Literature Review of Project Delivery Models
VerifiedAdded on  2023/04/10
|10
|1713
|240
AI Summary
This literature review explores different project delivery models in construction projects, including design-bid-build, construction management multi-prime, construction management-at-risk, design-build, and integrated project delivery. It discusses the advantages and disadvantages of each model and provides a case study on the use of integrated project delivery in a children's hospital expansion project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Literature Review of Project Delivery Models
Contents
Introduction................................................................................................................................1
Delivery Models.........................................................................................................................1
Design-Bid-Build...................................................................................................................2
Construction Management Multi-Prime (CM MP)................................................................3
Construction Management-at-Risk (CMAR).........................................................................3
Design-Build (DB).................................................................................................................4
Integrated Project Delivery.....................................................................................................5
References..................................................................................................................................6
1
Contents
Introduction................................................................................................................................1
Delivery Models.........................................................................................................................1
Design-Bid-Build...................................................................................................................2
Construction Management Multi-Prime (CM MP)................................................................3
Construction Management-at-Risk (CMAR).........................................................................3
Design-Build (DB).................................................................................................................4
Integrated Project Delivery.....................................................................................................5
References..................................................................................................................................6
1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Literature Review of Project Delivery Models
Introduction
Project delivery in construction projects involves planning, designing, construction, and
project management services like organizing, planning, execution and management. A typical
project involves three key internal including owner, designer, and developer that have major
impacts on the project outcome. They need to take critical decisions on the project such as
method of procurement to use, contract types to develop and delivery method to use. When
taking decisions about the delivery systems, these stakeholders may have different
perspectives as every delivery system may have different set of advantages and disadvantages
for each of them.
Delivery Models
Common types of delivery systems used worldwide are design bid build construction
management multi-prime, construction management at risk, design build, design build
operate/maintain, and an integrated project delivery model. Some benefits provided by a
specific delivery model could be associated with all the three types of stakeholders but there
are no absolute values. A design-build project would have a positive impact on the project
schedule which can benefit all. Integrated Product Delivery (IPD) increases process
efficiencies as well as reduce the risks of litigation. Thus, it is seen as the best delivery
system by many contractors. Based on the different perspectives of the people on these
benefits decision can be taken on which delivery model to use on a project. Any delivery
model that is chosen must try to reduce the wastage on the project and may even be changed
if currently used delivery system is causing wastage (Fischer, Reed, Khanzode, & Ashcraft,
2012).
2
Introduction
Project delivery in construction projects involves planning, designing, construction, and
project management services like organizing, planning, execution and management. A typical
project involves three key internal including owner, designer, and developer that have major
impacts on the project outcome. They need to take critical decisions on the project such as
method of procurement to use, contract types to develop and delivery method to use. When
taking decisions about the delivery systems, these stakeholders may have different
perspectives as every delivery system may have different set of advantages and disadvantages
for each of them.
Delivery Models
Common types of delivery systems used worldwide are design bid build construction
management multi-prime, construction management at risk, design build, design build
operate/maintain, and an integrated project delivery model. Some benefits provided by a
specific delivery model could be associated with all the three types of stakeholders but there
are no absolute values. A design-build project would have a positive impact on the project
schedule which can benefit all. Integrated Product Delivery (IPD) increases process
efficiencies as well as reduce the risks of litigation. Thus, it is seen as the best delivery
system by many contractors. Based on the different perspectives of the people on these
benefits decision can be taken on which delivery model to use on a project. Any delivery
model that is chosen must try to reduce the wastage on the project and may even be changed
if currently used delivery system is causing wastage (Fischer, Reed, Khanzode, & Ashcraft,
2012).
2
Literature Review of Project Delivery Models
Design-Bid-Build
Figure 1: Design-bid-build
This is the traditional method of delivery system in which separate contracts are created for
separate project participants. In Design-Bid-Build model of project delivery, two types of
contracts are formed, one for the architect and other for a main contractor to take care of
other deliveries. The work follows a linear sequence on this project and thus have advantages
like low cost and greater control over design. A typical design-build project would follow a
linear sequence of execution starting with engagement of a qualified engineer, and then
designing, obtaining bids for execution, and engaging contractor for project completion.
There can also be some variations from this sequence such as addition of performance
measures during designing and building of contractors based on performance specifications
(Beck group, 2015).
However, because of this linearity, the project can be very time consuming to execute. Also,
the project owner is responsible for any cost changes on the project and the contractor may
not have any say on it. Thus, the contract favours the owner more than the contractor
(Rawlins & Godwin, 2015).
The selection of right designer is critical for such a project as remining project stages would
largely depend on the efficiency of the project design. Thus, an engineer involved in this
work is carefully selected considering certifications of quality standards, experience, vendor
3
Design-Bid-Build
Figure 1: Design-bid-build
This is the traditional method of delivery system in which separate contracts are created for
separate project participants. In Design-Bid-Build model of project delivery, two types of
contracts are formed, one for the architect and other for a main contractor to take care of
other deliveries. The work follows a linear sequence on this project and thus have advantages
like low cost and greater control over design. A typical design-build project would follow a
linear sequence of execution starting with engagement of a qualified engineer, and then
designing, obtaining bids for execution, and engaging contractor for project completion.
There can also be some variations from this sequence such as addition of performance
measures during designing and building of contractors based on performance specifications
(Beck group, 2015).
However, because of this linearity, the project can be very time consuming to execute. Also,
the project owner is responsible for any cost changes on the project and the contractor may
not have any say on it. Thus, the contract favours the owner more than the contractor
(Rawlins & Godwin, 2015).
The selection of right designer is critical for such a project as remining project stages would
largely depend on the efficiency of the project design. Thus, an engineer involved in this
work is carefully selected considering certifications of quality standards, experience, vendor
3
Literature Review of Project Delivery Models
partnerships, and pricing strategy compared to competition. Considerations also have to be
made for product knowledge, time available for outsourcing work, and needs for project
management (Walewski, G. Edward Gibson, & Jasper, 2001).
Construction Management Multi-Prime (CM MP)
Figure 2: Construction Management Multi-Prime
In this type of project delivery mode, several different contracts are made for architect,
contractors and subcontractors. This model also lets the project owner retain the control over
the design and gives the advantage of low cost of execution. However, it fast tracks the
project by involving contractors at early stages. However, owner is responsible for making
any changes in scope and the subcontractor may not be involved in the process which leads to
a lac of oversight on the project (Rawlins & Godwin, 2015).
4
partnerships, and pricing strategy compared to competition. Considerations also have to be
made for product knowledge, time available for outsourcing work, and needs for project
management (Walewski, G. Edward Gibson, & Jasper, 2001).
Construction Management Multi-Prime (CM MP)
Figure 2: Construction Management Multi-Prime
In this type of project delivery mode, several different contracts are made for architect,
contractors and subcontractors. This model also lets the project owner retain the control over
the design and gives the advantage of low cost of execution. However, it fast tracks the
project by involving contractors at early stages. However, owner is responsible for making
any changes in scope and the subcontractor may not be involved in the process which leads to
a lac of oversight on the project (Rawlins & Godwin, 2015).
4
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Literature Review of Project Delivery Models
Construction Management-at-Risk (CMAR)
Figure 3: Construction Management-at-Risk
Just like the design-bid-build model, this types delivery model also involves development of
two types contractors including those for architect and for contractor. However, the
contractor is selected based on specific qualifications and the paid fee. The contractor can
assign sub-contracts to other contractors. The project price is flexible for suppliers and
subcontractors due to open book process. In this type of delivery model also, the owner is
only responsible for the selection of the contractor and take major business decisions. No
inputs may be taken from the contractor while planning design for a construction project. In
this arrangement, codesigning and construction phases are separated. The construction
manager is the owner of the design phase while construction is majorly taken care of by the
contractor (LEVELSET, 2019).
5
Construction Management-at-Risk (CMAR)
Figure 3: Construction Management-at-Risk
Just like the design-bid-build model, this types delivery model also involves development of
two types contractors including those for architect and for contractor. However, the
contractor is selected based on specific qualifications and the paid fee. The contractor can
assign sub-contracts to other contractors. The project price is flexible for suppliers and
subcontractors due to open book process. In this type of delivery model also, the owner is
only responsible for the selection of the contractor and take major business decisions. No
inputs may be taken from the contractor while planning design for a construction project. In
this arrangement, codesigning and construction phases are separated. The construction
manager is the owner of the design phase while construction is majorly taken care of by the
contractor (LEVELSET, 2019).
5
Literature Review of Project Delivery Models
Design-Build (DB)
Figure 4: Design-Build (DB)
In design-build project delivery systems, a single point of contact is made which makes this a
the fastest delivery system. The project scope is well-defined and the approach is cost
effective. The single major contractor needs to administer the whole design-build process. In
this type of delivery system, inputs are also taken from the main contractor during the
designing phase of the project. Any gaps or overlaps existing are identified during the pre-
construction stage. With early resolution of the issues related to construction and designing,
the schedule of the project can be improved and a tight budget control system can be
implemented to ensure adherence to allotted budget (Molenaar, Harper, & Yugar-Arias,
2014).
The costs are reduced in these types of contracts and procurement can happen directly
through trades without addition of any mark up on supply prices. This type of contract may
serve best in the interest of the project owner. However, this type of project delivery also has
some drawbacks such as lack of oversight for contractor, responsibility for the change lying
on the project owner, need for advanced understanding and planning of performance criterial,
and need of the owner to take early decisions that can influence the whole project thereafter
(Beck group, 2015).
6
Design-Build (DB)
Figure 4: Design-Build (DB)
In design-build project delivery systems, a single point of contact is made which makes this a
the fastest delivery system. The project scope is well-defined and the approach is cost
effective. The single major contractor needs to administer the whole design-build process. In
this type of delivery system, inputs are also taken from the main contractor during the
designing phase of the project. Any gaps or overlaps existing are identified during the pre-
construction stage. With early resolution of the issues related to construction and designing,
the schedule of the project can be improved and a tight budget control system can be
implemented to ensure adherence to allotted budget (Molenaar, Harper, & Yugar-Arias,
2014).
The costs are reduced in these types of contracts and procurement can happen directly
through trades without addition of any mark up on supply prices. This type of contract may
serve best in the interest of the project owner. However, this type of project delivery also has
some drawbacks such as lack of oversight for contractor, responsibility for the change lying
on the project owner, need for advanced understanding and planning of performance criterial,
and need of the owner to take early decisions that can influence the whole project thereafter
(Beck group, 2015).
6
Literature Review of Project Delivery Models
Integrated Project Delivery
Figure 5: Integrated Project Delivery
In the integrated project delivery system, an integrated team of contractors and architects is
formed such that designers as well as construction contractors can all contribute to the project
in all phases. This eliminates redundant efforts and thus, reduce cost of construction by
reducing wastage (Cassino, 2018).
Figure 6: Integrated Project Delivery System (Fischer, Reed, Khanzode, & Ashcraft, 2012)
In IPD system, synergies need to be created between different technical systems operating in
a project including product, processes, information and project organizations. Specific
performance metrics are developed by the owner to measure the achievements on the project
at every stage. The integrated system relies on the concept of working together and works on
7
Integrated Project Delivery
Figure 5: Integrated Project Delivery
In the integrated project delivery system, an integrated team of contractors and architects is
formed such that designers as well as construction contractors can all contribute to the project
in all phases. This eliminates redundant efforts and thus, reduce cost of construction by
reducing wastage (Cassino, 2018).
Figure 6: Integrated Project Delivery System (Fischer, Reed, Khanzode, & Ashcraft, 2012)
In IPD system, synergies need to be created between different technical systems operating in
a project including product, processes, information and project organizations. Specific
performance metrics are developed by the owner to measure the achievements on the project
at every stage. The integrated system relies on the concept of working together and works on
7
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Literature Review of Project Delivery Models
the belief that no system can be build on isolation but needs collaboration from all. Fr
instance, when designing lightening for a building, other considerations that may be
associated with other contractors are important to make. The width of the building and height
of the floors may affect the choice of lightening (T., Lehoux N., & Y., 2017).
There can be different ways of doing process integration. An integration can happen between
the value defined for the project and the designing process as the users may not be able to
understand the value as well as what they want through the design. A design needs to be
validated by different users while in making such that adjustments have to be made by the
designer accordingly. The construction perspective also has to be brought in the process of
designing because of creation of building design is the key output in the project design
process which can affect the whole construction project (Chong, Brandt, & and Martin,
2010).
Figure 7: IPD Framework (Ashcraft, 2011)
The objectives behind using an IPD framework for project deliveries are removal of barriers
to communication, alignment of all project participants to common goals, and increasing of
the project value by associating it with rewards. An IPD project relies on key structural
elements that include early involvement of project participants, shared risk as well rewards
between participants, join control over the project, reduced exposure to liability, and joint
development as well as validation of project targets (Walewski, G. Edward Gibson, & Jasper,
2001).
8
the belief that no system can be build on isolation but needs collaboration from all. Fr
instance, when designing lightening for a building, other considerations that may be
associated with other contractors are important to make. The width of the building and height
of the floors may affect the choice of lightening (T., Lehoux N., & Y., 2017).
There can be different ways of doing process integration. An integration can happen between
the value defined for the project and the designing process as the users may not be able to
understand the value as well as what they want through the design. A design needs to be
validated by different users while in making such that adjustments have to be made by the
designer accordingly. The construction perspective also has to be brought in the process of
designing because of creation of building design is the key output in the project design
process which can affect the whole construction project (Chong, Brandt, & and Martin,
2010).
Figure 7: IPD Framework (Ashcraft, 2011)
The objectives behind using an IPD framework for project deliveries are removal of barriers
to communication, alignment of all project participants to common goals, and increasing of
the project value by associating it with rewards. An IPD project relies on key structural
elements that include early involvement of project participants, shared risk as well rewards
between participants, join control over the project, reduced exposure to liability, and joint
development as well as validation of project targets (Walewski, G. Edward Gibson, & Jasper,
2001).
8
Literature Review of Project Delivery Models
Project Delivery Case Study
The current research takes the case of construction for the expansion of a children’s hospital
called Cardinal Glennon in St. Louis, Missouri. The project consisted of 138,000 square foot
of space that was built in the budget of $45.5 million. The project used Integrated Project
Delivery approach which was decided by developer, architect and engineer of the project
during the designing stage. This choice was made to share project responsibilities equally
among partners, build high level of coordination between teams and saving money through
management of contingencies (Christner Inc., 2010).
References
Ashcraft, H. W. (2011). The IPD Framework. San Francisco, CA: Hanson Bridgett.
Beck group. (2015). An Analysis of Design/Build vs. Design-Bid-Build. Beck group.
Cassino, K. E. (2018). Project Delivery Systems: How They Impact Efficiency and
Profitability in the Buildings Sector. McGraw Hill.
Chong, G. H., Brandt, R., & and Martin, W. M. (2010). Design Informed: Driving Innovation
with Evidence-Based Design. . Wiley.
Christner Inc. (2010). Integrated Project Delivery: Case Studies. AIA.
Fischer, M., Reed, D., Khanzode, A., & Ashcraft, H. (2012). A simple framework for
integrated project delivery. Stanford University.
LEVELSET. (2019). Common Construction Project Delivery Methods: A Breakdown.
LEVELSET.
Molenaar, K., Harper, C., & Yugar-Arias, I. (2014). Guidebook for Selecting Alternative
Contracting Methodsfor Roadway Projects:Project Delivery Methods, Procurement
Procedures,and Payment Provisions. Boulder, Colorado : University of Colorado .
Rawlins, D. D., & Godwin, B. (2015). CHoosing a Project Delivery Method. Design-Build
Institute of America.
T., P., Lehoux N., & Y., C. (2017). Design-Build in Construction: Performance and Impact
on Stakeholders. 25th Annual Conference of the International Group for Lean
Construction (IGLC), (pp. 35-43). Heraklion, Greece.
Walewski, J., G. Edward Gibson, J., & Jasper, J. (2001). Project Delivery Methods and
COntracting Approaches Available for Implementation . Austin, TX : The University
of Texas at Austin .
9
Project Delivery Case Study
The current research takes the case of construction for the expansion of a children’s hospital
called Cardinal Glennon in St. Louis, Missouri. The project consisted of 138,000 square foot
of space that was built in the budget of $45.5 million. The project used Integrated Project
Delivery approach which was decided by developer, architect and engineer of the project
during the designing stage. This choice was made to share project responsibilities equally
among partners, build high level of coordination between teams and saving money through
management of contingencies (Christner Inc., 2010).
References
Ashcraft, H. W. (2011). The IPD Framework. San Francisco, CA: Hanson Bridgett.
Beck group. (2015). An Analysis of Design/Build vs. Design-Bid-Build. Beck group.
Cassino, K. E. (2018). Project Delivery Systems: How They Impact Efficiency and
Profitability in the Buildings Sector. McGraw Hill.
Chong, G. H., Brandt, R., & and Martin, W. M. (2010). Design Informed: Driving Innovation
with Evidence-Based Design. . Wiley.
Christner Inc. (2010). Integrated Project Delivery: Case Studies. AIA.
Fischer, M., Reed, D., Khanzode, A., & Ashcraft, H. (2012). A simple framework for
integrated project delivery. Stanford University.
LEVELSET. (2019). Common Construction Project Delivery Methods: A Breakdown.
LEVELSET.
Molenaar, K., Harper, C., & Yugar-Arias, I. (2014). Guidebook for Selecting Alternative
Contracting Methodsfor Roadway Projects:Project Delivery Methods, Procurement
Procedures,and Payment Provisions. Boulder, Colorado : University of Colorado .
Rawlins, D. D., & Godwin, B. (2015). CHoosing a Project Delivery Method. Design-Build
Institute of America.
T., P., Lehoux N., & Y., C. (2017). Design-Build in Construction: Performance and Impact
on Stakeholders. 25th Annual Conference of the International Group for Lean
Construction (IGLC), (pp. 35-43). Heraklion, Greece.
Walewski, J., G. Edward Gibson, J., & Jasper, J. (2001). Project Delivery Methods and
COntracting Approaches Available for Implementation . Austin, TX : The University
of Texas at Austin .
9
Literature Review of Project Delivery Models
10
10
1 out of 10
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.