logo

Plant Purchase, Installation and Replacement

   

Added on  2023-06-12

9 Pages2462 Words478 Views
Finance
 | 
 | 
 | 
Assignment 2: Plant Purchase, Installation and replacement
Name of the Student
Name of the University
Plant Purchase, Installation and Replacement_1

Table of Contents
Answer to question 1:.............................................................................................................. 3
Answer to question 2:.............................................................................................................. 4
Answer to question 3:.............................................................................................................. 5
Answer to question 4:.............................................................................................................. 6
Answer to question 5:.............................................................................................................. 6
Introduction to costing.........................................................................................................6
Gaps Identified in life cycle costing......................................................................................6
Improving cost benefit balance............................................................................................7
Reference List.......................................................................................................................9
Plant Purchase, Installation and Replacement_2

Answer to question 1:
The concept of annual worth (AW) is used in capital budgeting decision for comparing
alternatives with dissimilar lives under LCM assumptions. The AW value has to be calculated
for only one life cycle.
In case of comparison of several option, the highest AW will be chosen for most feasible
alternative. This is calculated as the difference between capital recovery and annual cost for
a given rate of return.
Degree A B C D
First Cost $10,000.00 $14,000.00 $20,000.00 $30,000.00
Annual Labour Cost $9,000.00 $7,500.00 $ 5,000.00 $3,000.00
Annual Power and
Maintenance Cost $500.00 $800.00 $1,000.00 $1,500.00
Salvage Value $500.00 $700.00 $1,000.00 $1,500.00
(A/P,i%,n) 0.22960738 0.22960738 0.22960738 0.22960738
(A/F,i%,n) 0.12960738 0.12960738 0.12960738 0.12960738
Annual Worth -$11,731.27 -$11,423.78 -$10,462.54
-
$11,193.81
From the above table it has seen that AW for Degree C is highest compare to other
methods. Hence, as per Annual Worth method, Degree C should be considered here.
Again, the concept of Present Worth (PW) is utilised further to evaluate the viability of any
project considering the life span as well as discount factor. It converts all the earnings to
present value. According to PW technique, the project will be selected if it has maximum
PW.
Degree A B C D
First Cost
$
10,000.00
$
14,000.00
$
20,000.00
$
30,000.00
Annual Labour Cost
$
9,000.00
$
7,500.00
$
5,000.00
$
3,000.00
Annual Power and
Maintenance Cost
$
500.00
$
800.00
$
1,000.00
$
1,500.00
Salvage Value
$
500.00
$
700.00
$
1,000.00
$
1,500.00
(P/A,i%,n) 4.35526069 4.355260699 4.35526069 4.35526069
Plant Purchase, Installation and Replacement_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Plant purchase, Installation and replacement PDF
|15
|3016
|23

Plant Purchase, Installation and Replacement
|16
|3540
|204

Plant Purchase Installation and Replace
|14
|3394
|24

Answer to Question 1 2 5 Answer to Question 4 8 Answer to Question 4 8 Answer to Question 5 8 Answer to Question 4 8 Answer to Question 5 8 Answer to Question 4 8 Answer to Question 5 8 Answer to Ques
|14
|3179
|474