Personal Commitment Eoc 1: Dealing with Ethical issues Claim 1 From June to September in 2018, I worked as a Project Development Engineer for Shier of Wyndham and East Kimberly (SWEK) in Western Australia. Iwasinvolved with implementation of 2017/18 state government fundedblack spotprogramme recommendation. SWEK has identified a street with Kununurra district centre under black spot programme that is neededto be improved.During the safety auditing, SWEK identified problem of the Bandicoot Drive,whichwas a poor illumination at night time. This enhanced the high pedestrian and vehicle accident rate at night time. SWEK got the service of Ansel Technical Electrical consultants to design the street lights for the street. Theyused to visit the siteand designed street lights as per the standard guidelines. I made coordination with designer, Horizon power (Western Australia Electricity Power authority) and SWEK to implement this recommendation. When I received the design of street lights, I reviewed the design at site. Inoticed that somestreet lights were closed toa balconyof an apartment in Bandicoot Drive. Inoticedthat this installationcan challengethe privacy of the occupant in the apartment. Underfollowing ethical guidelines such as: Engineers Australia (EA), 1.3 Respect the dignity of all persons,4.1 Engage responsibility with the community and other stakeholders (Be sensitive to the public concern), and 1.1 act appropriately, and in a professional manner, when you perceive something to be wrong. Therefore, I instructed electrical design consultant to revise the design of particular location in the view of my finding. I highlighted my management in future safety auditing of the street should account ethical aspect as well. Moreover SWEK received severalfeedbacksfrom people for poor illumination at River Fig Avenue which isclosetothemain shopping area of Kununurra. It was also raised by SKEK planning department in their frequently safety auditing of the city centre. I raised this matter with Ansel Technical Electrical consultants to accelerate the design of the avenue. Then I prepared necessary application with comply with design and raised Purchasing Order with Horizon power to get the necessary material and implement the design as soon as possible. There I followed the ethic guideline of EA, 4.1 Engage responsibility with the community and other stakeholders (Be sensitive to the public concern). Claim 2 2
Between November 2004 to December 2007, I worked in the North-East Regionof AfghanistanastheRegionalEngineerforUnitedNationOfficeforprojectServices (UNOPS). During this period I implemented 24.5 km asphalt surfacing of Imam Sahib Connector road including 35 Culverts and floodway. We implemented this project onthe behalf of USAID (United State Agency for International Development). Ihadselected a contractorin orderto implement the project as per USAID and UNOPS guidelines. After the Contractor commenceddemarcatedthe right of way for the road corridor, my national engineers reported that a farmer had cultivated wheatinsome portion oftheland within the project limits. I immediately visited the site with municipal council officers and noticed that the road corridor had been clearly encroached. The Wheat fields were ready to be harvested, but the Contractor was about to commence clearing and grubbing on this land. When I met the farmer, he accepted that he had encroached on demarcated landandrequested me to consider delayingofthe works by two weeks, allowing him to harvest the crop. I realised that, though the Contractor was legally allowed to start work on the land in question,but it could have beenan ethical issue if wedid notlet the farmer to harvest. I discussed this with the Contractor's Project Manager and municipality officers to check whether he can proceed with the farmer's requirement without compromising the progress of the works. Contractor agreed to delay the works in that particular area and utilised his resources for works in another section with no additionalclient cost. Farmer was very happy for our solution to the problem.I also advised my national engineers to immediately investigate any other activities by residents that could potentially delay the progress of the works.Finally, I discussed this matterwith the Municipal Council to prevent such things fromhappening in the future, by maintaining appropriate level of communication with landowners, in particular of the legal implications of such actions. Project was completed well aheadofthe schedule and contractor was very happy with his outcome of the project. As a regional team leader, I assisted contractor to achieve this targets technically and logistically indifferentways. At the opening ceremony of the project I received a very expensive handmade rag from the Contractor, butrealised that accepting a gift from the Contractor could be an ethical issue. Code of Ethics of Institute of Engineers Sri Lanka (IESL) stated that 'Engineers shall neither solicit nor accept gratuities, directly or indirectly from contractors or their agents', and UNOPS code for Employeesas well. Therefore, I convinced thisethicalpractices and principles, bound to contractor anddeclined his gift. 3
Eoc 2: Practise Competently From March 2001 to Oct 2004, I worked for Toa Corporation (Japan) as a Civil Engineer in the Pulau Tekong Island development project ($1.2 billion, Singapore) in Singapore. Toa was engaged in the off shore land reclamation using sea sand and basic infrastructure development in the reclaimed land such as access road, terminal building, jetties and rock revetment of new reclaimed boundaries. Works carried out by me,included developing conceptual designs for rock revetment, internal road network and data processing for volume calculations for reclaimed land and site inspections. Within two weeks of my commencement in Toa, I was assigned to study Global Position System (GPS) basedsoftware’sfor survey data collection, processing, design and volume calculation. I followed trainingfromTrimble (Singapore) for GPS related software HydroPro Naviedit and Theramodel. These software’s were capableof surveyingdata collection in land and water (including seabed) and generate contour plans, cross sections and volume calculations.They werecapable of real time tide correction for hydro surveying. I generated contour mapping for the offshore area andcalculatedthe volume of sea sand requiredto fill the sea up to 2.5 m above the mean sea level (MSL). I was aware that I had very limited exposure to NaviEdit, and Theramodel during previous work experiences and new exposure. Therefore, whenever I had some free time, I followed built-in tutorials to increase my understanding of the command, tools and technique and efficient handling of the software. I kept good contact with Trimble (Singapore) technical coordinators/ trainers and gainedsome clarification from them. I discussedcompletesurvey to shear the knowledge with them. Within few months, I gained good knowledge of these software’s,ensured efficient generation ofinformation and plans for trailer suction hopper dredgers for dumping the sand at right location. Throughout this engagement, I tried to keep my competency levels high, utilised my experience and knowledge whilst applying engineering principles to resolve engineering problems. I produced designs thatcompliantwith standards and guidelines, like British Standards (BS), Singapore standard etc.Utilised allthe available resources such as AutoCAD and Land Development. I voluntary participatedinthe Eco sounding survey training with Trimble (Singapore) andinvolved others in it, when my work was less demanding. It gave me theconfidenceof conducting Hydosurvey of sea bed using Eco sounder and GPS software. I followed necessary manuals andlearnedthe process of instrument calibration before starting any survey of sea bed. Thisgavemore stabilitytoToa when Hydro surveyors were absent,as a viable option to cover any urgent survey due to my malty skill. My overall 4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
knowledge of surveying and data processing software made meanexpert in the field. I could identify any kind ofpotential problemwithin thesurvey data and analysed the reason for such poor data collection. With my knowledge of engineering principle and calculation I became a good volume calculator using Hydropro and AutoCAD. I was able to transfer some data between these two programme using DFX (Drawing interchange format) or CSV (Comma Separated Value) format of survey data in boththe software’s.The experience I gained for volume calculationenabledme to work as a team member of Toa Corporation international tendering team. When they quote for significant international tender Iworked long hoursaccording to the requirementin tendering work. I studied the effective use of MS Excel for simple programming and summarise and presentation of quantity extract from other software such as AutoCAD, NaviEDIT and Theramodel. To enhance my report writing and presentation skills, Ivoluntarilyparticipated inthe Toa staff developmentactivities, including one ISO 9001 quality assurance workshop in Malaysia as well. My employer maintained a system database that recorded the technical skills of each employee. In addition to updating this system, I also maintained a spreadsheet that recorded trainings and workshops that I participated. I underwent performance reviews in every 6 months during this employment, which helped me in assessing my competency and performance against those required by the employer to fulfil my duties effectively and efficiently. Through this process I was able to identify the areas I was under performing and needed improvements. As an example, during my first 6 months review, I recognised lack of experience and competency in handling work scheduling for tender submission. I discussed possible ways to improve my competency level in MS Project with Project Manager. He agreed to arrange a training course in MS Project formeat the earliest possible opportunity. I set an agreed target of achieving required competency in MS Project within 3 months. After participation in the training, I was able to practice the skills I gained in real business and was successful in achieving the required competency within given time frame for tender submission. As a Civil Engineer, I worked within my field of expertise. Whenever I had issues or concerns in incorporating inputs from other disciplines, such as survey, design code and geotechnical engineers, I sought advice from the relevantparties. The majority of my works involved incorporating design engineering requirements, which created more challenging situations. I maintained very close liaison with the senior design engineers who were very helpfuland made meunderstand their requirementswhich were neededto be incorporated in my designs. 5
It also helped me in enhancing my knowledge in the field of design and geotechnical engineering, including 3D modelling, volume analysis and the tools used in the industry. EoC 3: Responsible for Engineering Activities Between November 2004toDecember 2007, I worked in the North-East Regionof AfghanistanastheRegionalEngineerforUnitedNationOfficeforprojectServices (UNOPS). During this period, I was involved in Design and construction of 8 district centre roads in thought out North-East region of Afghanistan. I was the team leader for technical, logistical and Administrative matters. The donor of the programme was USAID and projects were delivered according to American Association of State Highway and Transportation Officials (AASTHO) standards and Ministry of Public Work (MoPW) Afghanistan. Project focused on development of internal roads network and drainage structures in city canters using DBST and Concrete pavements construction. Enhance the efficiency of internal road network, appearance, positive environmental aspect by avoiding dust and mud during the different weather condition were some of the output expectation of these projects. These road projects were very challenging due to remoteness of locations and lack of experience of contractors. During the first month in this project, I performed community and stakeholders consulting for the projects. I acquired data of the topographical survey that wascompletedby the third party. Based on these data designthatwere performed by road design team of UNOPS head office in Kabul according to AASTHO, MoPW standard. It took nearly year to finalise the design in Kabul office due to limited design resources and final approval from USAID. When I received the preliminary design, I reviewed them to identify potential issues and recommend necessary adjustments forsome sub projects. UNOPS programme manager delegated me more responsibilities to amend the design as per site requirements, due to my local knowledge, previous involvement in the design work and data collection. I noticed that there were some locations thatwere neededto be revised to contain the construction works within the right of way. Moreover some other developments implemented by another implementation agency without proper coordination with municipality officers were clash with our original design due to design delay. I recognised that there were a few adjustments that needed to be done through a quite complex process to resolve, including re-community consultation and assessment of construction delay and cost implications. The procedure I followed during the design revision included following steps. 6
Firstly, I amended the geometric design of the district centre to suit the present site conditions. During this step, I consulted and sought advice from the city municipality, local community, government officers, regional USAID representative and other relevant stakeholders. Ipreparedashortreport,includingcommunityconsultationoutcomes,arisk assessmentandcostvariations.Ialsodocumentedthefieldnotesanddesign calculations for each proposed design change and modified the designed drawing as required. Then, I forwarded the final revised drawings, report and supporting information to the senior design Engineer for his final comments and approval. The proposed changes were accepted by the programme manager subjected to a few changes. I took more responsibilities of these changes as head office team and was busy with another 6 regions of Afghanistan to ensure my projects starts on time. I got the soft copies of AutoCAD drawings and did necessary changes by myself. I ensured maximum utilisation of fund allocation of eachsubproject. Scope changes of some projects save some money and I moved this money to provide additional cover drain slabs with in the city limits. I obtained necessary templates, documents from Kabul Office and completed the BOQ for all sub projects with regional team. I ensuredand reviewed all quantities myself before finalising BOQ. I prepared all tender documents according to UN procurement guideline and got approval from procurement department. I performed tendering processes with my regional team and evaluated bids as per procurement guidelines. Evaluation process was little bit complicated as itwasneeded tobecompliedwith both UN procurement guidelines and some donors interest. Donor, USAID wanted toawardall jobs for local contractor and ban any bituminous product or construction materials from Iraq. Mostly bituminous product comes to Afghanistan from Iraq as it share borders with Afghanistan. So I took advice from procurement departmentin orderto comply with USAID requirements and our procurement guidelines. I managed to get approval for selectedcontractorwith in the approved time lines and budget without significant problem. We started the projects on time and manage to complete them as per USAID and UN financial discipline guideline.I managed to complete the projects in advance, on budget with various challenges such as incompetent local contractor, volatile security and natural calamities such as flood in several district centres. 7
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
EoC 4: Develop safe and sustainable solution Claim 1 Ihadcompleted the South Australia general construction induction CPCCOHS1001 with TAFE SA. This training is required for anyone who wants to visit or work on site and in theconstructionindustry.Itoutlinedmethegeneralworkplacehealthandsafety requirements for all work on site, and an appreciation of safety requirements required within my design. Ihadalso completed site specific and internal safety inductions such as Fortescue Metals Group Ltd (FMG) rail induction for Solomon rail spur project and Hansen Yuncken site induction for new Royal Adelaide Hospital project etc. Moreover Ihadcompleted RIIWHS205D and RIIWHS302D, traffic control and implementing the traffic management plans. From June 2012 to Jan 2013, I worked in Solomon rail spur project for Lucas Total contract solution (LTCS) as a project engineer. One of my main responsibilities was to ensure that adequate safety and environmental protection measures were in place. Whenever I observed or was reported ofany kind ofsafety or environmental issues, I immediately advised the Site safety coordinator to provide adequate measures at the earliest possible withintheinplacehazardreportingstructurewithsupportinginformation,including photographs, to take appropriate actions as per the project safety guideline. Any failure to abide by safety and environmental requirements was considered very seriously in this project. The project involved extensive earthworks with 0.2 m – 2.5 m rail embankment construction across traditional aboriginal land. Even though LTCS placed plastic barricading tapes alone the railway alignment, I noticed that the people were trespassing the barricades often. This raised a serious safety concern with heavymachineries' movingatthesite. I discussed this matter with site safety officers to established adequate signage. Moreover, I paid attention to educate the community with community lesson programme and reviewed the adequate safety crossing across the railway aliments. I further discussed this matter with safety coordinator with hazard report and explained the need of an appropriate measure to protect local people from potential hazards. Later, LTCS installed warning signs and installed plastic barriers, temporary fences at some critical sections All construction works had to beconfirmedto the Handbook of Environment Control (HEC), to the approved environmental management plan of Client, Fortescue Metals Group (FMG). I ensured that adequate silt control measures were in place as per the HEC, to prevent adjacent lands from siltation. I realised that there was a risk of siltation in the event that the top layer of the embankment fill left un-compacted overnight, particularly when rain occurs 8
during the same night. I discussed this issue with the site manager to arrange adequate compaction of the topmost layer before works are done for the day or avoid laying of material at the end of the day to control siltation. These actions ensured that the short and long-term environmental impacts from the construction works on adjoining lands were minimal. Throughout my involvement in this project, I ensured that I follow Safety Manual for the project that conformed Health and Safety and requirements in General Conditions of Contract, whenever I was on the site. For example, I ensured that I wear Personal Protective Equipment (PPE) all the time and had a bottle of water, a first aid kit and emergency flashing lights in my site vehicle. Claim 02 From March 2001 to October 2004,I worked as a Civil Engineer on Tekong Island Development project for Toa Corporation in Singapore. One of my responsibilities was to ensure that adequate safety and environmental protection measures were in placeas per the design;some soft groundsweretreated before placing,by any geo-textile materials as fillers to increase the bearing capacity. I observed thatthesegeo-textilematerialsgotunloaded at many locationsand were exposedto direct sunlight. From my previousexperience, I recognised that thishadadverselyaffectedthe properties of geo-textilematerials.From the manufacturer'sgivenspecifications, I found thatthese materialsshould not be exposed to direct sunlight for more than 72 hours as theywouldlose their propertiesdue to contact with UVrays. Idiscussedthiswith geotextilesub-contractorandrequested tofollowthe manufacturer's specifications which was supported by sub-contractor asI was right.Thus,I advised the sub-contractor to take immediate actions to protect thematerialsfrom direct sunlighton site,and alsoensured thatthese materials were coveredimmediatelyby a layer of construction materialafter its laid.Along with,I also issued a Sitevisitto the Contractor to comply withgiven instructions andspecifications in handling geo-textilematerialsat all the sites. Later, I noticed that there were some instances that the Contractor was not following in regard tomishandlingofgeo-textilematerials. In some cases, it wasalsoreported that materialshad been exposed to direct sunlight for more than a week. I raised this matter with my Project Manager and instructed the sub-Contractor to replace those with newset of materials without charging additional costs withthe Client. It impacted progress of the geotextile installation, butthisaction was necessary to achievethesustainable construction works. 9
EoC 5: Engage with the relevant community and stakeholders Between November 2004 and December 2007, I worked in the North-East Regionof Afghanistan as a Regional Engineer for United Nation Office for project Services (UNOPS). Iencountered with manynegativeexperiences fromprevious projects in thesameregion becauseof interferences by local communities and authorities duringthe implementation stage. This causeddelays, variations in projectandcreated dissatisfaction amongdonorsfor theannual financial planning.Sometimes the local communities which were led bypowerful ex-combated local soldierandcommanderschallengedthe project scope, security and safety with questionable remarks oncontractor and project staff.Therefore, I discussed this matter with my program manager andbuiltnew strategy to deal with such problems forthenext constructionproject in comingyears.We builta24.5 km Imma Sahib Connector road, linking two district centres tothemain National Highway ofthisregionandthe roadcorridor runsthrough paddyfieldsand farmingareas. During the planningof designingstage, I assigned two national engineers tointeract withtheCommunityConsultantundermydirection.Irequestedhimtoestablish4 community groups along the road corridortoget their opinions, views fortheproposed development. The leaders ofthesecommunity groupswerepowerfulandinfluentialand well connected withlocal elders. They assured smoothrunningof the project andprovided securitytoall project mates. Welistenedtothe queries of thelocal farming communityin the presence of all the leaders and involvedcommunity groups, whorequested to build around 12 newandupgradedculverts.ThenIcommunicatedthesedetailswithlocalirrigation authoritiesandmunicipal councils to finalise thescope.Later I receivedconfirmationfrom relevant stake holders forimportantaspects of the project such as irrigation structuresalong- withthemapping ofroad corridors. Iwasprovidedwith cleardesignbriefings forroad design team in UNOPS, Kabul Office. These community groups were well recognised at all the important events throughoutthe projects. They organised the inauguration and opening ceremonies of the project with the patronage of localpoliticiansand authorities. Moreover, I introduced them to another UN environment program to obtain somefundingsand resources topromoteplantation of trees along the road corridor. Due to lack of maintenance budget with local governments, we noted maintenance of the roadwould be challenginginthefuture. Therefore, I established a maintenance strategy with the community groupunder my programme manager's consultation. UNOPS established a maintenance fund, managed bythecommunity group leaders by focusingon thefuture maintenance. Most of theunskilled labourerswere employedinthe project through these 10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
community groups and 5 % of theirincomeswereabsorbedin thecommunity fund. Moreover, they were given 10% of local lease incomefrom thelandsallocated for theproject such as site camp, project officeandborrow areas. I have discussedthesematters in advance withtheProgramme Supporting Officer and procurement departmentas well.It was included in the project contractunderspecial conditionstocomplywith theprocurement guidelines. Projectrun wasverysmoothwith minimumdisturbancesfrom the community. Iwas always convincedaboutthebenefitsoftheRegionalRoadProgrammesuchasemployment generation,environmental friendly approachand socio economicaspectsofthis projectin receivingpositive support. Localcommunities werehappywiththeir ownership and overall participation of the projectto bringemployment opportunities. At the end of the project, UNOPS conducted a workshop for road maintenance with the leaders of local community groups, Local government officersandMinistry of public workrepresentatives.Theystressedontheimportanceofpropermaintenanceuseof community fund, technical knowledge and information of road maintenance. The community engagement ofthisproject was very successful anditwas used as a role model tosimilar projects indifferentregions. Regional representative of USAID (Doner of the project) was invited for the opening ceremony of the road project. Iwasconvincedaboutthe success of my team's community strategies that were used to complete it. The Regional representative was very happywith thepositive community engagement and assured morefundingsfor community based future projects. As a part of security assessment, I communicated with United Nations Mine Action Service (UNMAS) to acquire the mine clearance for most of the road projects. Imam Sabib road corridor was heavily contaminated with mines and unexploded ordnance (UXO). Moreover, I communicated very clearly with appropriate channelssuch aslocal, governors, government officers, local community leaders to get thedetailsof minecontaminationof barrow areas and road segments. Ialsomanaged to get de mining clearance well aheadofthe construction with proper coordination between the required stakeholders. During the project execution stages, I prepared monthly progress reports, financial reports, security assessment reports andsharedthese documents with UNOPS programme manager and USAID offices to keep them in the picture of project movement. In addition to that, I regularly engaged with my top management and other stake holdersviaemails, letters andphone-calls regardingthe regional project related matters. Iattendedand represented the updatesof UNOPS regionaloperationsin the annual UNOPS regional conference. This was presented bytheUNOPS top management, donors’representativesand other regional 11
engineers of UNOPS. I presented the annual progress review of ongoing legacy projects and upcoming project status of my region in the meeting with PowerPoint media. EoC 6: Identify, assess and manage risk Between November 2004 and December 2008, I workedatthe UnitedNationsOffice for Project Service as a Regional Engineer for North East Region in Afghanistan. During this period, I was involved in Imam Sahib Connector road project in Kunduz province. Not only this project, Ihavemaintained the risk registers for my all sub-projects.I always identified, assessed and managed risks for all my projects with my team's consultation. I maintained and reviewed the riskregistersregularly throughout projects with the details of ownership and mitigationmeasuresbyensuringabouttheresidualrisksasacceptable.ImamSahib connectorroadprojectwasassociatedwithvarioustypesofrisksmainlysecurity, geographicalconditions,lack of capacity of contractor and weather. Due to volatile security situation of the area, we made the security plan for the project underthe consultation ofproject'ssecurity advisor. Imaintainedgoodrelationshipswith regional security coordinators to get updated information of regional securityaboutproject. Before commencing the construction, I co-ordinated with United Nation Mine Action Service (UNMAS) to acquire the mine clearance for road corridor and barrow areas of the project. For each team site visit, we obtained the security clearance fromUN securitymain regional department and complied with theirrequirementssuch as regular radio communication, bullet proof vehicles, more than one car convoy at all the timeetc. Contractor was advised tokeep usinformed regardingany development at sitetomaintain goodrelationshipswith local community leaders, police and government officers. We received excellent support from 3 community groupsduring the progression ofProject belt. Wedidnotfaceany major security related incident during theproject'simplementation and itled tominimum impacton the overallprogress.Therefore,our initiativewasto identify, access andmanagethe security risksof the projectwhich was reviewed oncommendablelevels. The Contractor had planned to commence works from two ends of the project and movedprogressively towards the middle. Their intention was to commence construction of twin irrigation culverts when theyreachedthe locations along the road trace. Though the Contractor originally planned to commence earthworks beforerainyseason, there were many issuesthat delayedthe work. The Contractor was planning to increase resources to catch up withthe lost progress, but it was alreadymonsoon before commencement ofearthworks. I realised that there was a risk in achieving the progress due to weather conditions andmight 12
raise thewater table. Any delays in embankment construction would adversely affect the progress of the culvert construction too. I proposed considering alternative accesses for culvertlocationsthroughadjacentprivatelands(withnecessarypermissionfromthe landowners)andhence,culvertconstructioncouldbestartedimmediately,withless dependency on progress of earthworks to mitigate the identified risks. Eventually, the Contractor managed to come to an agreement to use a part of their land to access culvert locations. I encouraged contractor to maintain the good site diary with weather details. We established a rainfall gauge at the project site. My site engineers alsomaintainedsite weather chart. In theeventofin completion of project on time, the contractor could use valid reason for taking permission for time extension. However, contractorwasable tocomplywiththe original time scheduledue to ourclosed guidance and corporation. During the tendering process, it was very hard to find a confident contractor to completethe project due to remoteness and logisticalissues. As I knew thecapacitiesof contractor, I alwaysguidedthe contractorto followappropriate ways to meet theproject's time line. As per my directions, my national engineers closelymonitoredtheproject's construction andspecific requirements. I acquired 10 ex-combated supervisorsforthe project from another UN training programme. UNOPS laboratory technicians were directed to work closely with contractor’s supervisors to achieve the right compaction. When contractor faced problem tolocatebase coursematerialsaccording tospecific requirements, I directed my team to modify the existingmaterialsto meet thespecificationswith necessary blending. To avoid any cash flow problem to project, I closely discussed with contractor andduringsome months,Ihadprocessed more than twopaymentsrequest. In fewoccasions, Ihadmade advancepaymentsto the contractor, in the basis of “material at site”. Therewere damagesto culvert atongoing construction due to uncontrolled irrigation flow. It was beyond the control of contractor. Local irrigation department washeldaccountable for such damage. However, I assessed the damageandconvinced my programme manager to pay for the damage under clause for “Force Majeure” in contract. Ihadprocessed this payment within a monthand was alwaysmotivatedandencouragedthe contractor to achieve theproject'sgoals. EoC 7: Meet legal and regulatory requirement Claim 01 From June to September 2018, I worked as a development engineer with Shire of Windham and East Kimberly (SWEK).One of my main responsibilities was to assess the Development applications and subdivision applications. These applicationsneeded to be 13
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
assess with in certain time frame withspecifiedregulatory requirementsin accordance with theCouncil Development Policies, Building Code of Australia (BCA), Disability access requirement withcomplianceof AS 1428. SWEK policies were mainly developed with followingMain road Western Australia and other Australiastandards.The applications neededspecial attentiontostormwaterrequirementsas high intensity of rain and strong wet seasonaffectedstormwater run-off, fromproperly managednew developments. As a solution for developments in the SWEK,there were requirementsto retention, on site storage and disposal on site of runoff from 0.2 Annual Exceedance Probability (AEP, Annual rainfall) stormwhichIhadperformed necessarycalculationsto ensure compliancestorage. WhileAssessing the subdivision application, itneededto be comply with model subdivisionconditions,majorinfrastructureandenvironmentpoliciesonthebasisof schedule of Western Australia Planning Commission and other councils. I assessed the application against theguidelinesof model subdivision condition schedule incontext to project'sinfrastructure aspect. SWEK planning department haddifferent criterion’s while assessingthisapplicationsuchasZoningrequirements,floorareaanddriveway requirements. I ensuredaboutmy applicationtocoordinate with planningrequirementsand my decision was concurrent with Engineering managerfornecessaryconsultationand his directions. Claim 02 Between November 2004 and December 2008, I worked in the United Nation Office for Project Service as a Regional Engineer for North East Region in Afghanistan. During this period, I implemented 24.5 km asphalt surfacing of Imam Sahib Connector road projects including 35 Culverts and floodway.It was followedon UNOPSdesigning guidelines, tenderingand constructed the project under USAID directed funding. My duties included preparation ofconceptualproposals and detaileddesigning for documentation. This provided a good opportunity and a great challenge for me to develop and perform as a Design Engineer under the direction of Chief Technical Advisor (CTA) and Chief Design Engineer in Kabuland worked underUNOPS head office. First, I studied the design and documentation criteria using previous project proposals, design reports and the designguidelinesthat had been drafted by a CTA. I also acquired copies of Terms of Reference document, applicable legislations and codes and contract specifications from my CTA. I also obtainedthelatest versions of key legislations and regulatory documents that wereapplicable from the operational and procurement department of UNOPS. Through this 14
process, I gained an understanding of the relevant legal and regulatory requirements of the design delivery. I prepared designs and design documentation for the sub-projects that I was involved with the coordination of my national engineersand guidelinesof Chief Design Engineer. In addition to the design drawings, I prepared feasibility study reports, conceptual and detailed design reports, contract specifications, bid documents and engineer's estimates. I also wrote special conditions for particular contracts, with reference to the General Conditions section of the contract documentation. The project included preparation of reports that consisted of various components such as baseline study, option analysis, socio-economic study, benefit-cost evaluation, risk and affordabilityanalysisandinitialenvironmentalexamination.Thesewerecompulsory components of any road development project in Sri Lanka and had been clearly specified under UNOPS and USAID project executionguidelines. I ensured that those aspects were well covered and explained in the reports I prepared, by referring to the relevant sections of Terms of Reference (TOR) and relevant regulatory documents. I also developed check-lists to be used during different phases of the sub-project feasibility studies to ensure the worksand tocomply with the regulatory requirements. I paid special attention to the regulatory requirements specified in the Ministry of Public Work (MOPW) guidelines to ensure smooth handoverofthe project'executionat the end. The projects were designed according to MOPWguidelines which wasbased on AmericanAssociationofStateHighwayandTransportationOfficials(AASHTO).I consulted experts to get advice on some specific areas. For example, when I was writing sections related to the Environment impact assessment, I sought advice from the Project Environment Officer aboutreport contents to beaccurately addressing theTOR requirements. Moreover, I studied some previous reports as wellonthe USAID funded road programme. However,I had limited experienceonSocio-economic studies, Iconsultedthe CTA to get confirmation in regard to the relevant sectionsofTOR. EoC 8: Communication Claim 01 I worked with Lucas Total Contract Solution (LTCS) from June 2012 to Jan 2013. I was assigned as project engineerofNew Royal Adelaide Hospital construction project in AdelaideCBD.ThemaintasksbyLTCSinvolvedGroundpreparation,excavation, 15
backfilling of column footing and foundations, embankment, subgrade preparation for car park and access road construction in the project. A full time project manager was not assigned by LTCSandtherefore, I worked as the site coordinator at the initial stage of the project. Asthesitemainrepresentative,Imaderegularcommunicationbetweenmain contractor, HYLC Joint Venture (JV), LTCS, Subcontractor and other internal and external stake holdersofthe project. Project communication and document managementweremainly done through Aconex document management system. I effectively used the system mainlyto communicate with HYLC (JV). According to projectspecifications, IconductedInspection and Test Plan (ITPs) and submitted to HYLC (JV) senior engineers to review via Aconex. Accordingtotheirfeedback,projectdemandandspecificationrequirement,I amended ITPs, where HYLC (JV) safety officers implemented project safetyinserious manner. I communicated with site supervisors and safety coordinators of LTCS to ensure Safe work method Statement (SWMS) submitted to HYLC (JV) safety department in due time. I instructed andmonitoredmy site stafftocomply withproject'ssafety plan. I regularly conducted tool boxmeetingswith LTCS staff and represented LTCS with HYLC (JV) in various site coordinationmeetings.When any safety related incidentoccurred atsite, I raised the safety incident report anddealtwith HYLS (JV) safety supervisors to resolve the matter without much impactonthe project. There wasonce aproblem at site due to high moisturecontentwith compacted material.Itnegativelyaffectedthe test result of field compaction tests. Golders Associates worked as the project independent testing authority. I arranged informal discussion with Golder field technician and LTCS site supervisor to resolve the matter. According to Golder site technicians feedback, I stressed my supervisorstomaintain the right moisturecontentof filling material. I regularly communicated with Golder managers and technicians to carry out field compaction test, CBR and proctor compaction test as required. Project consisted with interdependent work schedule among subcontractor.LTCS needed to handover prepared subgrade or surfaceforconcreting within schedule timeto tacklefailureandhandoverit to any lotthat mightadversely affectonother subcontractors. For example, order from concrete mixing plant and manpower and equipment at site can be idlingwithother sub-contractor. Therefore, I maintained strong communication and connection with Golder management, theirsite supervisors, technicians and other sub contractor’s representatives at site. I updated 16
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
test reports, safety reports, and other project specificdocumentsto ACONEX document management system to share and review information with HYLC (JV). I regularly communicated with HYLC (JV) project engineer and management to schedule and update our work and ensure LTCS machineries and manpowerarenotidleat site. To meet the high demand of site I coordinated with my project manager, LTCS Plant manager to mobilise the additional equipment and manpower to the site as required. During the breakdown of machineries and equipment, I communicated with LTCS workshop and mobilised mechanical technicianswhich were available atsite immediately without giving much impact to the site progress. Moreover, I communicated with LTCS workshop and authorise heavy vehicle service providers (PIRTEK) to get the service of heavy machineries and equipment in due time. Service record of site machineries were updated to ACONEX as a part of site safety requirement. When I needed to verify the finished level of subgrade or calculated thevolumeof back fill, I communicated with Lucas survey department and mobilised the surveyor to the site as project did notassignfulltime surveyor. I ensured advance coordination with survey coordinator to avoid any potential delay to site progress or progress claim. I regularly reported project progressonmonthly, weekly and daily basis to the engineering manager and project manager. I reflected daily productivity, resources, site issuers and scheduled task in my daily progress report. When site needed the service or material, I called quotations from supplier and selected the supplieras perthedirections from my project manager. I processed the payment request of subcontractors and supplier and forwarded their claim to LTCS financial departmentwith delivery docketsand other supporting documents.I kept good contact with my site staff and sent their time sheets and leave request to LTCS administrative department regularly. I communicated with LTCS finance department, my project manager and prepared monthly progress claim. Moreover, I followed up progress claim with HYLT (JV) finance officers to avoid any delay. EoC 9: Performance BetweenMarch2001andOctober2004,IworkedinPulauTekongIsland development project in Singapore with Toa Corporation, Japan. My duties included detailed design documentation, drafting, Survey data processing, calculation and site inspection. I acquired necessary training and work as a survey data processing using GPS based, design software, NaviEdit, Theromodel and Hydropro. Hydro surveys provided the Eco sounding data using compatible GPS software use as a row data foe these applications. I followed 17
severaltrainingswithTrimble-SingaporefortroubleshootingofGPSinstallationfor sounding survey and handing of related software.Then Iusedto do data processing for construction requirement,generatedseabed profile, andfilled thevolume calculation up to +2m from the Mean Sea Level. While Iwas getting trainingfor Survey data processing, I learnt the use ofNaviEdit for field data collection. In addition to Survey data processing and calculation, I used to work as a Hydro survey during different stage of project as per project demand. Therefore, I grabbed overall knowledge ofsoftware,itsapplication and capacities within fewmonths. During my involvement in the project, I noticed that there was room to improve the design, survey and drafting software application process. One deficiency that I noticed was the inconsistency and lack of accuracy of my volume calculation with relevant to main sand supplierto the project, Jan-De- Nul. This often created discrepancy anddelayedthe payment request of Sub contractor.Jan-De-Jul owned and operated with massive trailer suction hopper ship fleets and latest navigation and survey technologies with first hand experience in that field. I initiated a discussion with the survey team leaders, design engineers, draftsmen and senior management to examine this issue and find a solution. Following the discussions I realisedthatthe main reason for this issue was the quality of survey practices andits application in our team. The surveys were conducted by 3differentgroupsfor duration of 24/7 to facilitate the sand dumping operations throughout the day.Someclauses in the survey methodology were very subjective andwere followed in different ways by different surveys. For example calibration needed to be done in stable water and reclamation site often consist with strong current, which discourage such calibration, therefore calibration of echo sounder attachedtothesurveyvesselswasnotperformedateachshift.Moreover,lackof coordinationwithinthe survey and design teamwasalso noted. To overcome the identified deficiencies in these software applications, I proposed to revisethe methodologyfor maintainingthe high quality of work. The key points in the supplementary guidelines were: Compulsory calibration of echo sounder beforecommencingsurvey To capture more seabed elevation in surveying, reduce the distance between survey paths Observation and react to the current pattern of the project side. To ensure that before applying tide correction,tide datais comparedwith Jan-De – Nul tide data. Edit the daily survey report format to capture vital data and ensure proper handover between shift and raw data to the design/processing team. 18
This new approach increased the quality of survey data and volume calculation.It significantlyaffected the efficiencyof survey process.The breakdown event of surveyvessel, also affectedthe progressof sandfilling operation. To overcome these challenges, my manger decided to get the service of another vessel and installed the Survey system as required. Toa was an international marine construction contractor and extensivelyinvolved in international tenders and projects. The experience Ilearnedfrom quantity extraction and drafting, paved me to serve with TOA international tendering team during the final stage of theproject.Indepthknowledgeofcalculationandrelevantsoftware,accuracy, accountability, attention to details and flexibility of working hours were key expectation of the team. I worked extensivelyforlong hourswith teamto cover the deadlines of tender submission. I used AutoCAD, Theramodel, and Excel to extract the quantities effectively. As a part of tender document requirement Ilearnedto prepare work programme with MS Project and analyse the critical part to fix the project time frame. I used to analyse the previous biding documents and maintained the data base for work norms and rates to ensure the good outcome for tender. Toensureeffective quantity calculation I developed excel programme. Data reportwas generatedfrom drafting/processing softwarefor directly exporting it toexcel for accurate and efficient calculation.I also maintained the discipline require for tendering such as secure, and buck up the data and maintain the privacy with sensitive information of the TOA corporation.We managed several on board projectsfor Toadepending upon organisation interest and work capacity. EoC 10: Taking Action Claim 1: From Sep 2018 I am working with Mindura Rural City council as a project Delivery Engineer. My duties mainly include supervision of project construction as per project specification, with in the time line, budget and quality and project tenderingmatters. Iinvolvedwithconstructionsupervisionof300mdoublebituminoussurface treatment (DBST) of Rodger St Construction, in Mildura city. Project Consist with pavement structure construction including soil improvement with lime stabilizing, drainage upgrade and vehicle crossovers. Ijoinedthe projectduring executingstage and bare major responsibilities of the project.I noticedlack of progress of the project as contractorwasbusy with several subdivisionprojectsand thus this small project was not taken seriously.It appearsthat the contractor used to deliver resourcesto projectwhen subdivision activities were less in demand. 19
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
I followed up contractor with thismatterthroughverbal and written communication andstressedtheimportance of acceleratingthe project. I managed to get the basic detail of their reverse work programme and develop the work programme as required. Then I pushed the contractor to meet the major mild stone of the work programme. The project was located in low elevation land. Therefore, drainage improvement was veryimportantelement of project.However, during the construction stage it was vulnerable to collect water in road stretch and damage the road pavement. Therefore, contractor was advised to minimise the gap between pavementlayerconstruction for avoiding exposure to flood and damage. Despitethe delayinproject, contractorwasable to complete the project with quality and revised time frame. Claim 2: From June 2008 to November 2009 I worked in South Sudan with United Nation Office for Project Service (UNOPS) for rural road rehabilitation project under European Union (EU) directed funding as a project engineer. My main responsibility was construction supervision and quality assurance/quality control (QA/QC) work of 110km Parasika-Yambio road rehabilitation project. The project Constructionwork wasundertaken by an international construction company, Kirinyaga Construction (K) Ltd (Nairobi, Kenya). I provided necessary advice to the National Site engineers and QA/QC technicians reporting to me, whilst organising regular meetings with my staff to discuss construction related matters including progress, quality, safety and environmental issues at the site. I advised them on potential measures to improve safety andtominimise impactsonenvironment during those meetings. I also updated the site Inspectors on project changes and latest site instructions. I regularly communicated with the Contractor's Site manager to discuss planning, programming and managing risks of the construction works. I used to conduct a short meeting every morning and regularlyattended contractor’s tool box meeting to discuss about the daily programme and resources allocation. I used this opportunity to discuss issues, including safety, Quality and environmental measures, with my team. As the project associated with massive earthmoving operation and cuttings across marshy lands and hills, it was very crucial to maintain adequate environmental protection measures throughout the site. I regularly checked the environmental protection measures against the Kirinyaga approved project environment management plans. There were many instances thatsome cuttingsections were not being provided with adequate side ditches and silt control ponds to minimise siltation and control erosion. I discussed these situations with 20
the Site Manager and arrangedto mitigatethe situationsfor complyingwith the approved plans. Moreover,when borrowarea operation was over, I ensured re-insisted the area. I ensuredthatbarrowareawereprovidedwithadequatebatterslope,andlesswater accumulation.Preventingwater stagnation was very important in the area to avoid mosquito breading which is a severe problem in the region. UNOPS project officereceived large numberof public complaints throughout this project. Most of the complaints were related to culverts, site drains, and barrow area management issues. I conducted initial investigations by myself or through my staff. I forwarded all public complaints, along with a short report on my findings, actions taken and recommendations to the project manager. Most of the issues were resolved on site, with the involvement of the Contractor. For example, once there was a community protest about an extensively damaged gravel road due to hulling of barrow area material. I immediately attended the location in question. It was evident that the public road had been heavily used by construction vehicles and the situation has worsened due to the rains overnight. I talked to the community representatives and agreed to provide a reasonable solution as soon as possible. I contacted and negotiated with the Site Manager to reinstate the condition of the road. He immediatelyagreedto repair the road and provided a quarry dust with blended hard material as an additional measure to protect road from further damages. My project manager requested to performed basic geotechnical investigation as a part of feasibility assessment for 264km Wau to Tambura road project while I wasengagedwith this project. Ministry of Infrastructure, South Sudan wanted this report to looking for possible funding of gravel improvement of this 264 km road stretch. It was very challenging to perform this task while taking responsibilities with ongoing project. This was scheduled to complete within3 months.First I acquired necessary resources including additional national technical staff and unskilled manpower. With the collaboration of other project staff, I lead the team for the investigation. I supervised, trained and performed with my team in first 50km by sampling the existing subgrade material every 2-5 km interval and locating barrow areas beside the roadcorridor. Then I closely supervised the material testing at UNOPS Yambio site office andensured thatproctor, CBR and Sieve analysis of these samplewas performed regularly. Moreover, I identified the sensitive part of road stretch using test result and topography of the location. I performed Dynamic Cone Penetration test (DCPT) at these locationsandanalysed these data with the direction of project manager. To meet the time line of theproject, I got special approval from my project manager to workonWeekends andfor 21
someadditional hourswithnational staff. The above actions taken by memade it possibleto meet the time line of report. EOC 11 : Judgement: Between November 2004toDecember 2007 I worked in the United Nation Office for Project Service (UNOPS) as a Regional Engineer for North East Region of Afghanistan. As a regional team leader of technical, logistical and financialmatter, I worked cooperatively with my regional and UNOPS head office team and with the other internal and external stake holders to deliver the road construction project successfullyon time. During this period, Iwas involved with Construction of Double Bituminous Surface Treatment (DBST) in Rustaq to Taloqan in North East Region in Afghanistan. Contractor could notmobilisethe machineries on time due to logistical challenges of the location. Therefore, when the constructionwork started, the Contractor had to significantly increase his labours and plants to catch up the lost progress due to initial delays. This increased the workload on Contractor's supervisory staff and also needed more planning and management of the resources to deliver thework efficiently and to maintain the quality. During these early stages, I have noted poor workmanship and non-compliantworkduring my field visits. Though Contractor performedrectification ofthose issues according to our direction, it was noted that the same non-compliant occurred again and again. I recognised that this was mainly due to the lack of experience and attention within the Contractor's site supervisors in roads and infrastructure works. I also noted deficiencies in form work and reinforcement fabrication for culverts during this time. At some instances, when pointed out by UNOPS Engineers, it appeared that the Contractor's site supervisors were reluctance to rectifysome of non-complying work, as rectification ofthatworkwas associated with additional costs. I identifiedthatthis situation should be corrected without any delay to avoid any negative impact on the progress of the works as well to deliver the worksbymaintaining quality and complying with construction drawings and specifications. I highlighted this issue in monthlyprogress meeting. The Contractor’s Project Manager agreed to deploy more experienced and competent supervisorsat workwithout further delay. Moreover, I acquired 10 student supervisors under Japanese government funded Ex-combated soldier training programme (Disarmament, Demobilization and Reintegration (DDR) as trainee construction supervisors to assistinsupervision of the project. Later contractor absorbedsome good performing trainees asitssupervisors. The proposedroad projectranthrough the irrigation land corrido.I notedthat some sectionshad challenges in diverting traffic due absence of alternative roots.The only option 22
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
was farming land beside the road corrido whichwassubjected to soft and wetcondition during the irrigation season. This was not reflected in contractor traffic management plan. I requested my national engineers to investigate the most challenging section of traffic diversion during the wet season. They did their assessment with the consultation of local farmers and irrigation department officers. I raised this issue during the progress meeting with contractor and requested to review their work programme giving prioritytothis sensitive section. Contractor revised the work programmed by allocating resources to sensitive section during the dry season. Myapproachwas successful and contractorwasable to perform the project without significant impact of traffic flow. Further,I witnessedthat contractorwasstruggling with cash flowatthe initialstages of project.His chiefEngineer leftthe project due to payment issue.Few heavy machineries demobilised from the project site without strong valid reasons. When I analysed the company profile of the contractor, it did not show strong performance or capacity. Contractor won the project due to lack of competition at the tendering stage due tochallenging location.I assumedthathis lack of initial capital would be a problem and it willaffectthe project progress at later stage. However,contractor establishedthe crusher plant at side.I also noted thathe has quoted good price for Aggregate Base Course (A.B.C) and 14mm and 10mm sealing layer. I requested contractor to operate crusher plantforlong hours to accelerate ABC and sealing aggregate production. Then I able made him significant payment as an advance under the “Material at Site” clause in the project contract. I made similar payment when his bituminous material arrived at the site too. This payment initiative helped to resolvemost of his problemsand projectperformedwell without significant cash flow problem at later stage. EoC 12: Advanced Engineering Knowledge Claim-01 From June 2008 to November 2009, I worked in South Sudan with United Nation Office for project Service (UNOPS) for rural road rehabilitation project under European Union (EU) directed funding as a project engineer. I was involved with 110 km Parasika- Yambio road rehabilitation project. Project consisted with gravel surfacing, more than 72 culvers and flood way, cover drained with in the major city centres. I took major responsibilities of project quality assurance/quality control (QA/QC) work due to my previous exposure to the field. Material testing laboratory performedtesting according to British Standard (BS). I reviewed tests procedures according to BS 1377 and ensuredthattechnicians follow the procedures according to specification. When I monitored 23
something was wrong, I discusseditwith technicians and corrected it. I wrote the important steps of testing methodology clearly, developed check list for the new technicians and asked them tofollows the steps. When there is a discrepancy or suspect about field compaction test using nuclear density meter methods, I always verified the result using sand replacement method. Because compaction ratio can be calculated using first principle andit does not involvecomplex instrumental or calibration errors in sand replacement method. Ministry of infrastructures sent 4 trainee engineers to the project. With other national engineers, national technicians involved in the project, I conducted a workshop for quality control testing as a capacity building of national workforce. Once, compressive strengthwhich was theresult of a critical culverthadfallen below the specification require criteria. As it was not complying with project specification, I discussedit withmy project manager to raise the non-compliant report. Then contractor requested to reconsider the decision and proposed to carry out rebound hammer test to re- assess thee strength. I reviewed specification for the testmethod ASTM C805 / C805M , rebound test and it was found rebound hammer test has limitation as the basis for acceptance or rejection of concrete Because it basicallyindicatesthe giving in-place strength and result also may vary according to moisture containand texture of test surface.Therefore,I proposed to obtain concrete core samples in accordance with test method C42/C42M to establish relationship by correlating rebound numbers measured on the structure with the measured strengths of cores taken from corresponding locations.However,it also indicated low strength of the concrete structure. So I confidently raised the non-confirmation report for the culver. Claim: 02 Between November 2004toDecember 2007, I worked in the United Nation Office for Project Service (UNOPS) as a Regional Engineer for North East Region of Afghanistan. I was involved with construction of 24.5 km Imam Sahib Connector road. Road corrido exposed to very high temperature during summer.Therefore,my programmed manager stressed the important of right mix ratio of asphalt to avoid deformation during hot weather condition. In fact this design is a project specification required document to USAID hold point in Inspection and Test Plan (ITP).Therefore,I discussed with UNOPS regional laboratory to develop and verify the right mix design to resist the local weather condition. I collected the necessary material and specification to perform the design. I have previously involved with concrete and asphalt mix design with the supervision of senior engineer during 24
the beginning of my career path with Engineering Laboratory Service (ELS). I followed the following steps to develop the mix design for denser grade asphalt for the Imam Sahib road with my laboratory team. 1.First of allI determined the physical properties of fine and course aggregate, such as size and gradation. 2.We select the 60/70 Penetration grade as a bituminous binder of the mix, which is commonly used in the region and comply with pavement temperature index chart. 3.Then I prepared several trial samples, each with different asphalt binder content, at 3.5,4.0,4.5 5.0, 5.5, and 6.0 percent asphalt by dry weight. 4.Then laboratory performed Marshall Test (ASTM D6927)for these samples to verified the Stability and flow. Air voids, and voids filled with asphalt binder were discovered with required tests and Thersitical maximum Dry Density. Then these results were plotted as below a)Binder content vs. density b)Binder content vs. Marshall Stability c)Binder content vs. flow d)Binder content vs. air voids e)Binder content vs. voids in mineral aggregates f)Binder content vs. voids filled with asphalt 5.Then I adopted bituminous content of air void content of 4 percent as the mix design ration for the production.It satisfiedthe specification criteria for other asphalt properties. We performed trial section with discovered mix ration and monitor the other desirable property of asphalt mix such as Workability, skid resistance. In long term wemonitor resistance to moisture induced damage, fatigue resistance of the surface. We constructed the pavement with discovered asphalt mix ratio andwerevery happy with the finishing of asphalt surface andexposureto hot weather during the 1 years defect liability period. EoC 13:Local knowledge Claim 01 From September 2018, I am working with Mildura Rural City Council (MRCC) as a project Delivery Engineer. I involved different subproject including tendering and project implementation.MRCCextensivelyinvolvedwithdrainageupgradeandconstruction activities. During the first few months of this employment, I acquired the knowledgethat was 25
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
requiredfordrainage design review including the design guidelines and specificationswhich suitsto local conditions.I was involved indesigned review of several storm water project at site. One of the sub projectI was involved in isMurrayville drainage project. Initially it was designed by Aurecon 6 months back. I visited the site with MRCC design officers to review the project design before scheduling the tendering plan. I notedthatmost drainage and pits were affected with siltation, sediment issues. Moreover, stability andusabilityof one of the heritage buildingwas also challengedby the upstream water flow.I realised that many side roads in hilly terrain need RC side drains, energy dissipation pits, and cascaded drains and scour protection plinth walls to protect drains from erosion and scouring. Further I discussed and acquired information on local storm water flowwith consultation fromthe community and local organisations. The initial design does not possess strong storm water flow of the area. It appears initial design has been done without proper site assessment. After gathering this information we conducted designed review meeting at MRCC office withmy presentmanager and design coordinator to finalize the requirements.With the based facts found at site,it was agreed to redesign the project. Claim 02 Between March 1999toMarch 2001, I workedatthe Engineering Laboratory Services (ELS) as a laboratory engineer. Testing of Civil Engineering material, prepared test reports and Carried out the field quality assurance and quality control tests (QA/QC) accordingtoBritishStandard(BS),AmericanAssociationofStateHighwayand Transportation Officials (AASTHO) and Sri Lanka Standard were my main responsibilities. After one year of engagement in main laboratory, I was assigned as the team leader of Queen Elizabeth Quay extension project in Colombo harbour as a team leader of field testing laboratory. The client was P&O Australia and consultant was Bovis Lendlease. The project was delivered according to Australian Standard. ELS worked as a Consultant appointed independent testing laboratory to the main Contractor, Hyundai Engineering. Project specification was made overseas and some time it challenging the requirement with the local availability of material and their properties. Contractor requested testing of several sample of rocks for Loss Angelis Abrasion Value (LAAV) for use as a rock revetment in breakwater extension. Most of the samplesdid notachieved the required criteria of the specification. I used my experience with ELS main laboratory to locate the right material.We collected the sample from potential quarry site which is 70 km away from project side. It was logistically very challenging to hulling massive quantity of material from 26
such a distance but material show highly desirable property for the intended purpose with high LAAV, good Alkalise resistance and less weathered particles. Moreover,initialdesignforcarparkareawaswitharound0.5-.75mmsoil embankmentfilling.Mostofthesoilpropertiesofthebarrowareacompliedwith specification requirement, but plasticity properties (Liquide limit and plasticity index) of soil sample did not show desirable properties consistently.Therefore,I proposed to modify the local available material by blend with sand to achieve the required property. Ididsome trial andevaluated desirablerate of blending of two material. It was more economical and efficient approach with nearby barrow pits. However, later consultant amend the design to do embankment fill with Sea sand. Because theyhadmobilisedrequiredvessels to mobilise the coarse sand from deep sea for container wharf extension. Container Wharf was design with paving of interlocking blocks.Initial plan was mobilisedthepavingblocksfromDubai.Theprojectspecificationspecifiedhigh compressive strength for the blocks. Because of logistical and pricing concern, contractor explored the possibility to acquire these paving blocks locally. I checked Sri Lanka Standard (SLS) for interlocking block which is well below the required merging. Moreover, according to my experience QC/QA was very rear with most local manufactures. I collected required literature for mix design and performed the mix design in ELS main laboratory with the collaboration of senior laboratory engineer. We discovered the right mix ratio for interlock blocks which achieve characteristic strength of 28 days specified in specification. This approach was approved by the project consultant. Then weperformed intensive production of these blocks in ELS precast concrete yard to match the time line of project. I frequently tested material and sampletoensure the quality of the sample as required. This local initiative helped to cut down the overseas block purchasing by significant amount. Eoc 14 : Problem Analysis From June 2008 to November 2008 I worked in South Sudan with United Nation Office for project Service (UNOPS) for rural road rehabilitation project under European Union (EU) directed funding as a project engineer. My main responsibility was construction supervision and quality assurance/quality control (QA/QC) work of 110km Parasika-Yambio road rehabilitation project. Project consistofrehabilitation, reconstructionof 72 culverts, Concrete side drain in city centres, gravel surfacing with including 2-4 m widening of more than 60% of the road and gravel surfacing. As the Stage 2 of the project, It was planned to bituminous sealing of this road. Therefore, EU was very interesting about the quality of stage 1 construction. Ijoinedthe project during executive stage. UNOPS executed this project as a 27
consultant and executing agency with international contractor. The project location was near the border of Democratic Republic of Congo and logistically many challenges for project execution. During my first progress meeting, Inoticedthat the project hadbeen significantly delayedmainly due to logisticalissuesand impact of QA/QC. UNOPS Project manager requested me to review the QA/QC procedures and improve the system. I discussed this matter with other project engineers, UNOPS laboratory technicians. Then I visited the material testing laboratory and review the test methodologies and equipment. Inoticed that most of the equipment need to be re-calibrated such as concrete compression machine, Moisture meters, and compaction mound and density equipment.Further safe handling or storing of nuclear density meter was not observed. Due to high demand of soil testing, quality of testingwasat challenging stage. Documenting, test reports filling system, and update of Inspection and Test Plane (ITP) was at poor stage too. Further unreliable power supply to the laboratory has been significantly affected the test progress. Community interruption during the barrow area operationwasalso noted. I discussed this issues with Contractor’s project manager and QA/QC coordinator to improve the system. Contractor was requested to immediately deploy at least two more laboratory technicians. Due to lack of 24hrs power supply moisture testing of laboratory was significantlyaffected.Duetothisdelayofthetestprogresswascausedespecially compaction test reports.I stressed the important of reliable power supply to the laboratory. He promised to fulfil theserequirementswithin two weeks. Further I observed discrepancy between compaction test results of nuclear density meter and sand replacement methods. Until wegot requiredtraining and calibration, I paused the use of Nuclear density meterbecause I wasmore confident with the accuracy with the sand replacement method. I trained UNOPS and Contractors technicians to performed test using sand replacement methods. Iattendednecessarycalibration and training for sand replacement. To overcome the time consuming challenge with Sand replacement method, Irequested additionalpeople to laboratory to train and performing the excavation of test holes and proctor compaction tests. Due to the non-availability of calibration services in locally, I took necessary arrangement to mobilise thecalibration service fromNairobi, Kenya. Further UNOPS and contractor laboratory technicians were trained for safe handling of nuclear density meter. Even the materialcamefrom same barrow areas, I requested toperformproctor compaction test regularly to avoid material variation at different location at site and material segregation. 28
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Barrow area supervisor wasadvisedto ensure proper mixing of material before transporting to the site. Moreover,I reviewed the test reports format and ensure all the tests are performed under supervision of UNOPS. These test reports were properly managed with hard folders and Excel data based. ITPs were updated and ensure necessary clearance and approval can be traced before proceeding to next layer of embankment. This new initiated significantly improved the quality of material testing and compaction test reports. After getting necessary training and calibration laboratory technician more confidently and safely handle the nuclear density meter.Discrepancy between Sand replacement method and nuclear density testing become marginalised and then I adopted nuclear density meter as a main test method for compaction testing. Ifollowedseveral strategies to overcome the community interference during the barrow area operation. First we carefully assess the new barrow area avoiding any berried site or sensitive community areas. Secondly we build up good relationship among the community membersnearby barrowarea. Contractor wasadvisedto give prioritytothem during the labour recruitment. These initiatives enhance the smooth barrow area operation throughout the project duration. ECO 15 Creativity & Innovation/Advanced Operation/Predictable Operation Claim 01: Between November 2004toDecember 2007 I worked in the United Nation Office for Project Service (UNOPS) as a Regional Engineer for North East Region of Afghanistan. I lead the regional UNOPS team with the collaboration of UNOPS head office team and with the other internal and external stake holders to deliver the regional road programme successfully in a timely manner. During this period, I involvedin theConstruction of Double Bituminous Surface Treatment (DBST) surfacing of Taleqan toward Rustaq road (16km) in Thahar Province. Contractor faced problem to locate a right base course material in the area. Locally available barrow material mostly silty and gave bellow the required CBR value of 80% in the specification. They discovered hard material around 70km from the Taleqan District center. Contractordid not quotehealthyprice to mobilise material from such a distance. The project venue is also logistically big challenge.I analysed the problem and gave an option to the contractor. I proposed to blend the local available material with hard quarry material to minimise the transport cost. To achieve the required mix ratio, we performed several blending and first test the material for CBR followed by partial size distribution test. We 29
discovered the right blending ratio for the improvement of local available material with imported hard material. I advised contractor to start subgrade and base-course operation near Taleqan to minimise the logistical/transport problem of hulling base-course material. We frequently tested the base-course material and changed the mix ratio as required. This approach resolved severe logistical problem of the project. Ihadnoted bleeding of DBST surface of Kuduz –Taleqan road whichwasbuilt 2 years ago by an international contractor. As a result skid resistancewasreduced, deformation of bituminous pavement under traffic loadwaswitnessed. I investigated this problem to avoid any negative impact on this aspect to our project. I found the road had been constructed with specified binder rates in the Ministry of Public work (MOPW) specification. However excessive temperature of the region during the summer caused binder material moved to surface. When I checked the specification, binder coat/ Tack coat spray rate was 0.25 to 0.4 litre per square meter.Therefore,I investigated to move this rate to closer the lower margin. However minimum amount of binder is essential to prevent the aggregates from being pulled out by the abrasive actions of moving vehicles on the carriageway. Moreover, I paid my attention tosufficient amount of binder content so that the aggregates are fully coated with bitumen and the voids within the bituminous material are sealed up to achieve sufficient strength of sealing materials.Therefore,we carefully moved backward to the spay rate by performing several trial section with the collaboration with my contractor. We exposed the spry rate closer to 0.3 litter per meter square.We carefully maintain this rate trough out the project by frequently checked the spray rate using tray test method and constructing several trial sections to verify the changes. Claim 02 Between March1999toMarch 2001, I workedatthe Engineering Laboratory Services (ELS) as a laboratory engineer. After one year of engagement in main laboratory, I was assigned as the in charge of Queen Elizabeth Quay extension project in Colombo harbour as a team leader of field testing laboratory. The client was P&O Australia and consultant was Bovis Lendlease. The project was delivered according to Australian Standard. ELS worked as a Consultant appointed independent testing laboratory to the main Contractor, Hyundai Engineering. The project consisted with upgrading and extending of 550 m Container Wharf which wasdesigned with paving of interlocking blocks.Initial plan was mobilisedbythe paving blocks from Dubai. The project specification specified high compressive strength for the paving blocks. Because of logistical and pricing concern, contractor explored the possibility 30
to acquire these paving blocks locally. Contractor collected several samples of interlocking blocks locally. But these samplesdidnotachievethe required criteria of specification. Then Iproposed Hyundaisenior engineer to performed mix design for interlocking blocks and manufacture locally to required strength of the specification in ELS precast concrete yard. I collectedrequired literature for mix design and performed the mix design in ELS main laboratory with the collaboration of senior laboratory engineer. We discovered the right mix ratio for interlock blocks which achieve characteristic strength of 28days specified in specification. This approach was approved by the project consultant. Thenwe didthe intensive production of these blocks in ELS precast concrete yard to match the time line of project. I frequently tested material and sampletoensure the quality of the sample as required. This local initiative helped to cut down the overseas block purchasing by significant amount. EoC 16: Evaluation Claim 01: From June to September-2018, I worked as a development engineer with Shire of Windham and East Kimberly (SWEK). The councilhad eagerto acquire on state and federal government directed funding due to low rate income and huge road network of the area. Engineering manager requested me to apply for State government funded black spot program 2019/20 expecting some funding for upgrade few intersections of Kununurra city limits. As the funding distributed priority basis of Western Australia wide, I ensured rigorous analysis of most critical locations in the state and local road network to apply for the funding. I followed the following evaluation method to apply for blackspot funding for SWEK region under the supervision of Engineering Manager. I evaluated traffic data of major intersection and sensitive location such as total number of crashes, casualties, and value of property damage. I accessed to “main road Western Australia”database to gather this information. Then I identified three critical intersection need to improve under blackspot programme attached to Weaber plain Road, Erythina, Ironwood, Leichhardt St. Statically dataof these 3 locations of last 5 years was compliedwith the blackspot programme evaluation criteria. I gathered information and analyse natures of concern of these intersections such as signage and Line marking, pedestrian crossing movement, vision at night time and traffic flow. I used present and historic traffic count data of SWEK asset management department for the analysis. 31
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
I identifiedthe proposed treatment for these locations such as improved of signage and line marking, school children warning signs, improve intersection lighting, installation of traffic island, pam rams, erecting of handrails with the cost estimation of each locations. I registered with “mainroad Western Australia” and gained access to Western Australia Crash Analysis Reporting System (CARS). So Ievaluatedeach intersection with Stick diagrams, CARS crash factor matrix, Benefit Cost Ratio (BCR), Net Present Value (NPV) as per calculation guide line in the system. I managed to lodge 3 applications for potential funding for three different locations under State government funding by providing strong data and conversing information. Claim 02 Between November 2004toDecember 2007 I worked in the United Nation Office for Project Service (UNOPS) as a Regional Engineer for North East Region of Afghanistan. Badakshan province is one of the remote province in my region, shearing boarders with China and Tajikistan. United State Government had strong commitment to link Fayzabath, provincial capital of Badakshan province to Kesham which is theclosestlocation to national transport network. Because remote Fayzabath district was logistically big challenge to access by road due to vales, mountain, waterways and security. It was heavily poppy cultivated area due to isolation. During the winder Fayzabath was very hard to access by existing very poor road network in the province. United States Agency for International Development (USAID) approached UNOPS to evaluate the road construction option to Faizabath. With the coordination with UNOPS head office in Kabul I conducted this assessment evaluating the possible roots to Faizabath. Strategically I identified the following two options to connect Fayzabath to Kesham by road, a)Option 1 Build road parallel to Kohcha River 98km b)Option 2 Build road Via Wahadat Distric center 88km The economic costs and benefits for each options were not quantified. Instead, a decision matrix was used to qualitatively evaluate the options against their economic (e.g. private and commercial travel time savings and transport efficiency), social (e.g. safety benefits and amenity improvements) and environmental (e.g. reductions in emissions, dust) impacts. I identifiedthe following key benefits of the preferred option over alternatives: Construction Cost Improved safety and efficiency Reduced travel time and freight cost Local economic benefits 32
Even option 1 waslonger, the recommended option was option 1. This road corrido covered significantly more numbers of settlement and cater service for more economic activity. On the other hand option 2 associated with significant amount of road structures, such as long spanbridges,Earthretainingstructures,rockexcavationandfloodways.Moreover, sustainability of option 2was also challengingdue to heavy water flow and geographical gradient of the area. Regional USAID representative highly commended my evaluation report. However later USAID selectedLouis Berger Group to execute this option as the complex nature of road structure with in road corrido. 33