Part Two: Define scope and scope management plan The management plan develops the scope of this online booking system, which collects requirements of both customer as well as project stakeholders. They are eliminated the conflicting requirements, track agreed scope to be delivered and verify the agreed project related deliverables. The plan is included of processes to prepare detailed scope statement. Define scope of the project In-scope: ï‚·Provide platform for customers to manage ticket bookings. ï‚·The customers can reserve online tickets and do payments throughout secured gateways. ï‚·Launch of web application ï‚·Online view of the information ï‚·Email reminders for the customers ï‚·Allow rescheduling of tickets ï‚·System testing ï‚·Complete plan within 3 months ï‚·Requirements documents are collected and recorded ï‚·Testing review and project specifications Out-scope: ï‚·Unable to cancel of tickets information online ï‚·Reminder of reservation schedules to the customers Assumptions and constraints Assumptions are: ï‚·Proper follow of the design of online booking system. ï‚·There are proper client/server architecture, hardware, software and network. ï‚·The new system should provide of real time information and future returns. Constraints are: ï‚·The project is completed within 3 months. ï‚·The project plan should meet its budget of AUD $100,000. ï‚·The plan should meet its scope to implement of online booking system.
Resource Plan ï‚·People ResourceStandard rate Project Manager$ 100.00/hr Marketing Manager$ 80.00/hr Production Manager$ 50.00/hr Finance Manager$ 80.00/hr IT Manager$ 70.00/hr Project Sponsor$ 40.00/hr Client Manager$ 90.00/hr Project Team$ 60.00/hr Analyst$ 90.00/hr Software Developer$ 60.00/hr Tester$ 50.00/hr Research&Development Manager $ 30.00/hr Risk Manager$ 40.00/hr Human Resource Manager$ 50.00/hr Project Planner$ 60.00/hr ï‚·Technology HardwareGraphic card, network interface card, RAM, serial port, optical disc, CPU NetworkHubs,stitches,routers,gateways, wireless access points SoftwareHTML, Java and PHP ï‚·Facilities The team is suited of onsite facilities to work into the organizational environment. ï‚·Other Travel requirementsTravel allowance Training requirementsTraining programs
Part three: Milestones for each phase and deliverable Task NameStart Milestone: Completed system planning phaseFri 3/2/18 Milestone: Completed system development phaseWed 4/25/18 Milestone: Completed system testing phaseTue 5/29/18 Activities/tasks Task Name Online booking system System Planning Phase Understand and explain the system requirements Utilize project specifications Meeting with project stakeholders Identify the project team Plan schedule and budget Milestone: Completed system planning phase System Development Phase Using flow chart of system processes Initial selection of process Start of system development Installation and change Focused on training
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Milestone: Completed system development phase System testing phase Design meets with business goals Check for errors Code review Verification and validation Written code of program Installation of developed system Milestone: Completed system testing phase Resource assignments Task NameResource Names Online booking system System Planning Phase Understand and explain the system requirements ITManager,ProjectManager,Finance Manager,MarketingManager,Production Manager ,Project Sponsor ,Project Team ,Research & Development Manager ,Risk Manager ,Analyst ,Client Manager,HumanResourceManager,Project Planner ,Software Developer ,Tester Utilize project specifications ProjectManager,ProjectPlanner,IT Manager,MarketingManager,Production Manager ,Project Sponsor ,Project Team ,Research & Development Manager ,Risk Manager Meetingwithproject stakeholders MarketingManager,ProductionManager,Project Manager ,Research & Development Manager ,Human ResourceManager,ITManager,Client Manager ,Finance Manager ,Project Planner ,Project Sponsor,Analyst,ProjectTeam,Risk Manager ,Software Developer ,Tester Identify the project team ProjectManager,ProjectPlanner,Analyst,Client Manager ,Finance Manager ,Project Team ,Research & Development Manager
Plan schedule and budget FinanceManager,ProjectManager,Project Planner ,Project Sponsor ,Client Manager ,Human ResourceManager,ITManager,Project Team,Research&Development Manager ,Analyst ,Marketing Manager ,Production Manager ,Risk Manager Milestone: Completed system planning phaseProject Manager System Development Phase Using flow chart of system processes Research&DevelopmentManager,Software Developer Initial selection of processProject Manager Startofsystem developmentSoftware Developer ,Tester Installation and changeSoftware Developer Focused on trainingHuman Resource Manager ,IT Manager ,Project Team Milestone: Completed system development phaseProject Manager System testing phase Design meets with business goals MarketingManager,ProjectManager,Project Planner Check for errorsSoftware Developer ,Tester Code reviewAnalyst ,IT Manager ,Software Developer Verification and validationSoftware Developer ,Tester Written code of programIT Manager ,Software Developer ,Tester Installation of developed systemSoftware Developer ,Tester Milestone: Completed system testing phaseProject Manager
Estimates of each activity and task Task NameDurationStartFinish Online booking system67 daysMon 2/26/18Tue 5/29/18 System Planning Phase5 daysMon 2/26/18Fri 3/2/18 Understandandexplainthesystem requirements1 dayMon 2/26/18Mon 2/26/18 Utilize project specifications1 dayTue 2/27/18Tue 2/27/18 Meeting with project stakeholders1 dayWed 2/28/18Wed 2/28/18 Identify the project team1 dayThu 3/1/18Thu 3/1/18 Plan schedule and budget1 dayFri 3/2/18Fri 3/2/18 Milestone: Completed system planning phase0 daysFri 3/2/18Fri 3/2/18 System Development Phase38 daysMon 3/5/18Wed 4/25/18 Using flow chart of system processes5 daysMon 3/5/18Fri 3/9/18 Initial selection of process7 daysMon 3/12/18Tue 3/20/18 Start of system development11 daysWed 3/21/18Wed 4/4/18 Installation and change5 daysThu 4/5/18Wed 4/11/18 Focused on training10 daysThu 4/12/18Wed 4/25/18 Milestone: Completed system development phase0 daysWed 4/25/18Wed 4/25/18 System testing phase24 daysThu 4/26/18Tue 5/29/18 Design meets with business goals2 daysThu 4/26/18Fri 4/27/18 Check for errors4 daysMon 4/30/18Thu 5/3/18 Code review6 daysFri 5/4/18Fri 5/11/18 Verification and validation2 daysMon 5/14/18Tue 5/15/18 Written code of program2 daysWed 5/16/18Thu 5/17/18
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Installation of developed system8 daysFri 5/18/18Tue 5/29/18 Milestone: Completed system testing phase0 daysTue 5/29/18Tue 5/29/18 Budget Task NameCost Online booking system$100,000.00 System Planning Phase$32,000.00 Understandandexplainthesystem requirements$7,600.00 Utilize project specifications$4,240.00 Meeting with project stakeholders$7,600.00 Identify the project team$5,840.00 Plan schedule and budget$6,720.00 Milestone: Completed system planning phase$0.00 System Development Phase$38,000.00 Using flow chart of system processes$3,600.00 Initial selection of process$5,600.00 Start of system development$11,920.00 Installation and change$2,480.00 Focused on training$14,400.00 Milestone: Completed system development phase$0.00 System testing phase$30,000.00 Design meets with business goals$3,840.00 Check for errors$3,520.00 Code review$10,560.00
Verification and validation$1,760.00 Written code of program$3,280.00 Installation of developed system$7,040.00 Milestone: Completed system testing phase$0.00 Figure 1: Gantt chart (Source: Created by author)
MS Project.mpp Ms project file:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Bibliography Amrollahi, A., Ghapanchi, A. H., & Talaei-Khoei, A. (2014). Three decades of research on strategic information system plan development.Communications of the Association for Information Systems,34(1), 84. Coronel, C., & Morris, S. (2016).Database systems: design, implementation, & management. Cengage Learning. Galliers, R. D., & Leidner, D. E. (2014).Strategic information management: challenges and strategies in managing information systems. Routledge. Goetsch, D. L., & Davis, S. B. (2014).Quality management for organizational excellence. pearson. Hubicki, M. (2014). Risk Management Plan. Kerzner, H. R. (2013).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Stark, J. (2015). Product lifecycle management. InProduct Lifecycle Management(pp. 1-29). Springer International Publishing.