Development of ONLINE MANAGEMENT system for Stud Farm
STUDENT ID: <<STUDENT ID>>
STUDENT NAME: <<STUDENT NAME>>
SUBMITTED TO LECTURER: ANDREA MUTHU LAKSHMI
Development of ONLINE MANAGEMENT system for Stud Farm_1

Table of Contents
Part One:...............................................................................................................................................2
1.1 MOV - Measurable Organisational Value.....................................................................................2
1.2 Value of the project.....................................................................................................................2
1.3 Appropriate metric......................................................................................................................2
2. Part Two:...........................................................................................................................................4
2.2 Out of Scope................................................................................................................................4
2.3 Assumptions....................................................................................................................................5
2.4 Constraints...................................................................................................................................5
2.5 Scope Management Plan.............................................................................................................5
2.6 Resource Plan..............................................................................................................................5
Part three:.............................................................................................................................................7
3.1 Project Milestones.......................................................................................................................7
3.2 Project activities..........................................................................................................................7
3.3 Project resources.........................................................................................................................8
3.4 Time estimation...........................................................................................................................9
3.5 Project budget...........................................................................................................................10
3.6 Time phase budget....................................................................................................................11
Part four:.............................................................................................................................................11
4.1 Assumptions..............................................................................................................................11
4.2 Project risks and management strategy....................................................................................11
Part Five:..............................................................................................................................................13
Part Six:................................................................................................................................................14
a. Annotated bibliography...............................................................................................................14
b. Develop a closure checklist..........................................................................................................14
Bibliography.........................................................................................................................................16
Appendices..........................................................................................................................................18
Appendix 1: Annotated Bibliography...............................................................................................18
Development of ONLINE MANAGEMENT system for Stud Farm_2

Part One:
1.1 MOV - Measurable Organisational Value
Area of Impact Rank (1 to 5)
Customer 1
Operational 2
Financial 3
Social 4
Strategy 5
1.2 Value of the project
The desired project value are explained below:
Better: The organization assist in providing proper facility with the help of number of new
features which further improves the operational efficiency and thus the facility which are provided
are considered to be efficient.
Faster: It is analyzed that the online transactions service is quite faster in crediting or debiting
money in comparison to the present system which is used by the organization.
1.3 Appropriate metric
Rank Impact Metrics Timeframe
1 Customer 20% more
customers are
added for utilizing
the services
provided by the
organization due to
3 months
Development of ONLINE MANAGEMENT system for Stud Farm_3

the I-crop system.
2 Operational There is around
12% increment in
the efficiency of the
organizational
efficiency as the
organization can
easily manage the
operations.
3 months
3 Financial 12% hike is
reflected within the
yearly revenue of
the organization due
to increment within
the customers
number
2 months
4 Social The organization
utilizes social
platform like
LinkedIn as well as
Facebook for
promotion.
1 month
5 Strategy It is quite necessary
to use proper
2 months
Development of ONLINE MANAGEMENT system for Stud Farm_4

strategies for
managing the
development of the
system.
2. Part Two:
2.1 Scope
The scope includes:
The website as well as application are developed
Selection of the prototype
Designing the entire project outline
Reviewing the project design
Adding the option of the preferred buyers
Adding the option of transaction facility
The option for the seasonal sales is added
Giving proper training manuals
Providing the facility of training
Documentation
2.2 Out of Scope
The project out-scope include:
Excluding the details related with the suppliers as well as vendors
Facility of training is omitted from project charter
Development of ONLINE MANAGEMENT system for Stud Farm_5

2.3 Assumptions
The assumptions of the project include:
The project manager makes assumption such that entire project completes within time and
budget that is given
Proper support and help from the stakeholders will be get during the project progress
The project will progress as per the scope and thus the objectives of the project can be
achieved successfully.
2.4 Constraints
The project constraints are listed below:
It is essential to finish the work related with the project within 119 days
The entire activities of the I-crop system should be executed within the budget of $79,240.
2.5 Scope Management Plan
The project manager generally takes the initiative of managing the project scope so that no
scope related issues as well as challenges can occur within the project. The steps include:
Properly determining the project related issues
Identifying the various types of reasons due to which the problem of scope creep occurs
The scope of the project should be managed effectively
Proper facility of training must be given to the team members so that they can avoid scope
creep
2.6 Resource Plan
People: The people who are engaged within the project work are listed within the given
table.
Resource Name Std. Rate
Project Manager $50.00/hr
Financial Officer $45.00/hr
Developer $40.00/hr
Operational Manager $40.00/hr
Project Planner $30.00/hr
Project Sponsor $0.00/hr
Development of ONLINE MANAGEMENT system for Stud Farm_6

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Development of Online Management System for Stud Farm
|17
|3275
|118

Development of Online Management System for Stud Farm - Project Management
|16
|2409
|462

Project Management Best Practices
|19
|2232
|75

Project Management Case Study: i-Corp
|23
|2745
|126

Assignment on Project Management | PM
|21
|2437
|30

Development of a new online cash marketplace platform – I-Crop
|20
|2460
|343