6109ENG Construction Project Management, semester 1, 2018 Construction Project Management for Luxury House -1 Construction DECCLARATION We declare that tis research proposal contains no material which has submitted for assessment in any subject at Griffith University. To the best of our knowledge and belief, this research proposal contains no material that has been previously published by any other person, except where due acknowledge has been made. Student IDFamily NameOther NamesSignature 1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 Contents DECCLARATION.............................................................................................................................1 PROJECT SUMMARY..............................................................................................................3 INTRODUCTION.............................................................................................................................4 Architecturedesign and function components.........................................................................4 Architectural plan review..........................................................................................................4 Building envelop........................................................................................................................5 Schedule overview....................................................................................................................6 Foundation, finishes and structure Narrative............................................................................7 Local condition..........................................................................................................................7 Methodology.................................................................................................................................8 Project cost evaluation..............................................................................................................8 LEED consideration..................................................................................................................11 Optimizing value engineering..................................................................................................12 Statement of General Conformance.......................................................................................13 Time Schedules of activities....................................................................................................14 Cost of Schedules of activities.................................................................................................16 Schedules of activities histogram............................................................................................18 Grantt chart.............................................................................................................................19 List of the tasks required.........................................................................................................20 Engineering, Procurement and Construction Project Budget approved.................................22 Team members work package................................................................................................24 Critical Path Method (CPM) diagram for service facility project.............................................26 Estimated Costs for the Construction Projects........................................................................27 Risk management plan for program delays.............................................................................48 Conclusion..................................................................................................................................50 References................................................................................................................................51 2
6109ENG Construction Project Management, semester 1, 2018 PROJECT SUMMARY Joyce and Gerry McGrade are the clients for McGrade house; the luxury house is situated at 41 Rankin Pde, main beach Queensland. The house has been deliberately planned according to the standard control codes and anticipated to meet the environmental regulation policies. The proprietors are set to open the building by December 2018; they are being dynamic and aspiring by executing precipitation water reap and water catching for the reuse in certain plumbing apparatuses. The proprietors will be satified with the culmination of the luxury McGrade house on the off chance that it will meet around $10 million spending plan, on the off chance that it will be open lately on December 2018, on the off chance that it meet both the standard control of construction codes and environmental regulation policies. 3
6109ENG Construction Project Management, semester 1, 2018 INTRODUCTION Architecturedesign and function components McGrade luxury house is another facility that comprise of three building segment that are isolated by slab floors. The basement is meant for parking of vehicle and furthermore it has a segment of support of the lift. The ground floor had three bedrooms, study room, rumpus room, laundry, washrooms and latrine in every room and store room, lastly the first floor that have the replica of ground floor. Architectural plan review During the architectural plan review the following will be considered; 1.Verification of the loads imposed on the structure due to dead load, fixed equipment, storage, live load. Comment; They are all coordinated with structural assumptions. 2.Verification of adequacy of non-structural components. − Ceilings and soffits Comment; Their connections resist vertical and lateral loads − Equipment, storage racks, cabinets and casework Comment; Their connections resist vertical and lateral − Parapets, architectural ornamentation and appendages Comment; Their connections resist vertical and lateral 3.Verification of architectural dimensions (thickness of walls, depth of roof structure, etc.). Comment; Their coordination are well fitted 4.Verification of the wood. Comment They are all protected against moisture, decay, and termites 4
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 5.Verification of the enclosed spaces Comment; They are well adequately ventilated. 6.Verification of the adequate roof drainage has been provided. Comment; They are all provided Building envelop The building envelope will contain materials that incorporate block around the base of the working up to a precast banding. The banding will fill in as a change to larger than average brick work boards. Aluminum Cladding is additionally utilized for outside dividers and shade spaces. Customer facing facade style Glass Walls will likewise be utilized all through the McGrade luxury house. One of the principle highlights of the building will be its Metal Canopy that stretches out finished the Main Entry. 5
6109ENG Construction Project Management, semester 1, 2018 Figure 1: Building envelope Schedule overview The total project is booked to take around 530 Days. Substructure is anticipated to keep going for around 165 days, superstructure will take around 130 days and the rough in and complete course of events is around 140 days. Building closeout incorporates testing for LEED point confirmation and other testing and parities, and also last punch list work. Final completion is relied upon to be on twentieth December 2018. See Gantt diagram Summary Schedule. 6
6109ENG Construction Project Management, semester 1, 2018 Foundation, finishes and structure Narrative The soil being unstable will expect geopiers to be built under footings to make a high load bearing capacity. Whatever is left of the site and sheds will utilize spread footings. The area of pool on the back side of the house territory will include the establishment of sheeting and shoring, a mud tangle, and unique water-sealing of the Pool Structure all around. Fundamentally the house will be built in three portioned segments of floors. The Substructure and Superstructure will both take after comparative grouping ways. The basement Section and core of the building will always lead followed by the ground floor and afterward the first floor. By sectioning the calendar all through the procedure teams will have the capacity to be of small sizes and more beneficial, if different exchanges have officially moved out of a specific zone before the following group beginning its work. There is however various exchanges that will require tight joint effort to make progress on this undertaking. The essential illustration being, the Electrical Contractor and Masonry Contractor the same number of square dividers should be roughed in while being built. The Rough-in and finish schedule will follow a similar sequence by starting in the basement, progressing to the ground floor and then finishing in the first floor of building. Local condition Normally in the Australia region the favored strategy for development is cast in place concrete. It is intriguing that the basic framework is mostly standard steel construction. With building height not being a plan constraint, in regard to augmenting number of floors this may have figured into the technique method chosen. The site permits restricted nearby stopping which is accessible. The encompassing zone is generally private and road stopping will give adequate parking spots amid development. Numerous construction recycling organizations are accessible to the Queensland area, from aggregate site recycling to arranging and hauling services. 7
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
6109ENG Construction Project Management, semester 1, 2018 The soil bearing capacity does not require much more than the use of geo-piers in specific areas. Spread footings are adequate in many territories and for segregated structures around sports facilities. 8
6109ENG Construction Project Management, semester 1, 2018 9
6109ENG Construction Project Management, semester 1, 2018 Methodology Project cost evaluation Table 1: Square foot estimates summary Construction costSourceConstruction cost per square meter $3,994, 992D4 cost estimating$170.92 $4, 120, 400R.S mean$213.45 $8,000,000Actual$385.74 The project task has a financial plan of $10 million and building expense of $8 million. The genuine building cost per square meter was ascertained to be $386. In Table 1, a correlation with the parametric gauge made utilizing D4 Cost Estimating can be seen; the evaluations made in this report give off an impression of being low. The genuine building cost considers the numerous civilities and offices made for McGrade extravagance house. In D4 it is entirely taking a gander at square meter and a comparable size of the building. The gauge utilizing Cost works (RS Means) has brought about a gauge of $4.1 million. The amendments made to the base square meter cost include: changing in accordance with proper story tallness and edge and also some extra civilities. The substantial contrasts can be represented in the distinctions in the plan of the task contrasted with different offices. RS Means square meter cost information can't represent the numerous pleasantries incorporated into the real development expenses of McGrade luxury house. 10
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 Table 2: MEP and structural cost estimates summary *Estimated Values SystemSystem cost% totalCost per square meter Mechanical$5,000, 000*16$60.50 Electrical$3,000,00012$48.67 Structure$2,000,000*4$16.75 11
6109ENG Construction Project Management, semester 1, 2018 12
6109ENG Construction Project Management, semester 1, 2018 LEED consideration The McGrade luxury house is presently anticipated to meet LEED Gold under LEED for Program. This rating will be accomplished by concentrating on Indoor Air Quality and Optimizing Energy Performance. A huge segment of the rooftop (more than 40%) will be broad green rooftop gardens, while the rest of the territories will be an exceptionally intelligent EPDM roofing material. Summary of the LEED can be seen below in Table 3. Table 3:LEED 2009 New construction and major renovation LEED 2009 New construction and major renovation Categoriespoints planned to be earned yesmay beNo maintainable site1526 Water Efficiency1030 Atmosphere and Energy11019 Resources and materials715 Quality Indoor Environmental1503 Design Process and Innovation312 Credits of Regional Priority000 Total61735 gold = 60 to 79 points 13
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
6109ENG Construction Project Management, semester 1, 2018 Optimizing value engineering The analysis begins with an examination concerning the green rooftop. Where the properties of the green rooftop examination included: cost, warm effectiveness, storm water stockpiling limit, weight, and construction span. Warm properties of the green rooftop framework are extremely intricate and will require cautious and innovative contemplations. Construction term for the rooftop framework can be diminished strikingly. At last, cost will be computed with changes and effects of alternate frameworks to decide the feasibility of taking out the green rooftop. To finish up this analysis taking LEED affirmation, Value Engineering and Schedule Reduction into thought will decide the dangers and openings related with Optimizing Value Engineering. Green rooftops give numerous focal points and burdens that should all be considered when choosing on the off chance that it is a reasonable choice for a material gathering. A couple of favorable circumstances to green rooftops are: storm water administration properties, goes about as a warm mass, capacity to clean the air and conceivable long haul vitality funds. A few inconveniences are: high introductory costs, expanded rooftop dead loads, support concerns and exorbitant repairs if required. 14
6109ENG Construction Project Management, semester 1, 2018 Statement of General Conformance FOR ARCHITECTS/ENGINEERS WHO UTILIZE PLANS, INCLUDING BUT NOT LIMITED TO SHOP DRAWINGS, PREPARED BY OTHER LICENSED DESIGN PROFESSIONALS AND/OR CONSULTANTS (Application No. ________342______________ File No. _____1247-04_________) The drawings or sheets listed on the cover or index sheet This drawing, page of specifications/calculationshave been set up by other plan experts or advisors who are authorized and additionally approved to get ready such illustrations in this state. It has been analyzed by me for: 1) outline plan and seems to meet the suitable prerequisites of Title 24, California Code of Regulations and the task determinations arranged by me, and 2) Coordination with my plans and determinations and is adequate for joining into the development of this undertaking. The Statement of General Conformance "might not be understood as calming me of my rights, obligations, and duties under Sections 17302 and 81138 of the Education Code and Sections 4-336, 4-341 and 4-344” of Title 24, Part 1.(Title 24, Part 1, Section 4-317 (b)) I find that:All drawings or sheets listed on the cover or index sheet This drawing or page is/are in general conformance with the project design, and has/have been coordinated with the projectplans and specifications. is/are in general conformance with the project design intent, and has/have been coordinated with the project plans and specifications. SignatureDateSignatureDate Architect or Engineer designated to be in general responsible charge Architect or Engineer delegated responsibility for this portion of the work Print NamePrint Name License Number 342Expiration Date 02/02/2019 License NumberExpiration Date 15 x x
6109ENG Construction Project Management, semester 1, 2018 Time Schedules of activities Table 4: Time schedule of activities Activities number DescriptionsDuratio n Early start Early finish Late start Late finish Total float Free float 5PROJECT NOTICE APPROVAL 326 may 2018 28 may 2018 26 may 2018 28 may 2018 00 10DEVELOP WORK PLAN 729 may 2018 6 June 2018 29 may 2018 6 June 2018 00 15FORM PROJECT TEAM 59 June 2018 13 June 2018 9 June 2018 13 June 2018 00 20DESIGN CONTRACTOR'S WORK 216 June 2018 17 June 2018 25 June 2018 26 June 2018 70 25IN-HOUSF: DESIGN WORK 316 June 2018 18 June 2018 16 June 2018 18 June 2018 00 30DESIGN BRIEFING MEETING 118 June 2018 18 June 2018 27 June 2018 27 June 2018 70 35PROJECT SITE- WORK DESIGN 119 June 2018 19 June 2018 25 June 2018 25 June 2018 40 40ON-SITE UTILITIES DESIGN 119 June 2018 19 June 2018 7 Aug 2018 7 Aug 2018 350 45A/E DESIGN BUILDING A 119 June 2018 19 June 2018 19 June 2018 19 June 2018 00 50FLOOR PLAN GROUND 1020 June 2018 3 July 2018 30 June 2018 11 June 2018 70 55SITE GRADING PLAN 1220 June 2018 7 July 2018 26 June 2018 11 June 2018 40 60STORM- WATER DESIGN 1020 June 2018 3 July 2018 8 Aug 2018 21 Aug 2018 350 65FLOOR PLAN FIRST FLOOR 1520 June 2018 10 July 2018 20 June 2018 10 June 2018 00 16
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 70FOUND/STRUCT OF THE BUILDING 453 July 2018 3 Sep 2018 22 June 2018 22 Sep 2018 130 75ARCH FINISHES OF THE BUILDING 303 July 2018 13 Aug 2018 12 Aug 2018 22 Sep 2018 2815 80SANITARY SEWER DESIGN 2110 July 2018 1 Aug 2018 10 July 2018 1 Aug 2018 00 85DOMESTIC WATER SYSTEM 75 Sep 2018 12 Sep 2018 5 Sep 2018 12 Sep 2018 00 90PLUMBING.102 Oct 2018 12 Oct 2018 2 Oct 2018 12 Oct 2018 00 95FINAL INSPECTION & APPROVAL 33 Dec 2018 6 Dec 2018 3 Dec 2018 6 Dec 2018 00 17
6109ENG Construction Project Management, semester 1, 2018 Cost of Schedules of activities Table 5: Cost of schedules of activities Activities number DescriptionsDurationCost 5APPROVAL OF PROJECT NOTICE 3$500 10WORK PLAN DEVELOPMENT 7$1200 15FORMATION OF PROJECT TEAM 5$850 20CONTRACTOR'S WORK DESIGN 2$3000 25IN-HOUSF: DESIGN WORK 3$1500 30BRIF MEETING ON DESIGN 1$1200 35WORK DESIGN ON PROJECT SITE 1$1400 40ON-SITE UTILITIES DESIGN 1$1200 45A/E DESIGN BUILDING A 1$1500 50FLOOR PLAN GROUND 10$9000 55PLAN OF SITE GRADING 12$14000 60STORM-WATER DESIGN 10$2000 65FIRST FLOOR FLOOR PLAN 15$26000 70FOUND/STRUCT OF THE BUILDING 45$31200 75ARCH FINISHES OF THE BUILDING 30$49000 80DESIGN OF SANITARY SEWER 21$12000 85DOMESTIC7$9000 18
6109ENG Construction Project Management, semester 1, 2018 WATER SYSTEM 90PLUMBING.10$28500 95FINAL INSPECTION & APPROVAL 3$3500 19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
6109ENG Construction Project Management, semester 1, 2018 Schedules of activities histogram 3101517202122232434465671116146167174184187 0 10000 20000 30000 40000 50000 60000 cost cumulative frequence on duration cost ($) Figure 2: Histogram of schedules of activities . 20
6109ENG Construction Project Management, semester 1, 2018 Grantt chart Figure 3: Grant chart of cost of schedule of activities 21 PROJECT NOTICE APPROVAL FORM PROJECT TEAM IN-HOUSF: DESIGN WORK PROJECT SITE-WORK DESIGN A/E DESIGN BUILDING A SITE GRADING PLAN FLOOR PLAN FIRST FLOOR ARCH FINISHES OF THE BUILDING DOMESTIC WATER SYSTEM FINAL INSPECTION & APPROVAL 05101520253035404550
6109ENG Construction Project Management, semester 1, 2018 List of the tasks required Table 6: list of activitiesProject: 060608/WBS-1 Pacific Motorway CONCEPT PHASE Project Management Appoint Project Manager Community Engagement Project Proposal Determination of a functional Necessities and Scope Project Proposal production Development of Options Analysis and Recommendations Develop Concept Planning Brief Procure Concept Planning Consultant Produce Options Analysis and Recommendations Recommend Preferred Option Approved Recommended Option Develop Preferred Option Business Case Review Risk Register and Project Estimate Produce Business Case Financial Approval DEVELOPMENT PHASE Project Management Project Management General Development Phase Prepare Design Brief Community Engagement Development Phase Preliminary Design Procure Preliminary Design Consultants Produce Preliminary Design Detailed Design Procure Detailed Design Consultants Obtain Legislative Approvals and Permits Produce Detailed Design Contract Documents Produce Contract Documents Pre-tender Financial Approval Preliminary Works Obtain Approval for Preliminary Works Acquire Right of Way Procure Public Utility Plant (PUP) Services Procurement Engage Contract Administrator 22
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 Procure Contractor Contract Financial Approval Contract Award IMPLEMENTATION PHASE Project Management Project Management (General) Implementation Phase Community Engagement Implementation Phase Contract Administration Practical Completion Certificate Construction Principal's Responsibility Official Opening FINALISATION PHASE Project Management Project Management (General) Finalization Phase Defects Liability Period Final Certificate Community Engagement - Finalisation Phase Complete Project Handover Report Evaluate Project Performance Post Implementation Review Close OutConsultation 23
6109ENG Construction Project Management, semester 1, 2018 Work Breakdown Structure (WBS) for service facility A/E Building Architectural Dan Milterplot plan Architecturalfloor plan Plot plansanitary sewersite improvement Floor plan- fencing structural Electricity- landscaping foundation StructuralWaterpaving FoundationDomestic- sub base mechanical Fire protectionconcrete plumbing MechanicalTelephone- parking /walkheat and air PlumbingDomestic electrical Heat and airSecurityaggregatefinish Electrical 25 A/E Building Kathy Dilch Contract design Dan Milter In house design Jan Thomas On- site utilities Fred James Site-work Jan Thomas EPC project Jim James
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
6109ENG Construction Project Management, semester 1, 2018 Finishes Team members work package Work package Title: Maintenance Building WBS: 20021 1.Scope Required scope of work: Architectural Service to be provided: floor plan drawing Services not included in this Work Package, but included in another work package: House units drawing plan Services not included in this Work Package, but will be performed by: 2.Budget Table 7: showing Budget 26
6109ENG Construction Project Management, semester 1, 2018 Personnel assign to the job Work – hours $-costCBS code Acct Computer services TypeHour$-cost Fredrick James 10$202345Typing and printing 6$5 Total work – hour = 10personnel cost = $200 Computer hours =6computer cost = $30 TravelingReproductionOther ExpendituresExpendituresExpenditures $50+$100+$70=$200 Total Budget = cost of Labor + cost of Computer + Traveling cost + Other costs = $350 3.Schedule Table 8: Schedule OBS Code Task of WorkAccountable person Date to startDate to end 2376Floor plan drawing Fredrick James16 June 201818 June 2018 Work package: start date: 16 June 2018end date: 16 June 2018 Additional comment: The work must be completed as agreed in all terms and conditions Prepared by:Peter KelvinDate: 02 march 2018 Approved by:David JonesDate: 05 march 2018 Critical Path Method (CPM) diagram for service facility project 27 Finish
6109ENG Construction Project Management, semester 1, 2018 Figure 4: Critical Path Method (CPM) diagram for service facility project 28 Project notice approval Develop Work plan Form project team Design contractors work In- house design work Design briefing meeting Floor plan Design review Foundation structureMech/elecArch finish Sanitary sewer On- site utilities design Site work design review Fencing of the area Concrete paving Site grading Project site work design Utilities design review Phone system design Domestic water system
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 Estimated Costs for the Construction Projects Bored excavation for 300mm diameter piers Table 9: Total volume is calculated by considering bulking factor of soil ItemParticularsUnitQuantit y Rate$Cost 1Bored excavation volume for 53 Ø300mm and 2.5m deep piers Cross sectional area of pier = πr2= π x 0.152= 0.07m2 Volume of pier = cross sectional area x depth = 0.07 x 2.5 = 0.18m3 Volume of 53 piers = 0.18m3x 53 = 9.54m3 Assume bulking factor of 1.4 (clay soil), total volume of soil material to be excavated for boring of piers = 1.4 x 9.54 = 13.6m3 m314$53571.43$750,000 Summary: A total of 5353 Ø300mm and 2.5m deeppier bores shall be excavated. For all the 53 piers, a total volume of about 14m3of soil material will be excavated for the piers to be bored. Table 10: Bulk excavation for general site preparation 29
6109ENG Construction Project Management, semester 1, 2018 ItemParticularsUnitQuantityRate$ Cost 2Bulk excavationm3150$3,533.3 3 $530,000 Overall bulk area of excavation (plus working space) = (12.83 + 4.08 + 2.00) x (11.87 + 2.00) = 18.91 x 13.87 = 262.28 Estimated depths at corners: NE – 0.69m, NW - 0.55m, SE – 0.50 and SW – 0.45) Average depth = (0.690 + 0.54 + 0.45 + 0.40)/4 = 0.55m Volume of bulk excavation = area x depth = 262.28m2x 0.55m = 144.25 Assume that only one side is battered = 18.91m x 1.0m wide x 0.55m = 10.40m3 Since battering is done at 45 degrees, battered volume is = 0.5 x 10.40 = 5.20 Total volume of bulk excavation = 144.25 + 5.20 = 149.45 Summary: A total of 150m3of shall be excavated from the site during general preparation of the site. This bulk volume includes working space, which extends outside the building towards the boundary by 1m. The longest side of the building shall also be battered at an angle of 45 degrees and a width of 1m from the building. The total bulk volume of 150m3to be excavated includes the actual site of the house, working space and battered 30
6109ENG Construction Project Management, semester 1, 2018 volume. The subcontractor has to use this value to determine the most suitable equipment to use for bulk excavation and if the excavated material will have to be cart away. 31
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
6109ENG Construction Project Management, semester 1, 2018 N25 concrete for the ground slab (beams, patio slab and pad footings) Thickness of slab = 150mm = 0.15m Thickness of beam = 450mm = 0.35m Width of beam = 100mm = 0.1m Table 11:N25 concrete for the ground slab (beams, patio slab and pad footings ItemParticularsUnitQuantityRate$C 3N25 Concrete for ground slabm3 Slab on ground = length x width x slab thickness = 12.83m x 11.87m x 0.15m = 22.84 m323 Patio slab = length x width x thickness = 6.35m x 1.67m x 0.15m = 1.59 m32 Family room = length x width x thickness = 5.51m x 4.08m x 0.15m = 3.37 m34 Beams on slab = total length of beams x width of beam x depth of beam = 82.82m x 0.1m x 0.45m = 3.73 m34 Pad Footings Area = 10(1.2 x 0.9) + (0.35 x 2.4) = 10.80 + 0.84 = 11.64m2 Volume = area x depth = 11.64 x 0.35 = 4.074 m35 Totalm338$22,894.7 4 $870,000 32
6109ENG Construction Project Management, semester 1, 2018 Summary: A total volume of 38m3of N25 concrete shall be required for the whole ground slab, including beams, patio slab and pad footings but excluding piers. Depending on the mix design recommended by the engineer, it noes becomes easier to determine the volume of concrete ingredients (concrete, coarse and fine aggregates and sand) needed for the ground slab. SL72 reinforcing mesh for the ground slabs Table 12: SL72 reinforcing mesh for the ground slabs ItemParticularsUnitQuantityRate$C 4Number of SL72 Reinforcing Mesh Sheets 4 (a)Area of ground slab to be reinforced with mesh (including 50mm cover) = length x width = 11.98m x 11.02m = 132.02m2 Area of family room to be reinforced with mesh = length x width = 4.66m x 3.68m = 17.15m2 Total area of slab to be covered = 132.02 + 17.15 = 149.17m2 m2150$6,00 0 $900,000 4 (b)Number of sheets = total area of slab/ effective area of SL72 Total area of slab to be reinforced with SL72 mesh = 150m2 Effective area of SL72 sheet = 5.8m x 2.2m = 12.76m2 Number of SL reinforcing mesh sheets No12 33
6109ENG Construction Project Management, semester 1, 2018 = 150/12.76 = 11.76 Summary: The total area of slab that requires to be covered by the SL72 reinforcing mesh is 150m2. Based on this area (and putting into consideration the required overlap length and cover at the edges), the number of 6.0m x 2.4m with 400mm lap SL72 reinforcing sheets required to complete the slab is 12. 34
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 Lengths of SL12TM for ground slab construction Table 14: Lengths of SL12TM for ground slab construction ItemParticularsUnitQuantityRate$C 5Length and number of SL12TM Trench Mesh 5 (a) Length of trench mesh (including 200mm lap) = length of one trench x number of trenches = 13.23m x 3 = 39.69m = length of one trench x number of trenches = 12.27m x 3 = 36.81m = length of one trench x number of trenches = 4.48m x 2 = 8.96m = length of one trench x number of trenches = 5.91m x 1 = 5.91m Total length of trench mesh = 39.69 + 36.81 + 8.96 + 5.91 = 91.37 m92$13,043.48$1,200,000 5 (b)Number of SL12TM trench mesh 16 sheets = Length of trenches/length of trench sheets = 92/6 = 15.33 No16 35
6109ENG Construction Project Management, semester 1, 2018 Summary: The total length of SL12TM trench mesh needed for ground lab (including overlap of 200mm at each end) is 92m. Since each trench measure comes in 6m lengths, the number of lengths of SL12TM trench mesh needed is 16. Therefore the contractor will have to supply 16 sheets of 6m long SL12TM trench mesh. 36
6109ENG Construction Project Management, semester 1, 2018 Structural steel Table 15: Structural steel ItemParticularsUnitQuantit y Rate$C 6Structural steeltonnes1.78$1,432,584.3$2,550,000 B1 Weight = 25.7kg/m x 12.83m = 329.73kg B2 Weight = 32kg/m x 12.83m = 410.56kg B3 Weight = 14kg/m x 11.87m = 166.18kg B4 Weight = 14kg/m x 11.87m = 166.18kg B6 Weight = 14kg/m x 11.87m = 166.18kg B5 Weight = 31.6kg/m x 12.83m = 405.43kg L1 Weight = 14.6kg/m x 4.08m = 59.57kg L2 Weight = 14.6kg/m x 5.51m = 80.45kg 37
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
6109ENG Construction Project Management, semester 1, 2018 Total weight = 329.73 + 410.56 + 166.18 + 166.18 + 166.18 + 405.43 + 59.57 + 80.45 = 1784.28kg Summary: The total weight of structural steel needed for the project is 1.78 tonnes. Plasterboard Table 16: Plasterboard ItemParticularsUnitQuantit y Rate$C 7Plasterboard 7 (a) Area of plasterboard Assume that the height of plasterboard wall is 2.4m Area of wall = length of wall x height of wall A1 = 11.93m x 2.4m = 28.63m2 A2 = 11.93m x 2.4m = 28.63m2 A3 = 11.93m x 2.4m = 28.63m2 A4 = 11.93m x 2.4m = 28.63m2 A5 = 10.97m x 2.4m = 26.33m2 A6 = 10.97m x 2.4m = 26.33m2 A7 = 10.97m x 2.4m = 26.33m2 A8 = 10.97m x 2.4m = 26.33m2 A9 = 3.63m x 2.4m = 8.71m2 m2245$1,632.7$400,000 38
6109ENG Construction Project Management, semester 1, 2018 A10 = 3.63m x 2.4m = 8.71m2 A11 = 4.61m x 2.4m = 11.06m2 A12 = 4.61m x 2.4m = 11.06m2 Total area of walls = 4(28.63) + 4(26.33) + 2(8.71) + 2(11.06) = 259.38m2 Deduct area of doors and windows Total area of doors = 5(2m x 0.9m) = 9.00m2 Area of windows = 6(1.2m x 0.8m) = 5.76m2 Total area of doors and windows = 9.00 + 5.76 = 14.76m2 Net measure = 259.38 – 14.76 = 244.62m2 7 (b)Number of plasterboard sheets The selected size of plasterboard sheets is 1200mm wide and 2400mm long Area of one plasterboard sheet = 1.2m x 2.4m = 2.88m2 Number of sheets = net measure of wall/area of one sheet = 245m2/2.88m2=85.07 No86 Summary: The total area of wall that will be covered with plasterboard is 245m2and a total of 86 plasterboard sheets measuring 1200mm wide and 2400mm long shall be required for the project. 39
6109ENG Construction Project Management, semester 1, 2018 66x18mm finished DAR primed pine skirting Table 17: 66x18mm finished DAR primed pine skirting ItemParticularsUnitQuantityRate$C 866x18mm finished DAR primed pine skirting 8 (a)Length of skirting L1 = 11.93m L2 = 11.93m L3 = 11.93m L4 = 11.93m L5 = 10.97m L6 = 10.97m L7 = 10.97m L8 = 10.97m L9 = 3.63m L10 = 3.63m L11 = 4.61m L12 = 4.61m Total length of skirting = 4(11.93) + 4(10.97) + 2(3.63) + 2(4.61) = 108.08m Plus 5% wastage Total length of skirting (including wastage) = 1.05 x 108.08 = 113.48 m114$2,631.5 8 $300,000 8 (b)Number of skirting lengths The selected length of 66x18mm finished DAR primed pine skirting is No48 40
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 2.7m Number of skirting lengths = length of skirting/ selected length of skirting L1: 11.93m/2.7m = 4.42 = 5 sheets L2: 11.93m/2.7m = 4.42 = 5 sheets L3: 11.93m/2.7m = 4.42 = 5 sheets L4: 11.93m/2.7m = 4.42 = 5 sheets L5: 10.97m/2.7m = 4.06 = 5 sheets L6: 10.97m/2.7m = 4.06 = 5 sheets L7: 10.97m/2.7m = 4.06 = 5 sheets L8: 10.97m/2.7m = 4.06 = 5 sheets L9: 3.63m/2.7m = 1.34 = 2 sheets L10: 3.63m/2.7m = 1.34 = 2 sheets L11: 4.61m/2.7m = 1.71 = 2 sheets L12: 4.61m/2.7m = 1.71 = 2 sheets Total sheets = 8(5) + 4(2) = 48 Summary: The total length of skirting is 114m and a total of 48 lengths of 66x18mm finished DAR primed pine skirting measuring 2.7m long shall be required for the project. 41
6109ENG Construction Project Management, semester 1, 2018 Ceramic floor tiles Table 18: Ceramic floor tiles ItemParticularsUnitQuantityRate$C 9Ceramic floor tiles 9 (a)Amount of ceramic floor tiles Family room = 4.08m x 5.51m = 22.48m2 Plus 10% wastage = 1.10 x 22.48m2 = 24.73m2≈ 25m2 Meals room = 2.43m x 4.68m = 11.37m2 Plus 10% wastage = 1.10 x 11.37m2 = 12.51m2≈ 13m2 Kitchen Floor tiles: 4.59m x 6.11m = 28.04m2 Plus 10% wastage = 1.10 x 28.04m2 = 30.85m2 Wall tiles (under cupboards) = 2(4.59m x 1.8m) + 2(6.11m x 1.8m) = 38.52m2 Plus 10% wastage = 1.10 x 38.52m2 = 42.37m2 Total kitchen = 30.85 + 42.37 = 73.22m2≈ 74m2 Foyer/stair area = 1.71m x 1.09m = 1.86m2 m2115$6,956.5 2 $800,000 42
6109ENG Construction Project Management, semester 1, 2018 Plus 10% wastage = 1.10 x 1.86m2= 2.05m2≈ 3m2 Total = 25 + 13 + 74 + 3 = 115 9 (b) (i) Number of boxes of floor tiles Number of boxes of floor tiles = area of floor tiles/1.2m2= (25 + 13 + 31 + 3)/1.2 = 72m2/1.2m2= 60 No60 9 (b) (ii) Number of boxes of wall tiles Number of wall tiles = area of wall tiles/1.4m2= 43m2/1.4m2= 30.71 No31 Summary: A total area of 115m2(including family room, meals room, kitchen and foyer/stair area) shall be tiled. 60 boxes of floor tiles and 31 boxes of wall tiles shall be required for the project. External opening Table 19: External opening ItemParticularsUnitQuantityRate$cost 10External opening Door frames, windows and finishes m2672.5$892.1 9 $600,000 Wrot mahogany Rebated frame 200 mm * 50 mm = 0.2 m * 0.05 m = 0.01 m2 Number of frame = 3000 Quantity = 0.01 * 3000 = 30 m2 Architrave 43
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
6109ENG Construction Project Management, semester 1, 2018 50 mm * 25 mm = 0.05 m * 0.025 m = 0.00125 m2 Total number = 1000 Quantity = 0.00125 * 1000 = 1.25 m2 Total area = 30 + 1.25 = 31.25 Number of doors = 22 Total area = 31. 25 m2* 22 = 627.5 m2 Carpenter rate per hour = $45 Total time taken = 15 hours Total labor cost = 15 hours * $45 = $675 Windows Windows size = 1500 mm * 1500 mm = 2250000 mm2 Number of windows = 20 Total area = 20 * 2250000 mm2= 45000000mm2= 45 m2 Windows board 125 mm * 25 mm = 3125 mm2 Curtain rod 25 mm diameter chrome curtain rod 20 mm diameter curtain Number of curtain rod = 6 Fixing of curtain rod = 6 hours Rate of fixing curtain rod per hour = $3 Total cost = 6 hours * $3 = $18 44
6109ENG Construction Project Management, semester 1, 2018 Table 20: plumbing cost Plumbing Item particularsUnitQuantityRateCost APlumbing work to Powder, Laundry, ensuite and Bathroom areas including the supply and fixing of all fittings. BSupply prices from provided PC schedule CLabour constants per Rawlinson 2014 DToilet suites to areas as noted;No4$25,600$102,400 Powder- 1 Laundry- 1 Ensuite- 1 Bathroom– 1 4 Supply (PC) $600 Labour 2.50 hrs @ $10,000/hr =$25,600 $800 each WC pan and cistern EShower bases to areas as noted; No3$30,500$91,500 Powder- 1 LaundryNil Ensuite- 1 Bathroom– 1 3 Supply (PC) $500 Labour 3.00 hrs @ $10,000/hr =$30,000 $30,500 Per shower base 45
6109ENG Construction Project Management, semester 1, 2018 FBaths to areas as noted;No1$20,750$20,750 Bathroom -1 Supply (PC) $750 Labour 2.00 hrs @ $10,000/hr =$20,000 $20,750 Per bath Total$214,65 0 Table 21: Drainage cost Drainage Item particularsUnitQuantityRateCost ADrainage work to Powder, Laundry, ensuite and Bathroom areas including the supply and fixing of all fittings. BSupply prices from provided PC schedule CLabour constants per Rawlinson 2014 DToilet suites to areas as noted;No5$50,600$253,000 Powder- 2 Laundry- 1 Ensuite- 1 Bathroom– 1 5 Supply (PC) $600 Labour 5 hrs @ $10,000/hr = $50,000 $50,600 EShower bases to areas as noted; No4$30,500$122,000 Powder- 2 46
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 LaundryNil Ensuite- 1 Bathroom– 1 4 Supply (PC) $500 Labour 3.00 hrs @ $10,000/hr =$30,000 $30,500 Per shower base FBaths to areas as noted;No1$30,750$30,750 Bathroom -1 Supply (PC) $750 Labour 3.00 hrs @ $10,000/hr =$30,000 $30,750 Per bath Total$405,75 0 Table 22: electricity cost Electricity Item particularsUnitQuantityRateCost AToilet suites to areas as noted;No4$30,600$122,400 Powder- 1 Laundry- 1 Ensuite- 1 Bathroom- 1 4 Supply (PC) $600 Labour 3 hrs @ $10,000/hr = $30,000 $30,600 47
6109ENG Construction Project Management, semester 1, 2018 BShower bases to areas as noted; No3$30,500$91,500 Powder- 1 LaundryNil Ensuite- 1 Bathroom- 1 3 Supply (PC) $500 Labour 3.00 hrs @ $10,000/hr =$30,000 $30,500 Per shower base CBaths to areas as noted;No1$20,750$20,700 Bathroom -1 Supply (PC) $750 Labour 2.00 hrs @ $10,000/hr =$20,000 $20,750 Per bath DHot tub areas as noted;2$30,500$61,000 Ensuite- 1 Bathroom- 1 3 Supply (PC) $500 Labour 3.00 hrs @ $10,000/hr =$30,000 $30,500 E Tape ware areas as noted;No3$21,000$63,000 Laundry-1 Ensuite- 1 Bathroom- 1 3 Supply (PC) $1000 Labour 2.00 hrs @ $10,000/hr 48
6109ENG Construction Project Management, semester 1, 2018 =$20,000 $21,000 Vanity areas as noted;No3$20,000$60,000 Laundry-1 Ensuite- 1 Bathroom- 1 3 Supply (PC) $600 Labour 3.00 hrs @ $10,000/hr =$30,000 $30,600 Total418,600 The approximate total cost of the project of building McGrade luxury house is $10 million 49
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
6109ENG Construction Project Management, semester 1, 2018 Risk management plan for program delays Table 23: Risk management plan for program delays Sub risk:Meanand standard deviation 1Shortageofskilfulworkers4.58 SD = 3.61 2Timeconstraint4.12 SD = 4.58 3Sub-contractorcorrelatedchallenges3.94 SD = 5.72 4Projectinterruption3.94 SD = 6.39 5Inappropriateauthenticationofcontractdocuments3. 83 SD =3.6 6Competitionoffered by othercorporations3.51 SD = 6.31 7Inappropriateprojectschedulingandbudgeting3.25 SD = 2.92 8materialspriceincrease 3.07 SD = 4.73 9Lossresultedtovariationofrate of inflation3.05 SD = 3.45 10Communicationproblem betweenclients3.03 SD = 4.47 11Lossresultedtovariationofinterestrate2.99 SD = 6.17 12Increased cost of labour2.95 SD = 6.88 13Shortage of Materials2.94 SD = 4.82 14Internal problems ofmanagement2.93 SD = 4.19 15Contract breachedbyprojectpartner2.91 SD = 1.99 16Inappropriatefeasibilitystudyof project2.86 SD = 5.07 17Unfamiliarconditions of site2.83 SD = 2.32 18Inappropriateorganizationstructureof a project 2.79 SD = 3.99 19 Lossresultedfrom fuelpricesrise2.75 50
6109ENG Construction Project Management, semester 1, 2018 41Governmentstandardsandcodes1.7 SD = 4.95 42Project partner bankruptcy1.69 SD = 7.53 43Site accidents1.57 SD = 3.52 44Accessoryfacilitiesprice increase1.54 SD = 3.65 45Lossresultedfromvariationofexchangerate1.43 SD = 3.34 46Topmanagementchanges1.43 SD = 2.54 47Supplyon fuelshortage 1.43 SD = 1.38 Conclusion The analysis conducted on McGrade house over has created and considered elective alternatives that enhance the first outline and development design. The last report fills in as the perfection of this analysis and a wellspring of thoughts for future undertakings. The discoveries and analysis are not planned at all to discover imperfections or saw botches in the genuine task. Building Information Modeling can be an extremely significant apparatus and process in building development. Through the Building Information Modeling Execution Planning Guide, created at Penn State, enables the greatest incentive to be accomplished with BIM. The McGrade house Project Team utilized BIM adequately on the task. Esteem Engineering is the procedure that incorporates creating and assessing elective construction strategies and systems to increase the value of a venture. In Analysis two the recommendation of LEED components being prohibited from the esteem designing procedure investigates a potential circumstance if the green rooftop was incorporated into the esteem building process. Through expulsion of the green rooftop, expanding the R-Value of the rooftop gathering and extending the grey-water framework, esteem was hypothetically included through a cost reserve funds and lessening of Potable water use in the activity of the building. Also the green rooftop stack on the structure will be 52
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6109ENG Construction Project Management, semester 1, 2018 evacuated permitting the size and weight of the steel encircling individuals to be decreased. References DelPico, W. (2012).Estimating Building Costs for the Residential and Light Commercial Construction Professional.New York: John Wiley & Sons. Peterson, S. ( 2014).Estimating in Building Construction.Chicago: Pearson Education. ASI Spray Insulation Professionals.(2011). Fireproofing + Thermal Insulation=Energy Savings and Protection:http://www.asispray.com. Border, T. (2011). Transportation Cost Information.(N. Diehl, Interviewer) Clark, P. (2011). Metal Stud Crete-Earl Corporation.(N. Diehl, Interviewer) Computer Integrated Construction Research Program. (2010). Building Information Modeling Project Execution Planning Guide. District of Columbia Department of Energy. (2011). Green Roofs in the District - Showcase Projects:http://ddoe.dc.gov/ddoe. Gamino, T. (2011). Electrical Rough in Informtion.(N. Diehl, Interviewer) Greensulate. (2011).Green Roof Diagram and Research. What is a Green Roof?: http://www.greensulate.com. 53