MANAGING RISK IN MODERN CONSTRUCTION
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
TABLE OF CONTENTS INTRODUCTION...........................................................................................................................1 TASK 1............................................................................................................................................1 (a) Project Identification..............................................................................................................1 (b) Research methods..................................................................................................................2 (c) Feasibility studies...................................................................................................................3 (d) Specification and brief...........................................................................................................3 TASK 2............................................................................................................................................4 (a) Identification of required resources, costs, personnel and timescales involved as a part of scope of project............................................................................................................................4 (b) Description of different kinds of techniques for potential solutions and stating clearly costs and cost planning involved..........................................................................................................5 (c) Preparation of Project management plan with resource and time tracking system included in work plan using PERT chart or CPM, and Gantt Chart..........................................................6 TAKS 3............................................................................................................................................7 (a) Evaluation of potential project management solutions using PERT or CPM chart...............7 (b) Justification of selected project solution with reference to Project specifications stated clearly in project scope................................................................................................................8 (c) Comparison of the outcomes of initial planned resources, timescales and costs with actual outcomes for review of performance...........................................................................................8 TASK 4............................................................................................................................................9 (a) written report of project by explaining all the stages of the project.......................................9 (b) Recommendation and final project outcomes........................................................................9 CONCLUSION..............................................................................................................................10 REREFENCES..............................................................................................................................11
INTRODUCTION Construction industry is one of those industries which has to remain updated with new and advance technologies and techniques as per the changing demand and needs of the market (Agyekum-Mensah and Knight, 2017). There are many civil engineering and construction problems that can impact overall construction project and can also degrade overall quality of the project, increase cost associated with project completion or can delay the project. Changing weather is one of the main problems associated with civil engineering and construction project. This project will lay emphasis upon addressing weather problems in civil engineering and constructionindustry.OrganizationfocuseduponinthisprojectisKellerGroupPlc organization. TASK 1 (a) Project Identification Construction industry is one of those industries which is growing continuously. Usage of advance technologies and techniques within this industry is also increasing. There are various kinds of problems that can impact construction done in civil engineering and construction industry.Weather problem is one of those problems that can impact this industry in many different ways. Due to extreme weather condition or sudden change within weather condition various kinds of problems are occurring(Moohialdin and et. al., 2019). Weather problem is one of the biggest barriers in this industry and can result in delay of project, increasing cost of construction and many other problems. This project will focus upon “addressing weather problemsincivilengineeringandconstruction”.Somemostcommonweatherproblems identified in civil engineering and construction industry are as follows: First problems identified is equipment or material damage or reduce in its efficiency. Unfavourable weather condition can impact overall performance of construction equipment’s and many times it can result in wear and tear of construction equipment’s. Labour shortage is another problem that can be created because of weather.Keller Group Plc is already experiencing shortage of skilled and knowledgeable labour and bad weather can enhance this problem to a certain extent. One of the most common weather problems is hot and dry condition of weather. Extreme hot weather condition can result in fast evaporation of water in concretes due to which its overall 1
strength can be compressed and sometimes it can result in decolouration as well(Yi and Wang, 2017). This clearly explains that there are many weather problems that are required to be addressed in this industry because it can impact overall construction work in various ways. Project aim To address different kinds of weather problems in civil engineering and construction. Project objectives To analyse different kinds of weather problems in civil engineering and construction industry. To recommend various ways though which weather problem can be addressed in civil engineering and construction industry. Reason of selecting this aim The main reason because of this aim has been selected is because weather problem is one of the most common problem that occurs within this industry and can impact construction project in many ways. It is extremely important for organizations likeKeller Group Plc to focus upon addressing weather problems in a timely manner so that damage that weather problem can create can be reduced (Ballesteros-Pérez and et. al., 2017). Many times, it is one of the main and primary reasons for increasing budget of the project and for delay in completion of project. (b) Research methods There are many methods though which data or related information for the project can be collected. It is extremely important to select an appropriate method for data collection as it helps in providing a brief idea about the project. For this construction project secondary data will be collected. By using different kinds of articles, books, research papers, journals weather problems in civil engineering and construction industry will be identified. IT will also help in identifying ways in which these problems can be addressed. From this secondary data it has been identified that weather problems mostly result in reducing performance of construction equipment or materials or in extreme cases it can result in wear and tear of construction equipment’s and materials(Sambasivan and et. al., 2017). So, for his project weather problems that has been chosen to be addressed is equipment or material damage or reduce in its efficiency. 2
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
(c) Feasibility studies Feasibility of a project is one of the most appropriate way though which all the areas of the project can be focused upon. Feasibility study of a construction project can help in identifying ways of addressing weather problem in civil engineering and construction industry so that projects can be completed successfully within specified deadlines. It can also be used for identifying alternative approach that can be used for addressing weather problem in this industry. It also helps in making sure all the work related to construction project are completed in an appropriate manner. There are many aspects or factors that can result in success or failure of construction project due to weather problems: Pre-emptive steps: These steps are one of the most important aspects that are required to be taken within construction industry especially at places where there are chances of weather problem to occur. These pre-emptive steps can result in success or failure of a project and many times in delay of project (Balogun, Anzari and Thwala, 2017). Keller Group Plc organisation need to focus upon all kinds of pre-emptive steps that they need to take so that adverse impact of weather upon construction project can be reduced. Not focusing upon pre- emptive steps that are required to be taken within construction project can result in: damaging construction equipment and materials or reduce in their efficiency, reducing quality of the construction project, delay in the project and many more. Detailed design: It is another important factor which is required to be focused upon within construction project that can impact a construction in many different ways and can become prime reason of success or failure of the project (Zuo and et. al., 2018). At detailed design stage all the problems associated with weather that can impact a project are identified. In detailed design all the precautionary measure taken within a project are included, additional material which is required to be included for protection of building from bad weather and many other steps are included. Financial plan: Detail study of financial plan helps in identifying all kinds of issues that can result in increasing budget of the project that can impact a construction project. (d) Specification and brief This project will lay emphasis upon “addressing weather problem in civil engineering and construction industry”. It is an important topic which is required to be focused upon because in this industry one of weather is one of the most common problem which is faced by civil 3
engineers in construction industry. Organizations likeKeller Group Plc need to identify all kinds of weather problems that can be faced by them so that they can take required measures or precautionary steps so that its adverse impact upon project is reduced.Detail description of specification of a project is one of the most important things which is required to be focused upon within a project that can result in success of a project(Mason, 2017). Specifications of a project is an important part of a project as it helps in identifying materials required to complete the project in a timely manner like preventive specification of this project that are required to be focused upon are: waterproofing, clean-up of Debris, excess water, and other foreign materials.. Each construction project should undergo a certain set of detailed steps so that they can identify problems that can occur in future in a timely manner. This identification of problems can help in timely addressing weather issues in civil engineering and construction projects. it can help in reducing direct/indirectimpactof weatherproblem upon construction and civil engineering project. TASK 2 (a) Identification of required resources, costs, personnel and timescales involved as a part of scope of project Project scope helps in identifying all the resources that are required for completion of a project. It also helps in identifying overall budget and time duration within which project is required to be completed. Scope of the project helps in identifying resources required for project, cost of the project, time duration of the project. Main scope of this project is to identify and address weather problem that can occur in construction and civil engineering projects so that effective measures can be taken such as pre-emptive steps, waterproofing, site clearing of debris, water etc. Resources and Personnel: Resources is one of the most important part of a project scope which is required to be focused upon. It helps in identifying all kinds of resources that are required for completion of a project(Johnson and Babu, 2020). It is also important to identify all kinds of resources that will be required within the project for addressing water problem effectively so that quality of the project is not compromised and can be completed within defined cost and time. Resources required to address water problem and complete project in a proper manner are: workforce, project manager, war material, project management tool, software for designing. 4
Cost: Another important part of project that help is identification of project scope is cost. Defining cost of the project helps in identifying cost required for addressing weather problem, maintenance of machinery and maintaining quality of the project, so that project can be completed successfully. Approximate budget required for completion of the project are £50,000. Timeline: It is important for project manager to evaluate and identify time duration which is required to complete whole project in a proper time period. It can be done by identifying time period required for completion of each activity so that overall time duration for the project can be identified. Overall schedule of completing this project on time is 100 days or 3 months and 8 days. (b) Description of different kinds of techniques for potential solutions and stating clearly costs and cost planning involved There are different kinds of methods or techniques that can be used for addressing and reducing water problems in civil engineering and construction projects. Solution that can be used for addressing water problems so that whole project can be completed within defined cost are: Pre-emptive steps are one of the best and most effective solution that can help in addressing water problem in construction industry is identifying pre-emptive steps through which impact of weather problems can be resolved (Demirkesen and Ozorhon, 2017). Pre-emptive steps such as performing clean-up so that debris, water or foreign material that has been collected due to bad weather can be cleaned so that its impact upon materials or construction equipment can be reduced. it will help in maintaining quality and performance of materials or constructionequipmentismaintainedandchancesofdamagedtothesematerialsor construction equipment is also prevented. Include weather forecasting information in schedule as it helps in identifying weather problems that can arise in future due to which quality of materials, building, equipment’s can be impacted. Both the solutions identified are cost effective and can be included within construction project which will not only help in addressing weather problems within specified budget but will also help in reducing it so that its impact upon project can be reduced, quality of construction equipment’s and material can be maintained and chances of wear and tear of equipment’s can 5
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
also be eliminated. Also, cost of pre-emptive steps and weather forecasting has already been included in overall cost of the project i.e. £50,000. (c) Preparation of Project management plan with resource and time tracking system included in work plan using PERT chart or CPM, and Gantt Chart There are various kinds of time tracking techniques or methods that can be used for preparation of project management plan. Two most commonly used methods are Gantt chart and PERT. Gantt chart: It is graphical representation of schedule of the project that also helps in identifying time period required by all the activities of the project to be completed. Task NameDurationStartFinishPredecessors Site planning10 daysMon 8/10/20Fri 8/21/20 Site plan approval5 daysMon 8/24/20Fri 8/28/201 Pre-emptive planning15 daysMon 8/31/20Fri 9/18/202 Inclusion of weather forecasting information in plan 10 daysMon 8/31/20Fri 9/11/202 Design approval5 daysMon 9/21/20Fri 9/25/203,4 Foundation15 daysMon 9/28/20Fri 10/16/205 Framing10 daysMon 10/19/20Fri 10/30/206 Completing construction work 30 daysMon 11/2/20Fri 12/11/207 6
PERT: It is a Project evaluation and review technique which is majorly used within projects for identification critical time interval required for completion of the project. PERT can also be used for calculating and identifying Crtical path that should be followed for completion of the project. TAKS 3 (a) Evaluation of potential project management solutions using PERT or CPM chart PERT chart is one of the most effective technique or method that can be used for evaluation of project management solution(Oleinik, 2018). It helps in identifying schedule, budget resources required for completion of project in an appropriate manner. it also helps in identifying sequential order of task which is required to be followed in order to complete the 7
project in a timely manner within defined cost. PERT chart has also helped in identification of effective solution that can be used and implemented within the project so that it can be completed in a timely manner. From the above PERT chart and critical path, it has been identified that out of both the solutions,Pre-emptive planning solution is more appropriate. PERT chart also helps in explaining that following this critical path task will also help in finishing the project within less cost and lower time duration. (b) Justification of selected project solution with reference to Project specifications stated clearly in project scope From the above project management techniques, it has been analysed thatPre-emptive planning is an appropriate solution that can be applied to the construction project. This is because this solution does not require software for collecting information of weather and overall construction project is not dependent upon this information. Pre-emptive planning can help in addressing with all kinds of weather problems in an appropriate and effective manner. PERT or CPM chart also helps in understanding that Pre-emptive planning solution is an appropriate solutionthatcanbeusedtoaddressmajorweatherproblemsincivilengineeringand construction. From the critical path identified from PERT and Gantt chart it has been analysed that time required for completion of the project is 90 days whereas initial identified time duration was 100 days. (c) Comparison of the outcomes of initial planned resources, timescales and costs with actual outcomes for review of performance If comparison of initial and actual resources is done then it can be said that there is difference in resources, timescale and cost required for completion of the project. Initial planActual plan ResourcesProjectmanagement software Weatherforecasting software raw materials equipment’s 15-20 workforce Projectmanagement software raw materials equipment’s 10-15 workforce Time scale100 days90 days 8
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Cost£50,000£40,000 So, from the above comparison it has been identified that as per the initial plan resources, time and cost required was much higher as compared to actual plan. TASK 4 (a) written report of project by explaining all the stages of the project Different stages of completing this project in an appropriate manner have been explained below: Project Introduction: At this stage examination of topic is done in which aim and objectives of the project are set. Here, examination of identified problem is done so that solution for the same can be identified. Aim of this project is “To address different kinds of weather problems in civil engineering and construction”. Project scope: It is another important part of a project in which overall scope of the project is identified with the help of required resources, budget and estimating time schedule required for completion of the project. Data Collection: At this stage data collection method chosen is selected though which information about the project is gathered. It is an important and useful step as it helps in collection of information for identifying and resolving main project problem. For this project secondary data collection method has been chosen in which in the form of literature review information is gathered. Data Analysis: At this stage transformation of collected information is done so that important and useful information can be extracted which will help in identification of solution though which identified problem can be resolved. Actions taken: At this stage as per the analysed information appropriate action is taken for supporting accurate results or outcome (b) Recommendation and final project outcomes Final findings of this weather problem project are that there are various kinds of weather problems that can impact an overall project. It has also been analysed thatPre-emptive planning solution that can be used and implemented for resolving and addressing weather problem in civil engineering and construction. Recommendations forKeller Group Plc organization for dealing within identified problem are as follows: Keller Group Plc can provide appropriate and required training to their employees 9
and workers so that they can enhance their skills and knowledge. This will further help them in addressing weather problem in a much appropriate manner (Du Plessis and Oosthuizen, 2018). Not only this, provision of training will also help civil engineers and project manager in doing Pre-emptive planning accordingly. It is also recommended to provide training to project manager about latest project management software and its features so that they can manage all the task, activities, resources of the project in an appropriate manner which will further help them in completing whole project in a timely manner(Van Rijn, 2016). CONCLUSION From the above assignment it has been summarized that there are various kinds of weather problems associated with civil engineering and construction project that are required to be addressed as they can impact the overall project in negative manner. Weather problems can impactconstructionprojectsinmanywayssuchas:degradingoverallperformanceof construction equipment’s or materials, damaging or wear and tear of construction equipment’s or materials, increase overall cost and time required for completion of the project, degrade overall quality of the construction project. It has been identified that there are man ways though which weather problems can be addressed but most effective solution for addressing this problem is pre-emptive steps. It has also been identified that project is one of the most effective way though whole construction project can be managed by fulfillinginitial requirement of the project and identifying appropriate solution that can be implemented within the project. 10
REREFENCES Books and Journals Agyekum-Mensah, G. and Knight, A.D., 2017. The professionals’ perspective on the causes of project delay in the construction industry.Engineering, Construction and Architectural Management. Ballesteros-Pérez, P., and et. al., 2017. Weather-wise: A weather-aware planning tool for improvingconstructionproductivityanddealingwithclaims.Automationin construction.84. pp.81-95. Balogun, O.A., Anzari, N. and Thwala, W.D., 2017. Adjudication and arbitration as a technique in resolving construction industry disputes: A literature review. InProceedings of the Sixth International Conference on Advances in Civil, Structural and Environmental Engineering. ACSEE. Demirkesen, S. and Ozorhon, B., 2017. Impact of integration management on construction project management performance.International Journal of Project Management.35(8). pp.1639-1654. Du Plessis, H. and Oosthuizen, P., 2018. Construction project management through building contracts, a South African perspective.Acta Structilia.25(1). pp.152-181. Johnson, R.M. and Babu, R.I.I., 2020. Time and cost overruns in the UAE construction industry: a critical analysis.International Journal of Construction Management.20(5). pp.402- 411. Mason, J., 2017. Intelligent contracts and the construction industry.Journal of Legal Affairs and Dispute Resolution in Engineering and Construction.9(3). p.04517012. Moohialdin, A.S.M., and et. al., 2019. Construction worker productivity in hot and humid weather conditions.Engineering, Construction and Architectural Management. Oleinik,P.,2018.Methodforcreatingaworkmanagementplanofaconstruction company.International journal of Construction Management.18(5). pp.446-451. Sambasivan,M.,andet.al.,2017.AnalysisofdelaysinTanzanianconstruction industry.Engineering, Construction and Architectural Management. Van Rijn, J., 2016. The work plan: project management.IMIESA.41(6). pp.61-62. Yi, W. and Wang, S., 2017. Mixed‐integer linear programming on work‐rest schedule design for constructionsitesinhotweather.Computer‐AidedCivilandInfrastructure Engineering.32(5). pp.429-439. Zuo, J., and et. al., 2018. Soft skills of construction project management professionals and project success factors.Engineering, Construction and Architectural Management. 11