The case for change This project is focused on developing a new facility for Mount Pleasant Community Healthcare Clinic so that they can easily manage the growing population and demand. The motive of this project is to provide Mount Pleasant Community Healthcare Clinic with a new place so that they can manage the growing obesity problem in the community.
Goal of the project The goal of this project is to develop a new facility for Mount Pleasant Community Healthcare Clinic to reduce the overgrowing problem of obesity in the community. This project will help to achieve the desired goals of the Mount Pleasant Community Healthcare Clinic.
Key objectives and measures Specific – New facility will be developed for treating growing obesity problem in the community. Measurable – New facility will provide treatment to persons in the community suffering from obesity. Achievable – New facility will help to reduce the estimated proportion of attendees at the clinic to 50% in 2035 which has been estimated to be 70%. Realistic – The growing number of people with obesity problem will be reduced by the year 2035. Time limited – The new facility will provide suitable treatment to the persons with obesity problem so that number of patients decrease by the year 2035.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Deliverables of the project The deliverables that will be achieved from the project are presented as below: Creation of conceptual design of the facility Creation of technical design of the facility Creation of funding document Analysis of market and competition A venue for the new facility Procurement of raw materials Designing of facility Development of facility Training to staffs Opening of the new facility
Work breakdown structure0 1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 2 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 4 4.1 4.2 4.3 4.4 4.5 4.6 4.7 Mount Pleasant Community Healthcare Clinic Development Project $1,142,120.002,216 hours Phase 1 - Initiation $5,880.00264 hours Determining the requirements $1,440.0064 hours Creation of conceptual design $1,800.0080 hours Creation of technical design $1,440.0064 hours Approval of project $400.0016 hours Review of the project $160.008 hours Preparation of draft $320.0016 hours Creation of funding document $320.0016 hours Phase 2 - Planning $1,008,480.00432 hours Evaluation of current business $1,080.0048 hours Research market and competition $800.0032 hours Evaluation of risks and threats $800.0040 hours Selection of venue $1,002,160.0096 hours Selection of contractor $840.0056 hours Selection of supplier $840.0056 hours Assessment of available resources $1,120.0064 hours Assigning task to development team $320.0016 hours Create resource allocation document $320.0016 hours Finalizing the plan $200.008 hours Phase 3 - Implementation $123,640.001,320 hours Designing the facility $1,600.0080 hours Review of design $400.0016 hours Implementing the design $3,360.00192 hours Procurement of raw materials $51,800.00120 hours Development of the facility $64,000.00800 hours Checking the construction $800.0040 hours Conducting evaluation of the facility $1,680.0072 hours Phase 4 - Closure $4,120.00200 hours Preparation of project document $320.0016 hours Presentation of report $480.0024 hours Standardizing the project $720.0032 hours Creation of facility blueprints $640.0032 hours Documentation of training materials $320.0016 hours Providing training to staffs $1,120.0056 hours Opening of facility $520.0024 hours
Gantt chart for the project
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Risk analysis and contingency plans Risk IDRiskDescriptionImpactProbabilityContingency plan 1Budgeting of projectOver budgeting of the project may leadto failureornon-acceptance by client HighMediumBudgetingoftheprojecthastobeapproved from client and financial status review have to be done on a regular basis 2Duration of projectExtendingtheprojectbeyond estimatedtimelinemayleadto failureorprojectandcost overhead HighMediumProgresshavetobemonitoredweeklyto determine the completion rate of the project 3Staffing for project teamLack of staffs in the project team may lead to delay of project MediumLowProper staffing has to be done with the help of resource management strategies 4Client-user staffingInadequate staffing may result into lengthening of the project LowLowProperstaffinghastobeensuredfrom client end after reviewing of the resource allocation from project team 5User departmentsIncreaseinnumberofuser departmentsmayresultinto changes in project scope LowLowStakeholders have to be engaged at every step of the project to ensure approval on fulfilment of requirements 6Administration and controlImproperchangecontrol managementproceduresmay result into project delay or failure MediumHighProper change management procedure has to be identified and implemented with immediate effect in case of any change in requirements 7Support from clientLack of support from clients may resultintowrongoutcomeand deliverables from the project HighMediumStakeholders have to be requested for feedback at each and every stage of the project 8Qualificationofproject development team Lackofprojectmanagement knowledgemayleadtodelayin project HighMediumThe professional skills and knowledge must be analysed prior to allocation in the development team
Project resources required Resource NameTypeInitialsStd. Rate Project managerWorkP$20.00/hr Business AnalystWorkB$25.00/hr Procurement manager WorkP$15.00/hr DesignerWorkD$20.00/hr ArchitectWorkA$25.00/hr Development officerWorkD$20.00/hr ContractorWorkC$10.00/hr SupplierWorkS$10.00/hr Raw materialsMaterialR$50,000.00 VenueMaterialV$1,000,000.00 The required resource for development of the Mount Pleasant Community Healthcare Clinic is presented as below:
Budget
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Timeframe for the project The project will take around 179 days from the initiation to completion. The project has been planned to start on 11 June 2018 and will accomplish on 14 February 2019.
Communications and reporting CommunicationFormatFrequencyDistribution Briefing of teamThroughrestrictedand secure intranet Every day at 09:30 AMTeamfortheprojectalongwith stakeholders that have access to secure project info area Weekly status reportsWith the help of internal intranet On a weekly basisProject team Project sponsor Senior management ReportforTechnical incident Through emailImmediatelyafter occurrence of an incident IT department Detailsonbudgetingand scheduling Withthehelpof spreadsheetsalongwith detailed Gantt chart Regular on a Weekly basisProject Sponsor Senior management Accomplishmentsalong with setbacks Email and intranetWeeklyInternal stakeholders Schedule milestonesEmail and intranetWeeklyInternal stakeholders Cost milestonesEmail as well as intranetWeeklyInternal stakeholders Analysis of risksEmail as well as intranetWeeklyInternal stakeholders
Bibliography Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge. Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn. Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298. JOSEPH. PHILLIPS, P. M. P., CBAP, I., & PMP, C. (2018). PMP PROJECT MANAGEMENT PROFESSIONAL STUDY GUIDE. McGraw-Hill Education. Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons. Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.