ProductsLogo
LogoStudy Documents
LogoAI Grader
LogoAI Answer
LogoAI Code Checker
LogoPlagiarism Checker
LogoAI Paraphraser
LogoAI Quiz
LogoAI Detector
PricingBlogAbout Us
logo

Legacy Way Tunnel Project: Construction of 4.6 km tunnel in Brisbane

Verified

Added on  2023/06/03

|6
|1456
|299
AI Summary
The Legacy Way Tunnel project aimed to improve traffic flow and connectivity between metropolitan areas and the airport in Brisbane, Australia. The 4.6 km tunnel was constructed with advanced technology and minimized environmental damage. The project was completed successfully within a period of 5 years and received several awards. The project schedule, deliverables, payment schedule, sub-contractors, stakeholders, applicable standards, acceptance criteria, and special requirements are discussed in detail.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Statement of Work Student Name:
Project Summary
The project aimed in construction of a tunnel of length 4.6 km in the city of Brisbane Australia. The project was
undertaken and led by ACCIONA along with the BDM construction. The construction company is known for
their sustainability in the construction process. The aim of this project was to improve the traffic flow and
improvement in the connection between the metropolitan areas the airport of the city. With the construction of
the Legacy way tunnel, it has become easier to manage the traffic and reducing the entire journey time with a
negligible impact on the local habitat. The project was implemented with advanced technology. During the
construction of the tunnel, the environmental damage was minimized as much as possible. The boring of the
tunnel was carried out by two enormous tunnel boring machines. The boring took almost 17 months. The
project followed a planned approach that led to the successful completion of the project. The service description
of the project is represented in the following section.
Service Description
The project was implemented with an aim of reducing the road congestions and improving the transport
processes. The tunnel linked various parts of the city along with the airport to make those places easily
accessible. The tunnel that is built is 4. Km long and it connects the western Freeway at Toowong along with
the Inner City Bypass in the Kelvin Grove. The project team and the contractors optimized the project design
for enhancing the user experiences for the motorists. The project facilitated the public transport services which
were really helpful for the daily passengers. The project was needed for improvement of the daily transport. The
project was huge success as the project has owned several awards till date. The list of awards that the project
received includes International Tunneling Project of the year. The schedule and the deliverables of the project is
represented in the following section.
Deliverables
The major deliverables of the project are represented in the following section.
Deliverables Schedule
The deliverables and the overall activities in the project is represented in the following table-
WBS Task Name Duration Start Finish
0 Legacy Way Tunnel 1369 days Mon 12-04-10 Thu 09-07-15
1 Project Starts 1 day Mon 12-04-10 Mon 12-04-10
2 Project Planning 140 days Tue 13-04-10 Mon 25-10-10
2.1 Gathering the Requirements of the
Project 1 month Tue 13-04-10 Mon 10-05-10
2.2 Understanding the Requirements
of the Project 3 months Tue 13-04-10 Mon 05-07-10
2.3 Estimation of the time 2 months Tue 06-07-10 Mon 30-08-10
2.4 Development of Project Plan 1 month Tue 31-08-10 Mon 27-09-10
2.5 1 month Tue 28-09-10 Mon 25-10-10
3 Project Initiation 80 days Tue 31-08-10 Mon 20-12-10
3.1 Project Scheduling 1 month Tue 31-08-10 Mon 27-09-10
3.2 Budget estimation of the Project 1.5 months Tue 28-09-10 Mon 08-11-10
3.3 Development of Statement of
Work 15 days Tue 09-11-10 Mon 29-11-10
3.4 Approval of Statement of Work 15 days Tue 30-11-10 Mon 20-12-10

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4 Project Implementation 880 days Tue 21-12-10 Mon 05-05-14
4.1 Site preparation 4 months Tue 21-12-10 Mon 11-04-11
4.2 Boring Tunnels 17 months Tue 12-04-11 Mon 30-07-12
4.3 Start of Construction 39 months Tue 12-04-11 Mon 07-04-14
4.4 Completion of the Project
Completion 1 month Tue 08-04-14 Mon 05-05-14
5 Project Closure 297 days Tue 06-05-14 Wed 24-06-15
5.1 Evaluation of the Project 3 months Tue 06-05-14 Mon 28-07-14
5.2 Reporting and Documentation 4 months Tue 29-07-14 Mon 17-11-14
5.3 Payment Completion 6 months Tue 18-11-14 Mon 04-05-15
5.4 Resource Release 37 days Tue 05-05-15 Wed 24-06-15
6 Opening of the Tunnel 1 day Thu 25-06-15 Thu 25-06-15
7 Project Ends 10 days Fri 26-06-15 Thu 09-07-15
The Schedule Gantt chart of the project is represented in the following table-
Figure 1: Representing the Gantt chart of the project
Document Page
(Source: Generated by Author using MS project)
The work activities marked in red in the Gantt chart above depict the critical path of the project
Period of Performance
The period of performance of the project is represented in the following table. The project was implemented for
almost 5 years and the project was successful.
WBS Task Name Duration
0 Legacy Way Tunnel 1369 days
1 Project Starts 1 day
2 Project Planning 140 days
2.1 Gathering the Requirements of the Project 1 month
2.2 Understanding the Requirements of the Project 3 months
2.3 Estimation of the time 2 months
2.4 Development of Project Plan 1 month
2.5 1 month
3 Project Initiation 80 days
3.1 Project Scheduling 1 month
3.2 Budget estimation of the Project 1.5 months
3.3 Development of Statement of Work 15 days
3.4 Approval of Statement of Work 15 days
4 Project Implementation 880 days
4.1 Site preparation 4 months
4.2 Boring Tunnels 17 months
4.3 Start of Construction 39 months
4.4 Completion of the Project Completion 1 month
5 Project Closure 297 days
5.1 Evaluation of the Project 3 months
5.2 Reporting and Documentation 4 months
5.3 Payment Completion 6 months
5.4 Resource Release 37 days
6 Opening of the Tunnel 1 day
7 Project Ends 10 days
Payment Schedule
The payment of the project was done according to the achievement of each milestone of the project. For
accurate payment of the resources, the budget was estimated at the initiation phase of the project. All the
payments that were associated with the project were completed within 15th of each month. The estimated budget
of the project was $1.5 billion.
Sub-Contractors
Sub contractors played a major role in successful completion of the project. The project was led by the
contractors and the sub contractors of ACCIONA. The construction part of the project was mainly led by the
BDM construction and Ghella.
Document Page
Representatives
The main representatives of this project were Brisbane City Council along with the Queensland Motorways.
The main stakeholders of the project include ACCIONA Infrastructure and BMD construction that is located in
Brisbane.
\
SUB SECTIONS
I. Risks and Assumptions:
The risk associated that were associated with this project are as follows-
Risk Severity Probability of Occurrence
Schedule Risk High High
Budget Risk Medium High
Resource Shortage High Medium
Risk of scope creep Low Low
The assumptions associated with the project are as follows-
1. The project should be completed within the set budget of the project
2. It is assumed that the schedule estimated for the project is accurate for project implementation
II. Stakeholders
The main stakeholders associated with the project are as follows-
Stakeholder Interest Influence
Project Manager medium Medium
ACCIONA High High
BDM Construction Medium High
Brisbane City Council High High
Contractors Medium Medium
Sub Contractors Medium Medium
III. Applicable Standards
The applicable standards associated with the implementation of the project are as follows-
1. AS 4915-2002/Amdt 1-2005 for accurate project management
2. AS ISO 10006-2003 for accurate quality management
IV. Acceptance Criteria
The acceptance criteria that was set for this project are as follows-
1. The project should abide by the applicable standards
2. The project should be completed within the estimated project schedule
3. The project should be able to achieve its set objectives.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
V. Special Requirements or out of scope items:
There were certain special requirements of the project that were considered as out of scope for the project These
are as follows-
1. The project was needed to be completed as early as possible
2. The tunnel boring took longer than expected.
Document Page
Bibliography
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management
Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management
performance and project success. International journal of project management, 32(2), pp.202-217.
Walker, A., 2015. Project management in construction. John Wiley & Sons.
1 out of 6
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]