Running head: PARALLEL COMPUTING
Parallel Computing
Name of Student-
Name of University-
Author’s Note-

PARALLEL COMPUTING1
1. Table showing tasks and dependencies
Task Name Duration Start Finish Predecessors
Baking a cake 58.75 hrs Mon 20/01/20 Mon 27/01/20
Project Approval 5.92 hrs Mon 20/01/20 Mon 20/01/20
Organize meeting with
baking team
65 mins Mon 20/01/20 Mon 20/01/20
Analyze the requirement 50 mins Mon 20/01/20 Mon 20/01/20 2
Confirm the Design 180 mins Mon 20/01/20 Mon 20/01/20 3
Project Approval complete 60 mins Mon 20/01/20 Mon 20/01/20 4
Planning 9 hrs Tue 21/01/20 Wed 22/01/20
Get ingredients details 60 mins Tue 21/01/20 Tue 21/01/20 5FS+1 day
Place order to supplier for
ingredients
60 mins Tue 21/01/20 Tue 21/01/20 7
Delivery of ingredients 300 mins Tue 21/01/20 Wed 22/01/20 8
Checking of delivered
ingredients
120 mins Wed 22/01/20 Wed 22/01/20 9
Baking day 3.08 hrs Thu 23/01/20 Fri 24/01/20
Weighing all the 60 mins Thu 23/01/20 Thu 23/01/20 10FS+1 day

PARALLEL COMPUTING2
ingredients
Preheating the oven to
180°C
15 mins Thu 23/01/20 Thu 23/01/20 12SS
Grease the cake pan 10 mins Thu 23/01/20 Thu 23/01/20 10FS+1 day
Creaming butter and sugar 30 mins Thu 23/01/20 Fri 24/01/20 12
Adding eggs and vanilla
essence
15 mins Fri 24/01/20 Fri 24/01/20 15
String the cake flour 15 mins Fri 24/01/20 Fri 24/01/20 16
Pouring batter in pan 10 mins Fri 24/01/20 Fri 24/01/20 17,14
Bake the cake 55 mins Fri 24/01/20 Fri 24/01/20 13,18
Testing 2.25 hrs Sat 25/01/20 Sat 25/01/20
Get client for testing 120 mins Sat 25/01/20 Sat 25/01/20 19FS+1 day
Test approval 15 mins Sat 25/01/20 Sat 25/01/20 21
Decorating the cake 3.5 hrs Sun 26/01/20 Sun 26/01/20
Whipping cream for
decoration
30 mins Sun 26/01/20 Sun 26/01/20 22FS+1 day
Make separate fillings and
flavours
60 mins Sun 26/01/20 Sun 26/01/20 24

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Designing Pharmacy App and Database Servers & Hardware
|11
|1662
|175

Project Management
|10
|784
|60

Calculations and diagrams for project management
|7
|557
|84

Project Management Schedule and Cost Estimation for Construction Project
|10
|955
|170

Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start:
|115
|2991
|4

Project Management Assignment: Answers
|9
|1409
|72