Operations Management Project

   

Added on  2023-04-07

5 Pages669 Words51 Views
 | 
 | 
 | 
Operations Management Project
Name
Institution
Date
Operations Management Project_1

Question 3: Done in Excel Sheet (Attached)
Question 6 Solution
Network Diagram
Solution
a. Desired Output = 6
Operating Time = 60 minutes (1 hour)
Cycle Time = OperatingTime
Desired Output =60 minutes
6 =10 minutes per unit
Task Immediate
Predecessor
No. of Following
Tasks
Task Time
(Minutes)
Positional
Weight
A None 4 7 26
B None 4 4 23
C A 2 2 13
D A,B 2 8 19
E B 2 3 14
F C,D,E 1 2 11
G None 1 2 11
H None 2 4 15
I F,G 0 9 9
Total Task Time 41
Theoretical Work Stations = TotaTask Time
Cycle Time = 41
10 =4.1 5 workstations
Assigning Tasks to Workstations
Principle used:
We are going to start at the first workstation and select the longest eligible task based on the
precedence relationship or tasks with highest number of followers. This process of adding the
A 7
B 4
D 8
C 2
E 3
H 4
F 2
G 2
i 9
Operations Management Project_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
SCOPE, TIME AND COST MANAGEMENT (MBP1123)
|10
|410
|84

Critical Path Analysis Practice-Uploader
|10
|2126
|422

Industrial Engineering Assignment
|7
|1253
|94

Project Management | Assignment-2
|4
|286
|17

Business Process Design Assignment 2022
|11
|1948
|32

Project Network Analysis for Desklib Online Library
|6
|820
|407