Table of Contents Introduction......................................................................................................................................3 Evaluate the common challenges faced by the Procurement and Supply chain managers and how to overcome them............................................................................................................................3 Appraise the main contracting issues for major programs and projects for successful completion5 Critique the main legal issues that relate to the formation of relationships in supply chain...........7 Appraise the legal implications of contractual non performance in procurement and supply........8 Conclusion.......................................................................................................................................9 Recommendations............................................................................................................................9 References......................................................................................................................................11
Introduction Construction projects are often complicated and needs to be properly handled in order to ensure that the contract is successful that helps the project as well. The project management is a process through which an activity is effectively organised, planned and controlled and executed to achieve the key objectives of the project (Kötz, 2017). There could be number of problems in the project management and hence it is extremely important to manage them effectively to make sure the project is successfully completed. The present case of A Rive Venues is quite clear. There are no problems understanding that the organisation has suffered issues due to the organisations it hired and they did not deliver. It is extremely important to note that in project management each and every organisations or entities have to perform in order to achieve the overall objectives of the project and in this case companies hired by A-Rive Venues have not operated well. The organisation A-Rive Venues have faced negligence in deliverance of objectives because the sub contractors like Construct it quick and “Brights” have not performed well. In this scenario the legal aspects that A Rive could implement to safeguard them from liability is discussed. Evaluate the common challenges faced by the Procurement and Supply chain managers and how to overcome them The organisation A-Rive Venues were to focus on developing few temporary spaces for the Olympics and the organisation received Government contract to do so with revised contracts and negotiated price but the organisation was not able to complete the project at the given time because the organisation faced several problems and one of the major being procurement and supply chain problem. The managers of A-Rive Venues focused on getting its supply chain to operateinthebestpossiblemannertoachievetheobjectivesbutitfailedbecausethe organisations with whom the organisation contracted failed to deliver the product on time. This is where the law and legal aspects come into the picture (Boyle, 2017).One of the major supplier and procurement problems that the organisation failed to pick up was the ability to ensure that the suppliers were completely legally and financially qualified to deliver the product. It is extremely important to note that in project management supplier relationship is considered extremely important but it is also important to have a professional relationship with them which the organisation in the present case completely failed to have which clearly affected the entire
project. From the case it could be said that there have been number of problems that the organisation faced and did not make an attempt to change them even though there was significant possibility of facing disastrous results (Heldman, 2018). Having a good relationship with the supplies means the organisation will be able to stretch itself to take risks because it will help the organisation to make suitable decisions for the project and also support it effectively. In this case A-Rive did take effective risks but it was unfortunate that the organisations taking part in the project have not shown complete transparency while taking the project in the hands. Another major aspect which comes into the picture in this case is there was not proper project risk planning done by the organisation A-Rive because when one organisation was announced bankrupt and was not in a position to continue the operations it took the organisation significant amount of time to manage another new supplier of services and in elevated prices which also added to the problems in the project. It is important to consider the position of the organisation in this scenario because it would largely help the organisation to ensure the company is able to get the best possible team to work for them. Risk management is extremely important for every organisation and for project management it becomes a priority because it is the stakeholders’ investment at stake (Turner, 2016). Strategy selection is another major problem that the supply chain managers of the organisation has had to face because it clearly showed that the organisation A-Rive hasn’t experienced this big a tender and hence has lesser experience to manage projects like this. It is important to note thattheorganisationwouldrequiretakingmoreresponsibilitieswhichwouldhelpthe organisation to get the entire project done responsibly and successfully. The professionals of A- Rive have suffered to make effective decisions for the organisation which is because the organisation has not been able to decide on their strategic system properly (Heagney, 2016). This was a bigger contract and the organisation had to be extremely focused on making the right decisions which they did not do. It is extremely important for the organisation to make sure that legally the paperwork should have been done in the best possible manner which would have helped the organisation to at least avert this kind of scenario. Another major problem that the supply chain managers of the organisation A-Rive have faced is managing the stakeholders. The end result for the organisation has not been good because the company has not been able to manage the project successfully which has led to minor injury to
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
the celebrity commentator which the organisation is going to get back through legal procedures and the organisation professionally has been devastated because its professional image has also got tainted which would affect its future contracts as well. It is the responsibility of the organisation to ensure that the company is able to manage its stakeholders in the best possible manner so that they are always informed about the progress being made by the organisation. It could be said that A-Rive should have been more proactive in communicating with the stakeholders key to the organisational success because it would help the organisation to get the best possible result.Hence it could be said that the main focus of the supply chain managers is to build a strong supplier management relationship which would help to make sure the organisation is able to perform effectively as well as evaluate the same whenever required for the best possible operation of the project (Steyn et al., 2016). In this case A-Rive probably did not have an effective evaluation system in place as the organisation was not able to manage the supplier relationship properly and in return got deeply affected by the overall operations of the project. The responsibility of the organisation A-Rive Venues stands to be important in this case. The main responsibility and aim of the project stands to be the deliverance of objectives set by the major stakeholders of the project. In this case the prime aim of the organisation was to deliver four different temporary venues for the Olympics Basketball venue. As per legal contract the main responsibility of the organisation A-Rive stands to be to deliver the venues within time failing which an organisation could be sued for breaching the contract. There are significant project management laws which would have to be implemented in order to make sure the project is successful. It is indeed a huge aspect for the organisation to consider the contract strategy effectively. One of the major aspects in project management is contract. It is important that the organisation hiringanother organisationfocuseson havingan excellentunderstanding of contract law in the project management (Kerzner and Kerzner, 2017). Appraise the main contracting issues for major programs and projects for successful completion According to the Contract Act 1990 (applicable) it is important for the project organisation to ensure that there are certain key conditions apart from the basic elements of contract to make sure the contract is strongly bound. As per the principal contract that took place between A-Rive
and the Government, it is important to note that the organisation will have to be held responsible for the overall completion of the project. It can be said that the Project manager of the organisation A-Rive should have been much more careful in order to ensure that the organisation is able to communicate with the sub contractors effectively and get the best possible result from the organisation. One of the major cases where the PM was held responsible for the failure of a project isRoyal Brompton Hospital NHS Trust–v- Hammond(2003) 88 Con LR 1 in 2003 where the judge addressed that the main role of the PM is to coordinate the project as per the interest of the client because the PM directly represents the project management organisation (O'Sullivan and Hilliard, 2016). It cannot be denied that the organisation should have been able to create a certain level of professional accountability among the sub contractor even. In the present case it is extremely clear that one of the major parts of contract that condition has not been properly highlighted. In the present case it is extremely important to note that the organisation A-Rive contracted with the organisation “Construct it Quick” and “Brights” for the construction and electrical operations. It is extremely important to note that the organisation completely failed to create conditions for the work to be operated effectively. As per the caseSix Continents Retail Limited v Carford Catering Limited[2003] EWCA Civ 1790 it also remains to be the responsibility of the sub contractor to make sure all the installations are done effectively as per the proper guidelines which did not happen in this case or else the celebrity commentator wouldn’t have been injured. It is extremely important for the organisation to ensure A-Rive to have a strong condition which would help to operate effectively and get the project completed successfully (Clack, Bakshi and Braine, 2016). Contract condition stands to be an extremely important aspect to be discussed in this case because the contract procedure for projects could be bespoke with numerous conditions being inserted in the form which helps organisations to ensure success in the project. The confusion in the contract has been clearly shown in the caseCarillion Construction Ltd v Woods Bagot Europe Ltd & Ors [2016] EWHC 905 (TCC) (28 April 2016)where there has been problems with the sub contractor because the bespoke form has not been filled properly which clearly eliminated some of the condition for an organisation to operate in favor of another organisation. This case showed that improper insertion of clauses and conditions might affect and delay entire project and hence it is
extremely important for the organisations like A-Rive Venues to make sure the conditions and contracts are effectively framed for better results in the future (Smits, 2017). Critique the main legal issues that relate to the formation of relationships in supply chain It is important to note that the liability in the project is an extremely important aspect and have to be kept in mind by the organisation A-Rive Venues. The liability of the failure of the project entirely goes to the company as the client that is the government will sue the organisation as it doesn’t know anyone else related to the project. It is important to note that the organisation will require focusing on implement strong statement ahead to safeguard its interest. The liability of the organisation would be held from the point of view of financial matters. It is important to note that the organisation A-Rive could claim for financial compensation from the organisation Construct it Quick and even from Brights stating the fact that there have been professional negligence. It is important to note in this case that professional negligence is an action which is not done in line with the project management activities and since Brights did not follow the guidelines during the installation it could be sued pretty unlike the casePeter Kellie and Kelly Kellie v Wheatley & Lloyd Architects Limited[2014] EWHC 2886 (TCC) (Stone and Devenney, 2017). On the other hand duty is another major aspect which would have to be kept in mind by the organisation A-Rive in this case because the organisation had the duty of completing the project within the given time and it failed and hence assumption of responsibility and duty comes into the picture which is pretty similar to the case ofHunt v Optima (Cambridge) Ltd[2014] EWCA Civ 714 (Cartwright, 2016). Even though the organisation was not directly involved in the construction and the project was passed to sub contractors the organisation A-Rive clearly has liability for the failure of the project which was clearly analysed inthe case Sinclair v Woods of Winchester [2005]. This case clearly analysed to what extent the liability of the contractor exists when a project is developed with defects or the project failed to complete within time. The UK courts do implement significant research on understanding whether the breach in contract is the key reason for losses happened to the project organisations which has been clearly showed in the case ofGreat Eastern Hotel Co Ltd v John Laing Construction Ltd & Anor [2005] EWHC 181. This case has helped to implement common sense on the cause of loss (Adriaanse, 2016).
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Appraise the legal implications of contractual non performance in procurement and supply InGreaves v Baynham Meikle 1975it was clear that the organisation is accused mainly assessing the purpose and level of diligence and duty showed towards a project. In this case it is clear that the organisation has not been able to show proper skills in selecting the subcontractor which clearly questions the role and duty of the contractor organisation in this case A-Rive venues. The law deals with the responsibility of design and hence the electrical defect might completely go against the parent contractor and hence it is extremely important that the company is able to prepare strong statements against non performance under contract (Adriaanse, 2016). As the contract mainly was to develop temporary venues for the London Olympics and the organisation failed to do that the client in this case the Government would be pretty clear to sue the organisation and repudiate the contract as it happened in the caseBettini v Gye(1876) QBD 183 where the court rightly breached the contract because the acceptor of the contract was not able to perform as per the contract (Burnett, 2016). TheHong Kong Fir Shipping v Kawasaki Kisen Kaisha[1962] 2 QB 26Court of Appealalso pretty clearly highlighted that the organisation suffering loss on the contract will be able to breach the contract and clearly call for compensation which is the natural action that could be taken in order to ensure proper verdict. The concept of innominate terms was brought in for effective analysis of the case (Smits, 2017). Hence in this case it could be considered that the organisation A-Rive venue was not able to act as per the contractual obligation and hence it is exposed to legal obligation on the basis of non performance. In this case the organisation might not get a second chance in the contract because the Olympics already started when the case exposed and the organisation didn’t have much time to recover the damages and hence the client would want a complete compensation for the entire project. Hence it is extremely important that the organisation look for statements that would be able to defend themselves (Haapio and Hagan , 2016).
Conclusion It is extremely important for the organisation to implement certain key steps to mitigate the challenges and resolve the existing problems to successfully complete the task. One of the major problems that the organisation faced during the project is the selection of service providers. The organisation needs to implement an effective strategy which would help the company to get the best possible result. Firstly it is important for the organisation to analyse the sub contractors properlygettingtheiroverallfinancialstatementstocheckthefinancialstabilityofthe organisation which would help the company to select the right vendor for the job that qualifies all the criteria especially the financial stability. It cannot be denied that the main contractor in this case A-Rive Venue is responsible for the design of the entire project and hence it will have to take the responsibility for making it right again and hence the design of the overall project especially construction and electrical system has to be reassessed which would help to mitigate the existing challenge and pressure (Steyn et al., 2016). Recommendations As the organisation is facing all the liabilities it is important that the organisation revisit their contract clauses and revisit the negotiations to make changes in certain clauses. The exclusion clause of the project would have to be remade. The organisation should focus on changing the exclusion clause in a case to make them completely free of liability in case the sub contractors fail to complete the project as shown in the caseL'Estrange v Graucob [1934] 2 KB 394.It is important for the organisation to make sure that the organisation is partially or completely saved from the issue. It could be still negotiated with the client to include this clause to partially take the responsibility and hence this will largely help to mitigate the impact on the organisation. Conditions have to be clearly mentioned in the contracts with the sub contractors which would help the organisation to make sure the entire project runs well and without any kind of hassle (Cartwright, 2016). The organisation ‘Brights” could be accused of knowing the defect or completely overlooking it showing negligence of performance as it was showed in the case ofIn Plant v Adams [2000].In this case the sub contractor was accused of negligence in performance as it also has a significant role to play and also have the duty in the safety and security of the people and hence it is clear from this case that “Brights” could be charged and compensation could be asked for the damage caused to the organisation A-Rive Venue. Hence revising the
contracts formed with these organisations should be revisited and key clauses will have to be inserted in terms of exclusion and sharing of liability which would help the organisation to reduce much of the pressure and get these sub contractors to act proactively which would help to achieve the project deliverables in the best possible manner (Monateri, 2017). In thecase Newton Abbott Development Co. Ltd v Stockman Brothers [1931]it was stated that the organisation facing loss from a project is clearly entitled to get compensation from the sub contractors involved in non performance.Overall it could be said that the organisation A-Rive Venue will have to seek legal help in order to clearly make the claimant understand the duties, liability, duty and to what extent it feels it has the responsibility in the failure of the project which would help the organisation to mitigate the legal challenge and in order to complete the project successfully the organisation needs to reinstate the subcontractors analysing the background properly and understanding their performance abilities before giving the project (Stone and Devenney, 2017).
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
References Adriaanse, M.J., 2016.Construction contract law. Palgrave Macmillan. Boyle, G., 2017.Design project management. Routledge. Burnett, R., 2016.Outsourcing IT-the legal aspects: Planning, contracting, managing and the law. Routledge. Cartwright, J., 2016.Contract law: An introduction to the English law of contract for the civil lawyer. Bloomsbury Publishing. Clack, C.D., Bakshi, V.A. and Braine, L., 2016. Smart contract templates: foundations, design landscape and research directions.arXiv preprint arXiv:1608.00771. Haapio, H. and Hagan, M., 2016. Design patterns for contracts. Heagney, J., 2016.Fundamentals of project management. AMACOM Div American Mgmt Assn. Heldman, K., 2018.PMP: project management professional exam study guide. John Wiley & Sons. Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kötz, H., 2017.European contract law. Oxford University Press. Monateri, P.G. ed., 2017.Comparative Contract Law. Edward Elgar Publishing. O'Sullivan, J. and Hilliard, J., 2016.The law of contract. Oxford University Press. Smits, J.M. ed., 2017.Contract law: a comparative introduction. Edward Elgar Publishing. Steyn,H.,Dekker,A.H.,Kuschke,B.,VanEck,B.P.S.andVisser,K.,2016.Project management: A multi-disciplinary approach. FPM Publishing. Stone, R. and Devenney, J., 2017.The modern law of contract. Routledge. Turner, R., 2016.Gower handbook of project management. Routledge.