logo

Sales Budget and Cost Variances: Calculations and Analysis

   

Added on  2021-11-16

12 Pages3002 Words497 Views
1

Part A:

Sales budget:
10,000 x £100 = £1,000,000

Production quantitative:

Units
Sales 10,000
Less: Opening inventory 4,000
6,000
Add: closing inventory 2,000
Production required 8,000

Direct material usage budget:
XY: 8,000 x 5 = 40,000
WZ: 8,000 x 3 = 24,000

Material purchase budget:

Direct material XY(units) WZ(units)
Usage 40,000 24,000
Less: opening stock 16,000 9,600
24,000 14,400
Add: desired closing stock (opening stock + 25%) 20,000 12,000
44,000 26,000
x £1 x£0.50
Direct material purchases £44,000 £13,200

2

Direct labour budget:

Production Finishing
Production unit 8,000 8,000
x direct labour hours required x4 x2
32,000 16,000
x direct labour rate per hour x5 x7
Direct labour cost 160,000 112,000

Fixed production overhead budget:
Given: £96,000.

The administration, selling and distribution overhead:
Given: £275,000.
The value of the closing finished stock:

£ £
Unit cost:
Direct material XY: 5 units x £1 5
Direct material WZ: 3 units x £0.50 1.5
6.5
Direct labour for production: 4 x £5 20
Direct labour for finishing: 2 x £7 14 34
Fixed production overhead 12
Total direct cost 52.5
x unit in stock x 2,000
Closing stock value 105,000
Factory overhead absorption rate = £96,000 : (32,000DLH + 16,000DLH) = £2/DLH
Factory overhead per unit = £2 x 6 = £12

3

The cost of goods sold:

£
Opening stock : £52.5 x 4,000 210,000
Manufacturing cost:
Production units x total direct cost = 8,000 x £52.5 420,000
630,000
Less: closing stock: 2,000 x £52.5 105,000
Cost of goods sold 525,000

The budgeted profit and loss account for Wollongong Ltd:

£
Sales 1,000,000
Less: Cost of goods sold 525,000
Gross margin 475,000
Less: administration, selling and distribution overhead 275,000
Budgeted net profit 200,000

Part B:
(a). Calculate the detailed variances for each element of cost and total cost variances:
I. Direct material variance:
Actual price per unit = 585,600 : 122,000 = £4.8
Price variance = (actual price standard price) x total quantity used
= (4.8 - 5) x 122,000 = £24,400 (F)
This indicates a saving of £24,400, given the actual material cost per unit was lower than the
standard cost per unit. This was favourable (F) to profit.


4

Usage variance = (total actual quantity used standard quantity for actual production) x
standard price
= (122,000 - 119,000) x 5 = £15,000 (A)
Standard quantity for actual production = 7 x 17,000 = 119,000 meters
In producing 17,000 units, XYZ Ltd should have used 119,000 meters (7 meters x 17,000
units), instead of 122,000 meters. If this extra usage is valued at the standard cost, there is an
adverse usage variance of £15,000 (3,000 meters x £5).
Total variance = Price variance + Usage variance
= 24,400 (F) + 15,000 (A) = £9,400 (F)
The £9,400 favourable total variance . This variance might have arisen because XYZ Ltd
purchased cheaper materials. If this were the case then it probably resulted in a greater wastage
of materials, perhaps because the materials were of an inferior quality.
II. Direct labour variances:
Actual hourly rate = £251,680 : 24,200 DLH = £10.4/DLH
Rate variance = (actual hourly rate standard hourly rate) x actual hours worked
= (10.4 - 10) x 24,200 = £9,680 (A)
The difference between the actual and standard hourly rates (£0.4 higher) resulted in an adverse
variance of £9,600 in total.
Efficiency variance = (actual hours worked standard hours for actual production) x
standard hourly rate
= (24,200 - 25,500) x 10 = £13,000 (F)
Standard hours for actual production = 1.5 x 17,000 = 25,500 DLH
The difference between actual hours and standard hours (1,300 DLH) can be valued at the
standard hourly rate of £10, resulting in a favourable variance of £13,000. The favourable
efficiency variance has arisen because the 17,000 units took less time to produce than the
budget allowed for
Total variances = Rate variance + Efficiency variance
= 9,680 (A) + 13,000 (F) = £3,320 (F)
The £3,320 total favourable variance . It arises because the company paid less per direct labour
hour than had been budgeted. This variance could have been caused by using a lower grade of
labour than had been intended. Fortunately, the lower labour rate per hour did not change the
production quality.

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Sales Budget For the Period Ending 30-09-2014 Partciulars 30--4-2014 31-5-2014 30-09-2014 30-07-2014 31-08-2014 30-09-2014
|6
|1151
|314

Preparation of Budgets and Ethics in Cost Accounting
|9
|1976
|241

ACC 203 Assignment .
|10
|1503
|213

Management Accounting: Solved Assignments and Essays - Desklib
|19
|3305
|132

ACC200 : Introduction to Managerial Accounting
|5
|1479
|439

Calculation of Costs | Assignment
|4
|1222
|301