6.2 Elevator pit excavation 4days August 12,
2020
August 17,
2020 Site Grading Contractor
6.3 Form column piers and
foundation spreading 4days August 18,
2020
August 21,
2020 Rough Carpenter Crew
6.4 Elevator related rough-in electric
& plumbing work 4days August 24,
2020
August 27,
2020
Plumbing
Contractor,Electric
Contractor
6.5 Formation of elevator pit walls 4 days August 28,
2020
September 2,
2020 Rough Carpenter Crew
6.6 Set up reinforcing & anchor bolts 4days September
3, 2020
September 8,
2020 Rough Carpenter Crew
6.7 Pour column piers & the
foundation 4days September
9, 2020
September
14, 2020 Concrete Crew
6.8 Pour concrete on the walls of the
elevator 4 days September
15, 2020
September
18, 2020 Concrete Crew
6.9 Curing of concrete on elevator
walls 4 days September
21, 2020
September
24, 2020 Labor Crew [10%]
6.10 Curing of piers and foundation 4 days September
25, 2020
September
30, 2020 Labor Crew [10%]
6.11 Strip wall forms 4 days October 1,
2020
October 6th,
2020 Labor Crew [10%]
5
Document Page
6.12 Strip column piers & foundation
forms 4days October 7th,
2020
October 12,
2020 Labor Crew
6.13 Installation of pneumatic tube in
the elevator pit 4days October 13,
2020
October 16,
2020 Elevator Contractor
6.14 Prepare & pour concrete floor
into elevator pit 4 days October 19,
2020
October 22,
2020 Concrete Crew
7 Steel Erection work 16days October 23,
2020
November
13, 2020
7.1
Erect the steel columns, beams &
the joist – in first and the second
floors
3 days October 23,
2020
October 27,
2020 Steel Erection Contractor
7.2 Erect the steel columns, beams
and joist – in third floor and the roof 3 days October 28,
2020
October 30,
2020 Steel Erection Contractor
7.3
Install miscellaneous iron and
bracing - in first and the second
floors
3 days November
2, 2020
November 4,
2020
Steel Erection
Contractor[75%]
7.4 Install miscellaneous iron and
bracing – in third floor and the roof 3 days November
5, 2020
November 9,
2020
Steel Erection
Contractor[75%]
7.5 Install stairs and various iron
railing 3 days November
10, 2020
November
12, 2020
Steel Erection
Contractor[50%]
7.6 Touch up paint on steel 1 day November
13, 2020
November
13, 2020
Steel Erection
Contractor[20%]
8 Forming and pouring of concrete -
Floors and the Roofs 66 days November
16, 2020
February 15,
2021
8.1 Form the second floor including
all the floor openings. 3 days November
16, 2020
November
18, 2020
Rough Carpenter
Crew,Labor Crew[20%]
8.2
Installation of rebar and the in-
floor utilities (including mechanical,
electrical, plumbing)
3 days November
19, 2020
November
23, 2020
Labor Crew[33%],Plumbing
Contractor[33%],Electric
Contractor[33%]
8.3 Pouring second floor’s slab 3 days November
24, 2020
November
26, 2020 Concrete Crew
8.4 Curing the second floor’s slab 3 days November
27, 2020
December 1,
2020 Labor Crew[10%]
8.5 Strip the forms from the second
floor’s slab 3 days December
2, 2020
December 4,
2020 Labor Crew
8.6 Form the third floor along with all
the floor openings 3 days December
7, 2020
December 9,
2020
Rough Carpenter
Crew[50%],Labor
Crew[20%]
8.7
Installation of rebar and the in-
floor utilities (including mechanical,
plumbing & electrical)
3 days December
10, 2020
December
14, 2020
Labor Crew[33%],Plumbing
Contractor[33%],Electric
Contractor[33%]
8.8 Pour third floor’s slab 3 days December
15, 2020
December
17, 2020 Concrete Crew
8.9 Curing third floor’s slab 3 days December
18, 2020
December
22, 2020 Labor Crew[10%]
6

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
8.10 Strip forms from the third floor’s
slab 3 days December
23, 2020
December
25, 2020 Labor Crew
8.11 Form roof slab including openings
of all the floors 3 days December
28, 2020
December
30, 2020
Rough Carpenter
Crew,Labor Crew[20%]
8.12
Installation of rebar and in-floor
utilities (including mechanical,
plumbing & electrical)
3 days December
31, 2020
January 4,
2021
Labor Crew[33%],Plumbing
Contractor[33%],Electric
Contractor[33%]
8.13 Pour roof slab 3 days January 5,
2021
January 7,
2021 Concrete Crew
8.14 Curing of roof slab 3 days January 8,
2021
January 12,
2021 Labor Crew[10%]
8.15 Strip forms from roof slab 3 days January 13,
2021
January 15,
2021 Labor Crew
8.16 Form first floor 3 days January 18,
2021
January 20,
2021 Rough Carpenter Crew
8.17 Installation of electrical
underground 3 days January 21,
2021
January 25,
2021 Electric Contractor
8.18 Installation of plumbing
underground 3 days January 26,
2021
January 28,
2021 Plumbing Contractor
8.19 Installation of rebar and the in-
floor utilities 3 days January 29,
2021
February 2,
2021
Labor Crew[33%],Plumbing
Contractor[33%],Electric
Contractor[33%]
8.20 Pour first floor slab 3 days February 3,
2021
February 5,
2021 Concrete Crew
8.21 Curing of first floor slab 3 days February 8,
2021
February 10,
2021 Labor Crew[10%]
8.22 Strip forms from the first floor
slab 3 days February 11,
2021
February 15,
2021 Labor Crew
9 Masonry Work 14 days February
24, 2021
March 15,
2021
9.1 Rough-in plumbing at toilets &
masonry walls 2 days February 24,
2021
February 25,
2021 Plumbing Contractor
9.2 Lay masonry at core, mechanical
& toilets 2 days February 26,
2021
March 1,
2021 Masonry Contractor
9.3 Installation of exterior masonry
task 2 days March 2,
2021
March 3,
2021 Masonry Contractor
9.4 Installation of roof drain 2 days March 4,
2021
March 5,
2021 Roofing Contractor
9.5 Installation of tile in the toilets 2 days March 8,
2021
March 9,
2021 Tile Contractor
9.6 Clean up of masonry work 2 days March 10,
2021
March 11,
2021 Masonry Contractor[50%]
9.7 Clean up of toilet room tiles 2 days March 12,
2021
March 15,
2021 Tile Contractor[50%]
7
Document Page
10 Carpentry work 6 days February
16, 2021
February 23,
2021
10.1 Installation of exterior sheathing
and metal studs 6 days February 16,
2021
February 23,
2021 Drywall Contractor
11 Roofing work 13 days March 16,
2021 April 1, 2021
11.1 Installation of flashing at the
parapet walls 3 days March 16,
2021
March 18,
2021 Roofing Contractor
11.2 Pouring the lightweight concrete
roof fills 3 days March 19,
2021
March 23,
2021 Roofing Contractor
11.3 Installation of seamless roofing
material 3 days March 24,
2021
March 26,
2021 Roofing Contractor
11.4 Spread stone ballast on the
seamless roof 3 days March 29,
2021
March 31,
2021 Roofing Contractor
11.5 Set up rooftop equipment 1 day April 1, 2021 April 1, 2021 HVAC Contractor
12 Closure of window wall & store
front 8 days April 2,
2021
April 13,
2021
12.1 Installation of window wall
aluminum & the glasses 2 days April 2, 2021 April 5, 2021 Window Contractor
12.2 Installation of interior stud walls
and the drywall 2 days April 6, 2021 April 7, 2021 Drywall Contractor
12.3 Installation of interior doors and
the hardware 2 days April 8, 2021 April 9, 2021 Finish Carpenter Crew
12.4 Installation of store front doors
and the hardware 2 days April 12,
2021
April 13,
2021 Window Contractor
13 Electrical work 12 days July 2, 2021 July 19, 2021
13.1 On the masonry walls rough-in
electrical 2 days July 2, 2021 July 5, 2021 Electric Contractor
13.2 On the drywall walls rough-in
electrical 2 days July 6, 2021 July 7, 2021 Electric Contractor
13.3 Pull wiring from conduit & set the
area transformer 2 days July 8, 2021 July 9, 2021 Electric Contractor
13.4 Install and terminate the electrical
devices 2 days July 12,
2021 July 13, 2021 Electric Contractor
13.5 Making electrical termination for
the HVAC equipment 2days July 14,
2021 July 15, 2021 Electric Contractor
13.6 Light fixtures Installation - testing &
cleaning 2days July 16,
2021 July 19, 2021 Electric Contractor
14 Elevators 12 days May 31,
2021
June 15,
2021
14.1 Setting elevator equipment in the
shafts 4days May 31,
2021
June 3rd,
2021 Elevator Contractor
14.2 In mechanical room, set the
equipment 4days June 4th,
2021
June 9th,
2021 Elevator Contractor
8
Document Page
14.3 Test & align the doors, including
the equipment 4days June 10,
2021
June 15,
2021 Elevator Contractor
15 Plumbing work 12 days June 16,
2021 July 1, 2021
15.1 On drywall walls rough-in
plumbing 3 days June 16,
2021
June 18,
2021 Plumbing Contractor
15.2 Tie-in the fire line riser & set the
valves 3 days June 21,
2021
June 23,
2021 Plumbing Contractor
15.3 Set up fixtures of plumbing and
trimming work 3 days June 24,
2021
June 28,
2021 Plumbing Contractor
15.4 Flushing, testing, & pipe cleaning,
also incorporate fixtures 3 days June 29,
2021 July 1, 2021 Plumbing Contractor
16 HVAC 20days July 20,
2021
August 16th,
2021
16.1 Set up mechanical room’s
equipment 4days July 20,
2021 July 23, 2021 HVAC Contractor
16.2 Rough-in mechanical on masonry
walls 4days July 26,
2021 July 29, 2021 HVAC Contractor
16.3 Rough-in mechanical on drywall
walls 4days July 30,
2021
August 4,
2021 HVAC Contractor
16.4 Installation of duct 4 days August 5,
2021
August 10,
2021 HVAC Contractor
16.5 Set up of HVAC trim and balance
system testing work 4 days August 11,
2021
August 16,
2021 HVAC Contractor
17 Finishes of Building 33 days April 14,
2021
May 28,
2021
17.1 Installation of millwork and the
wood trim work 3 days April 14,
2021
April 16,
2021 Finish Carpenter Crew
17.2 Wall painting and woodwork 3 days April 19,
2021
April 21,
2021 Painting Contractor
17.3 Installation of conduit at ceiling
plenum space 3 days April 22,
2021
April 26,
2021 Electric Contractor
17.4 Install the duct in the space of
ceiling plenum 3days April 27,
2021
April 29,
2021 HVAC Contractor
17.5 ceiling grid Installation 3days April 30,
2021 May 4, 2021 Drywall Contractor
17.6 ceiling tile Installation 3days May 5, 2021 May 7, 2021 Drywall Contractor
17.7 Sticking wallpapers 3 days May 10,
2021 May 12, 2021 Painting Contractor
17.8 Installation of building carpet 3 days May 13,
2021 May 17, 2021 Carpet Contractor
17.9 Hardware and the accessories
Installation 3 days May 18,
2021 May 20, 2021 Finish Carpenter Crew
17.10 Completion of interior and 3 days May 21, May 25, 2021 Landscape Contractor
9

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
exterior sod, including planting work 2021
17.11 Pave, curb, and stripe parking lot 3 days May 26,
2021 May 28, 2021 Paving Contractor
18 Last Clean-up and building
occupancy 8 days August 17,
2021
August 26,
2021
18.1 Installing hard tiles floor in the
common area 2 days August 17th,
2021
August 18th,
2021
18.2 Clean up of hard tile floorings 2days August 19th,
2021
August 20th,
2021 Tile Contractor
18.3 Removal of building debris and
completion of final cleaning 2days August 23rd,
2021
August 24th,
2021 Tile Contractor[50%]
18.4 Substantial date for completion 2days August 25th,
2021
August 26th,
2021 Labor Crew
19 Last Inspection Checking 8days August 27th,
2021
September
7th, 2021 Superintendent
19.1 Completion of elevator
inspection, including certifications 2days August 27th,
2021
August 30th,
2021 Elevator Contractor
19.2 Completion of architect
inspection 2days August 31st,
2021
September
1st, 2021
Superintendent[50%],Proje
ct Manager[50%]
19.3 Completion of local building-
agency inspections 2days September
2, 2021
September 3,
2021
Project
Manager[50%],Superintend
ent[50%]
19.4 Completion of fire-Marshal
inspections 2days September
6, 2021
September 7,
2021
Superintendent[50%],Proje
ct Manager[50%]
20 Completion of punch-list item
inspection 2days September
8, 2021
September 9,
2021
21 Getting occupancy certificates 2days September
10, 2021
September
13, 2021 Project Manager
22 Issuing the final documents, including
the warranties 6 days September
14, 2021
September
21, 2021 Project Manager
23 Issuing of final the payment request 6 days September
22, 2021
September
29, 2021
Project
Manager[33%],Accounting[
33%],General
Management[33%]
24 Management of Cost 1day April 25th,
2023
April 25th,
2023 Project Manager
25 Management of Risk 1day April 26th, April 26th, Project Manager
10
Document Page
2023 2023
26 Management of Quality 1day April 27th,
2023
April 27th,
2023 Project Manager
27 Project’s Integration Management 1day April 28th,
2023
April 28th,
2023 Project Manager
1.3 PROJECT RESOURCES PROCUREMENT
The resource procurement is divided into the following categories:
1) Material procurement
2) Labor procurement
11
Document Page
1.4 COST
The cost of each task is presented in the following table.
Table 2: Cost of each task
12

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
13
Document Page
14
Document Page
Resource Cost
Figure 1: Resource Cost
15

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Total Project Cost
Figure 2: Total project cost
2.0 PROPOSED PROJECT MANAGEMENT
PRACTICE/METHODOLOGY
The proposed project management practice/methodology applicable for LSr project to turn out as an
effective management is suggested to be Project management tools. This tool has the capacity to reflect
the professional attributes and aspirations of a professional and responsible project manager. The main
objective of the project management tools include supporting the plan of the managers in executing as
well as to control each task of the project management. Usually, the key tools are relied on by the
companies for ensuring the effective management of the project, which monitors the time to complete
the tasks and balances the workload of the staff, this results in optimal time management project
(Wrike.com, 2019). Therefore, the project management tools helps to enhance the efficiency of resource
and ensures to meet the project scope, especially for complex projects. However, the project
management tools like task assignments, project plans, Gantt charts, project budgets are used to plan
and schedule the project. It allows the manager to handle the most critical phases like accurate
estimation, planning, communicating, resource management, expense reporting, time management,
and tracking the project, and helps them, to precisely define the project goals and objectives
(Renolds, 2017).
16
Document Page
On the other hand, there are several project management techniques like the rational unified process,
agile project management, waterfall technique, critical path technique, extreme project management,
program evaluation and review technique, and critical chain technique (blog, 2019). The project
management techniques supports to manage any project easily and effectively. Some of the best
techniques used by the project managers are Gantt Chart, WBS, PERT (program evaluation and review
technique), Kanban, and Critical Path Method (CPM). These techniques help to establish collaboration
and allows improved workflow (Landau, 2019). Thus, it is essential to select an appropriate technique
and tools before the commencement of any project, and can guarantee its success.
3.0 PROPOSED APPROPRIATE PROJECT MANAGEMENT
TECHNIQUES/TOOLS
In this project, the project management techniques and tool utilized includes waterfall technique and
the project management tools, respectively.
The waterfall technique is referred as a traditional method which offers classic approach to the project,
and benefits to deliver clarity of understanding the project. The waterfall technique is characterized with
the Gantt chart, which helps to see the sequence of the tasks to be performed or completed. Gantt chart
can also be assist in monitoring the designed tasks and their performance (ProjectManager.com, 2020).
The project management tool includes planning, scheduling, communication, time management, and
finance & accounting. All these tools are beneficial to manage the project. The following are the ten core
PMBOK areas and the respective tools (Dzone.com, 2019) (Hartney, 2016).
Table 3: PMBOK
Knowledge
areas
Project management Processes’ Groups
Group for
initiating the
processes
Group to Plan the
processes
Group to
Execute the
processes
Group to
monitor &
control the
processes
Group
to close
the
process
Project-
Integrati
on
manage
ment
Development
of Project’s
Charter
Development of
Project’s
management plan
Directs &
manages the
tasks of a
project
Monitors and
controls the
tasks
of project
integration and
change control
Project
closure
17
Document Page
Project
Scope
Manageme
nt
Defines
scope
Creates
tasks
WBS
Validates
scope
Scope
statement
WBS
None Validates scope Closes
the
validatio
n of
scope
Project
Time
Manageme
nt
Defines the
sequence
of the
activities
Schedule
developme
nt
Milestone
developme
nt
Estimates
activities
Estimates the
duration of
activities
Critical path
Plan schedule
management
Precedence
Resources and
time estimation
Track
the tasks
Leads &
lags
Controlli
ng time
scheduli
ng
Close
Project
Cost
Manageme
nt
Estimates cost
Determines
the budget
Plans the cost
management
EVM
forecast
EVM
manageme
nt
Cost controlling Close
Project
Quality
Manageme
nt
Planning Quality
management
Assurance
of quality
Cost of
quality
Quality
controlling
Close
Project HR
Manageme
nt
None None Negotiating Performance Close
Project Planning Manages Model for Close
18

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Communic
ation
Manageme
nt
communication
management
information Communication
Project
Risk
Manageme
nt
Identifies
the risk
planning
Risk
managem
ent
Risk
categorizati
on
Risk
assessment
Risk controlling Close
Project
Procureme
nt
Manageme
nt
None None Conducting
procurement
Controlling
procurement
None
Project
Stakeholde
r
Manageme
nt
Stakeholder
identification
None None None Close
4.0 PROPOSED PMBOK TOOLS
The proposed PMBOK of LSr project is provided in this part. The proposed tasks are developed
depending on the project management techniques as well as tools. For instance, the used project
management technique is the waterfall technique, whereas the used tools include- Planning, scheduling,
communication, time management, and finance & accounting.
The following table represents the tasks that are proposed for this project:
Table 4: Proposed tasks
Proposed Project Management Tasks
Project Plan of Labuan Square
19
Document Page
Basic Condition
Long Lead Procurement
Site’s Mobilization
Grade the Site and its utilities
Demolition process
Foundation work
Steel Erection work
Forming and pouring of concrete - Floors and the Roofs
Carpentry work
Masonry Work
Roofing work
Closure of window wall & store front
Finishes of Building
Elevator work
Plumbing work
Electrical work
Heating and Ventilating – AC work
Last Clean-up and building occupancy
Last Inspection Checking
Completion of punch list item inspection
Getting certificate of occupancy
Issuing the final documents, including the warranties
Issuing of final the payment request
Cost Management
Risk Management
Quality Management
Integration Management of a Project
The below listed tasks represent the collection of processes in the PMBOK (Westland, 2019).
The proposed and recommended management practice contains risk management, integration
management, cost management and quality management. They are planning, scheduling,
20
Document Page
communication, time management, and finance & accounting tools which assists in coordinating every
single task, its management and respective costs. Therefore, the project parameters are cost, quality and
time.
References
blog. (2019). Most Useful Project Management Tools and Techniques. [online] Available at:
https://www.actitime.com/project-management/project-management-tools-and-techniques/
[Accessed 14 Feb. 2020].
Dzone.com. (2019). Project Management Techniques and Tools Made Simple - DZone Agile.
[online] Available at: https://dzone.com/articles/project-management-techniques-and-tools-
made-simpl [Accessed 14 Feb. 2020].
Howard, B. (2013). Microsoft Project 2013. Sebastopol (CA): O'Reilly Media.
Hartney, J. (2016). The 10 PMBOK Knowledge Areas. [online] ProjectEngineer. Available at:
https://www.projectengineer.net/the-10-pmbok-knowledge-areas/ [Accessed 14 Feb. 2020].
Landau, P. (2019). 5 Project Management Techniques Every PM Should Know. [online]
ProjectManager.com. Available at: https://www.projectmanager.com/blog/project-
management-techniques-for-every-pm [Accessed 14 Feb. 2020].
Pampliega, C. (2013). Stakeholder Management in the Construction Sector. [online] SALINERO
PAMPLIEGA. Available at: http://salineropampliega.com/2013/10/stakeholder-management-in-
construction.html [Accessed 14 Feb. 2020].
ProjectManager.com. (2020). Waterfall Methodology in Project Management. [online] Available
at: https://www.projectmanager.com/software/use-cases/waterfall-methodology [Accessed 14
Feb. 2020].
Renolds, N. (2017). The Importance of Project Management Tools. [online] Bizfluent. Available
at: https://bizfluent.com/info-8320824-importance-project-management-tools.html [Accessed
14 Feb. 2020].
21

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Westland, J. (2019). The 10 Project Management Knowledge Areas - (PMBOK). [online]
ProjectManager.com. Available at: https://www.projectmanager.com/blog/10-project-
management-knowledge-areas [Accessed 14 Feb. 2020].
Wrike.com. (2019). What Are Project Management Tools?. [online] Available at:
https://www.wrike.com/project-management-guide/faq/what-are-project-management-tools/
[Accessed 14 Feb. 2020].
22