This report discusses the project management of an open air music theatre event organized by LMAC for Lord Mayor Charity Appeal. It covers the objectives, methodologies, deliverables, stakeholder analysis, risk analysis, breakdown structure and quality related features. The report also includes a network diagram and measures for controlling the event.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
BM522 PROJECT MANAGEMENT
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents INTRODUCTION..........................................................................................................................3 MAIN BODY..................................................................................................................................3 Project objectives, deliverables and methodologies....................................................................3 Development of Network Diagram..............................................................................................4 Stakeholder analysis of the project..............................................................................................5 WBS.............................................................................................................................................6 Risk analysis and risk management strategies.............................................................................7 Measure for controlling the event..............................................................................................11 CONCLUSION..............................................................................................................................11 REFERENCES..............................................................................................................................12
TITLE:“Lord Mayor Charity Appeal Open Air Music Theatre Event in association with the Samaritans” INTRODUCTION Project management is referred to the usage of specific skills, knowledge, tools and various techniques for they purpose of delivering something of a great value to the world. It encompasses, expectations which are supposed to be met and has a defined schedule, and budget according to which the team work (Armenia and et.al., 2019). Project management also facilitates tracking each and every initiative that a team takes. All this result in smooth functioning and in a great efficiency of the project (Guo and Zhang, 2022). Here, in report project of open air music theatre has been prepared for Lords Mayor Appeal Charity, which aims to make the city better. The report will present the objectives, methodologies, deliverables, stakeholder analysis, risk analysis, breakdown structure and the quality related features. MAIN BODY Project objectives, deliverables and methodologies The music theatre event has been arranged by LMAC in order to raise awareness about “A Better City for All “ , an initiative taken by the charity (Hair and Sarstedt, 2021). During the event the group will be highlighting its key partner “the Samaritans” and will emphasize on making the city better. Here are are main objectives of the event mentioned below: The motive of the event is to make the city a better place to live in. This by the name, itself suggests that the event aim to develop a sense of empathy amongst the people. Its aim is to establish a sense of empathy towards the other people and animals (Tereso and et.al., 2019). It aims to relieve the poverty, protect the environment and the animals. The event is organized in order to gain a strong support from the people. To be able to complete the project within estimated time period. Project deliverables: Agreement with the composer and playwright Budget report Investigation report of the event venue Projected strategic directions Contract reports (with the investors, investors and suppliers)
ď‚·Activity scheming (network diagram and WBS) Project Methodology As per the project, methodology adopted will be agile in order to manage the entire project and break the project into number of phases. This can also be done by collaborating with the stakeholders at each new stage. This approach is the most flexible a well as fast approach that is the main reason it has been chosen for the project. The model was also used earlier all the restaurants before opening their shops. Development of Network Diagram Task ModeTask NameDurationStartFinishPredecessorsResource Names 1Budget Approval1 dayMon 10/17/22 Mon 10/17/22 2Hire Publicity Director9 daysTue 10/18/22Fri 10/28/221 3Hire Set Designer9 daysTue 10/18/22Fri 10/28/221 4Hire Place For Auditions17 daysMon 10/31/22 Tue 11/22/222 5Advertising To Hire Crew and Cast25 daysWed 11/23/22 Tue 12/27/224 6Hire Production & Publicity Crew33 daysWed 12/28/22Fri 2/10/235 7Set Designed and Built41 daysMonMon3,6
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
2/13/234/10/23 8Train Production Crew41 daysMon 2/13/23 Mon 4/10/233,6 9Auditions To Hire Cast33 daysWed 12/28/22Fri 2/10/235 10Cast Rehearsal41 daysMon 2/13/23 Mon 4/10/239 11Hire Orchestra9 daysTue 10/18/22Fri 10/28/221 12Music17 daysMon 10/31/22 Tue 11/22/2211 13 Photograph Cast And Crew & Collect Biographies 41 daysMon 2/13/23 Mon 4/10/236,9,11 14Enter Information Into Computer49 daysTue 4/11/23Fri 6/16/2313 15Printing57 daysMon 6/19/23Tue 9/5/2314 16Develop an Advertising Plan41 daysMon 2/13/23 Mon 4/10/236 17Advertising Media49 daysTue 4/11/23Fri 6/16/2316 18Orchestra rehearsal25 daysWed 11/23/22 Tue 12/27/2212 19Order Costumes41 daysMon 2/13/23 Mon 4/10/239 20Costume Parade And Alterations49 daysTue 4/11/23Fri 6/16/237,19 21Dress Rehearsal57 daysMon 6/19/23Tue 9/5/238,10,18,20 22Performance65 daysWed 9/6/23Tue 12/5/2315,17,21 Stakeholder analysis of the project With this very analysis it becomes easy for the project manger to ascertain the interest of the stakeholders with the following project (Raum, 2018.). Here, as per the very first stage, this matrix is going to be used for determining the external and internal stakeholders and their interest associated with the project as well as the power that they hold. Here is the following stakeholder matrix of the current project: HighKeep SatisfiedManage Closely
PowerMonitor (Minimum effort)Keep Informed LowLowInterest High Manage closely-This is a very important factor as seen here the power and the interest associated with the close management is very high. This management can be look over by the internal stakeholders such as the project managers, the team members, volunteers etc. Keepinformed-Thisfactorisalsoveryimportantastheinternalaswellasexternal stakeholders should be informed time to time about the progress of the event. The external stakeholders do not have the high power but they definitely have high interest. Keep satisfied-This is important for the external stakeholders such as the audience of the project. If the stakeholders are not satisfied it may lead to the project failure. Monitor-Stakeholders who monitor the project event are the participants, attendees and the spectators, they hold a very low interest and the power both. WBS Risk analysis and risk management strategies RiskProbabilityImpactRisk ratingRisk mitigation Action
strategy Improper definition regardingthe need and purpose of the project 3412AvoidIt can be assured withthehelpof consultancyfirms orbyhiringone consultant (Larssonand Larsson, 2020). Incomplete designand deliverables definedfor project 155AvoidBy fetching inputs fromexpertsand shaping the scope bydesign workshops. Unclear explanation of the project schedule 236AcceptThis can be eliminated by attending the workshops which are engaged with the scheduling of a project (Wu and et.al., 2021.). This will develop a proper understanding of in the team as well as in the manager. Incapableof controllingthe team's priorities. 339AvoidHere the members of the team can be brief about the entire project and its tasks. Rejectionor delays 155TransferThis risk can be eliminated by by also adding some penalties under the contract of the project. Budget overrun414Controlling and monitoring This can be eliminated by keeping a constant watch on the project's activities and by allocating the timely funding to the project. Incorrectness339AvoidBy tracking the
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
whileestimating schedule schedule daily and keeping a watch on what have been done and what still awaits, the risk can be eliminated. Poorsupport of executive 339AvoidComing in contract with the steering committee which demands the managerial support all throughout the life cycle of the project. Suppliersor vendorsleaving the business. 155AcceptNew alternative can be found by the contracting committee in order to complete the duties. Inappropriate venue 133AvoidMaking a prior visit to the place before the event. This will help to mange the wrong things there and will help in eliminating the risk. Poorstage performance. 155Transferor Accept By taking the auditions first and having agood budget thye project can hire good performers or by reducing the cost incurred, the loss can be handled accordingly. This can also be eliminated by giving recommendations
to the people. Depleted marketing opportunities (Improper strategic directions) 155AvoidThis particular risk can only be eliminated by contacting the marketing professionals Regular meeting with the marketing professionals to frame appropriate and effective strategies. Inadequate Safety and health during event. 339ControlThis can be eliminated by going through all the protocols that are to be followed in an event and then after various safety and health measure can be developed. With a proper security team also, the event can be guarded. Non – acceptance of the design that hasbeen proposed. 144AvoidThis can be mitigated by coming up with different alternatives. Market observation also plays an important role in this, as it will help in shaping the design better. Troublein permission grants fromthe stakeholders 236AcceptThis can only be tackled by meeting the stakeholders in a regular period. Miserableevent development 224MonitorMonitoring is the only one thing through which the
miser ability of an event can be avoided. With the proper monitoring, the progress of the event can be checked, each step can be checked thoroughly and also the stakeholders consent can be taken. Poor Instrumental quality 133TransferThis can be eliminated by checking the band performance and the risk can also be reduced by already mentioning the quality in the contract. Conflictwith councilof Student Union. 133AcceptBy creating a Backup plan related to the fund acquisition. Eventsuddenly got cancelled 155AvoidThis can be reduced by already coming with the terms and conditions with the stakeholders in the contract. Riskofthe natural disasters 155AcceptThe location of the event can be chosen by looking at the risk of disaster prone areas. Measure for controlling the event Quality expectations-It should meet the expectations of the customers, be it regarding the food or the music. This will make the event successful.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Quality specification-With the proper lightening and proper crowd, the event will hold no harm to anyone and the event will end successfully. CONCLUSION From the above report it has been concluded that, for a successful management, the goals, objectives, deliverables etc. play a very important role. The project should be well defined . Also, the stakeholders and risk analysis should be performed well in order to make the project achieve its desired goals.
REFERENCES Books and journals Armenia, S. and et.al., 2019. Sustainable project management: A conceptualization-oriented review and a framework proposal for future studies.Sustainability.11(9). p.2664. Guo, K. and Zhang, L., 2022. Multi-objective optimization for improved project management: Current status and future directions.Automation in Construction.139.p.104256. Hair, J.F. and Sarstedt, M., 2021. Explanation plus prediction—The logical focus of project management research.Project Management Journal.52(4). pp.319-322. Tereso, A. and et.al., 2019. Project management practices in private organizations.Project Management Journal.50(1). pp.6-22. Larsson, J. and Larsson, L., 2020. Integration, application and importance of collaboration in sustainable project management.Sustainability.12(2). p.585. Wu, C. and et.al., 2021. Ontological knowledge base for concrete bridge rehabilitation project management.Automation in construction.121.p.103428. Raum, S., 2018. A framework for integrating systematic stakeholder analysis in ecosystem servicesresearch:StakeholdermappingforforestecosystemservicesintheUK. Ecosystem Services.29.pp.170-184.