logo

Microsoft - Project Practicals - Assignment

4 Pages786 Words352 Views
   

Added on  2020-03-02

About This Document

In this document, we will discuss the Microsoft  - project practicals with a giant chart. 

Microsoft - Project Practicals - Assignment

   Added on 2020-03-02

ShareRelated Documents
MS-Project Practicals ChecklistStudent ID: ___________Student Name: _____________________________Check the status if you have completed the task. Give description where necessary. If you have taken any screenshots, place them below the table with a title. For example, Fig. 1 Network diagram.Practical-1Item StatusDescription1 Project Informationi.Change the start dateChangedii.Change Title & AuthorChangediii.Enter HolidaysEnterediv.WBS enteredEnteredv.Set Project Title as 0 taskDonePractical-2Item StatusDescription2 Adding Duration & relationshipsi.Durations entered Yesii.Predecessors enteredYesiii.Inserting lagsYesiv.What are the types of lags+ve lag: the duration by which successor is delayedthan predecessor is called lag-ve lag: also called lead [ CITATION Gup14 \l 1033 ]v.What do the different types of relationships mean?FS: successor cannot start unless predecessor finishesFF: successor cannot finish unless predecessor finishesSS: successor cannot start unless predecessor startsSF: successor cannot finish unless predecessor startsvi.Milestones addedYesvii.Displaying Critical Path‘Develop the Business Case Study report’, ‘Developthe Project Charter document’, ‘Document all necessary documents from client’, ‘Identify Scope’,‘Do risk assessment’, ‘Do Cost Planning’, ‘Develop Quality Management document’, ‘Develop overall PMP’, ‘Design database system’, ‘Develop proper logics’, ‘Trial run the system’, ‘Trial run the program’, ‘Install and Implement the system’, ‘Develop and submit user's manual for operation’, ‘Handover the developed system’ and ‘Document the lessons learnt’viii.How many CP(s) in this projectOneix.What is the slack for non-critical tasks17 days
Microsoft  - Project Practicals - Assignment_1
x.What does the CP suggest about the sensitivity of the network? Almost all the activity are in critical path, so the schedule is highly sensitivexi.Answered FS and TSFS (Free Slack): the duration by which the predecessor can be delayed without delaying the successor activityTS (Total Slack): the duration by which an activity can be delayed without delaying the final completion date or total duration of the project[ CITATION Kel07 \l 1033 ]xii.Screenshot of Network diagramFig. 1 Network DiagramFig. 1 Network Diagram
Microsoft  - Project Practicals - Assignment_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Practical Project Management and Tracking using Microsoft
|3
|439
|85