1MANAGERIAL FINANCE Executive summary The report is prepared for carrying out the feasibility of the manufacturing plant that is analysed by Dell Inc. for starting up. It is found from the project evaluation that the NPV of the project is $ 258,659,222.81. It is signifying that the project will be able to generate the amount of initial investment for the project IRR of the project is 26% whereas the cost of capital of the company is 16%. Looking into the payback period computation it is found that the payback period is 3.66 years and the discounted payback period is 5.88 years. Hence, the project is able to recover the amount of initial expenses within the useful life of the project. From all the aspect the project is therefore acceptable. Further, from the computation in question 2 it is found that for the project to meet financial disciplineit can borrow theamount maximum at interest rate of 15%.
2MANAGERIAL FINANCE Introduction The main objective of this professional report is to answer some question related to evaluation of the project that is projected to be started by Dell Inc. It is planning for setting up of new plant for manufacturing laptop. The report will analyse the profitability of the project through considering different approaches like Net present value, internal rate of return and discounted payback period. Based on the results from these approaches recommendation will be provided regarding acceptability of the projects (Žižlavský 2014) Question 1 Answer (a) Yearly depreciation expenses for the project are as follows – Depreciation schedule YearDepreciationBook value 0$500,000,000.00 1$50,000,000.00$450,000,000.00 2$45,000,000.00$405,000,000.00 3$40,500,000.00$364,500,000.00 4$36,450,000.00$328,050,000.00 5$32,805,000.00$295,245,000.00 6$29,524,500.00$265,720,500.00 7$26,572,050.00$239,148,450.00 8$23,914,845.00$215,233,605.00 9$21,523,360.50$193,710,244.50 10$19,371,024.45$174,339,220.05 Answer (b) Yearly cash flow from year 1 to year 9 Year123456789
4MANAGERIAL FINANCE cash flow 162,750 ,000.00 163,580,0 00.00 164,696 ,600.00 166,078 ,532.00 167,706,8 02.64 169,564,4 68.69 171,636 ,435.07 149,99 4,428.0 7 176,371,0 56.90 Answer (c) Cash flow in year 0 Year0 Initial investment$-500,000,000.00 investment in inventory$-100,000,000.00 Cash flow before tax$-600,000,000.00 Tax @ 45%$- Cash flow after tax$-600,000,000.00 Answer (d) Terminal or year 10 cash flows Year10 Initial investment Value of land Sales in units597546.28 selling price per unit$700.00 Sales revenue$418,282,399.02 Variable cost$-83,656,479.80 Fixed cost$-25,000,000.00 Depreciation$-19,371,024.45 investment in inventory Cash flow before tax$290,254,894.76 Tax @ 45%$-130,614,702.64 Cash flow after tax$159,640,192.12 Add: Salvage value Plant$150,000,000.00 Land Add: Depreciation$19,371,024.45 Recovery of inventory$100,000,000.00 Free cash flow$429,011,216.57
5MANAGERIAL FINANCE Answer (e) Net present value (NPV) NPV is the difference among present value of future cash flows from any investment and the amount invested for the acquiring the project. Present value of expected cash flow is calculated through discounting the cash flows at the required return rate. Positive NPV signifies better return and the negative NPV signifies worse return that is lower than zero. While any manager requires comparing the projects and deciding regarding which one is to be selected. It can be considered as a good approach for analysing the profitability of any investment in the entity or any new project of the entity (Leyman and Vanhoucke 2016). NPV approach provides various advantages like it considers the discounted cash flows while computing the computing the value of net cash flows. Further, it considers the cost of capital and the inherent risk while making the projections regarding future. Projection of the cash flows for 10 years into future is definitely lower as compared to the cash flow for the next year. Looking into the NPV calculation for the manufacturing plant of Dell Inc. it can be identified that the NPV of the project is $ 258,659,222.81. It is signifying that the project will be able to generate the amount of initialinvestmentfor theproject.Hence, ifthe projectistakenup itwillincreasethe shareholder’s wealth. Hence, considering the NPV only the project shall be accepted (Leyman and Vanhoucke 2017) Answer (f) Internal rate of return and payback period Internal rate of return (IRR)– IRR is the rate used for estimating the profitability of any investment. It makes the discount rate of all the cash flows from the particular project equal to
6MANAGERIAL FINANCE zero. For analysing any project on the basis of IRR, it is accepted if the IRR of the project is more than the project’s cost of capital. Looking into the IRR of the entity it is found that the IRR of the project is 26% whereas the cost of capital of the company is 16%. Hence, the project shall be taken up if the IRR is considered for taking up the project (Patrick and French 2016) Payback period– payback period is the time taken by the project for recovering the investment cost. To be more specific, payback period is length of time taken by the project to reach the point of break-even. Desirability of any project is directly associated with the payback period. Shorter payback period signifies that the investment is attractive as it takes less time to recover the amount of initial investment. Looking into the payback period computation it is found that the payback period is 3.66 years and the discounted payback period is 5.88 years. Hence, the project is able to recover the amount of initial expenses within the useful life of the project (Mellichamp 2017) Hence it can be identified that from all the aspects the project is acceptable as the NPV of the project is in positive, IRR of the project is more than the cost of capital and the payback period is less than the useful life of the project (Magni 2016). Answer (g) While analysing any project or investment for the purpose of investment, the cash flows from the projects are discounted to the present value for assuring that the undertaking’s true value is captured. Generally, discount rate applied is based on the market rate. However, on the basis of circumstances associated with the investment or project it is required to utilize the risk adjusted rate of discount. Risk adjusted rate of discount reveals the relationship among return and risk (Gorshkov et al. 2014). Practically, an investor is willing to exposed herself or himself
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7MANAGERIAL FINANCE to more risk and it will be rewarded through higher return as greater losses can take place. This is reflected under risk adjusted discount rate as the adjustment will make changes to the discount rate that is based on the risk faced. Further the expected return on the investment in enhances with the increase risk of the project. Most common adjustment to the risk is done due to the uncertainty to timing, duration of the cash flows and dollar amount. Apart from that, uncertainty is also there for the long term projects regarding future market scenario, level of inflation and profitability on investment (Lane and Rosewall 2015). The risk shall be adjusted for the risk adjusted projects based on the liquidity of the entity and the risk of default from the other parties. Hence, the entity shall adjust the discount rate for reflecting the investment with potential to damage the reputation of the entity that may lead to lawsuit or results into the regulatory issues. Hence, the company’s approach of using the same discount rate for all the projects is not appropriate and shall adjust the same based on the specific risks of the projects (Gorshkov et al. 2016). Answer 2 Answer (a) Total amount required to be raised through bank loan is 600 million. It is to be repaid in 10 equal instalments that is each instalment require payment of (600/10) = 60 million along with interest. For the project to meet financial discipline, the lowest amount of cash flow that is $ 14,99,94,428.07 that is the cash flow of year 8 will be considered. Hence after paying 600,00,000 as principle repayment it will left with 899,94,428.07 for meeting the interest expense. This amount can meet up the interest rate of 15% as computed in excel.
8MANAGERIAL FINANCE Answer (b) Pros of the new system are – Payment of interest and principle amount can be met comfortably with the cash flow available with the company The company will never fall short of the amount for making payment towards the loan over the useful life of the project. Cons of the new system are – Cash is just the projection and based on the same deciding regarding the loan and its interest rate will not be appropriate. Due to market changes or other unfavourable circumstances sales as well as cash flow in any year may not be as expected. In such scenario the company will face liquidity issue in meeting its debt expenses. Conclusion and recommendation Based on the above discussion it can be identified that in question 1, where the entity was considering taking up the project related to manufacturing plant, it is found that from all the aspects the project is acceptable as the NPV of the project is in positive, IRR of the project is more than the cost of capital and the payback period is less than the useful life of the project. Hence, it is recommended that the project shall be taken up. However, the system used by the entitythatisapplyingsamediscountrateforallprojectsisnotappropriateanditis recommended that it shall adjust the same based on the specific risks of the projects.
9MANAGERIAL FINANCE Reference Gorshkov, A.S., Rymkevich, P.P., Nemova, D.V. and Vatin, N.I., 2014. Method of calculating the payback period of investment for renovation of building facades.Stroitel'stvo Unikal'nyh Zdanij i Sooruzenij, (2), p.82. Gorshkov, A.S., Vatin, N.I., Rymkevich, P.P. and Kydrevich, O.O., 2018. Payback period of investments in energy saving.Magazine of Civil Engineering,78(2). Lane, K. and Rosewall, T., 2015. Firms’ investment decisions and interest rates.Reserve Bank of Australia Bulletin. June quarter, pp.1-7. Leyman, P. and Vanhoucke, M., 2016. Payment models and net present value optimization for resource-constrained project scheduling.Computers & Industrial Engineering,91, pp.139-153. Leyman, P. and Vanhoucke, M., 2017. Capital-and resource-constrained project scheduling with net present value optimization.European Journal of Operational Research,256(3), pp.757-776. Magni, C.A., 2016. Capital depreciation and the underdetermination of rate of return: A unifying perspective.Journal of Mathematical Economics,67, pp.54-79. Mellichamp, D.A., 2017. Internal rate of return: Good and bad features, and a new way of interpreting the historic measure.Computers & Chemical Engineering,106, pp.396-406. Patrick, M. and French, N., 2016. The internal rate of return (IRR): projections, benchmarks and pitfalls.Journal of Property Investment & Finance,34(6), pp.664-669. Žižlavský, O., 2014. Net present value approach: method for economic assessment of innovation projects.Procedia-Social and Behavioral Sciences,156, pp.506-512.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser