PPMP20008 Lessons Learnt Assignment

This assignment requires students to reflect on their participation and experience in the unit, identify lessons learnt, and consider actions to address those lessons.

7 Pages1930 Words343 Views
   

Added on  2022-10-01

About This Document

This assignment entails reflection on key lessons like conflict, multiple tasks, etc.in project, strategies to improve the existing situations and through implementation of strategy. Lessons learnt or lessons learned can be defines as the experiences gained through the course of project. These lessons learn should be compiled properly and should be pro- actively applied in the future projects.

PPMP20008 Lessons Learnt Assignment

This assignment requires students to reflect on their participation and experience in the unit, identify lessons learnt, and consider actions to address those lessons.

   Added on 2022-10-01

ShareRelated Documents
PMMP 20008 – Initiating and Planning Projects Assignment 3
PPMP20008
2019 TERM 2 ASS_3
LESSONS LEARNT
Name: Insert full name
Student Number Insert student number
Campus: Insert campus or distance
Tutor: Insert tutor name
Tutorial number: Insert tutorial number
tmpet5en22b3684211_303445877_1096314.docx4 Page 1 / 7
PPMP20008 Lessons Learnt Assignment_1
PMMP 20008 – Initiating and Planning Projects Assignment 3
1. INTRODUCTION
Reflective practice is the art of learning through various self-experiences and self-analysis to
ensure continuous learning over the course of life (Kotnour, 2000). The various lessons learnt
in process is to gain insights through reflection over the project completion and apply these
lessons in future projects. This assignment entails reflection on key lessons like conflict,
multiple tasks, etc.in project, strategies to improve the existing situations and through
implementation of strategy. (Thamhain, 2004)
2 LESSONS LEARNT: FRAMEWORK
2.1 Lessons learnt framework explained
One of the most widely used lessons learnt framework is double loop learning. The double loop
learning process is a powerful framework as it operates at both project level and organization
level (Schindler & Eppler, 2003)
Given that the fact that capturing lessons learnt is critical in every project, double loop learning
framework captures the major lessons learnt and the situation, value or parameters against
which the lesson was learnt during the course of the project. (Frank 2014) The framework es-
tablishes the importance of the parameters under which a particular lesson was learnt as the ab-
sence of the same can lead to poor decision making and failure of the lesson capturing process.
2.2 Lessons learnt process: How I planned to gather, and document lessons learnt
STEPS WHEN WHO HOW
(i) Identify The lessons learnt
during the course of
the project will be
identified upon
successful project
completion
The lesson learnt
framework will be
developed by
engaging with the
various project team
members
I planned to identify
the major lessons by
reviewing the
strengthens, issues
faced, hurdles, etc.
during the course of
project
(ii) Document The documentation
will be kicked off
upon successful
identification of
lesson learnt, the
same shall be
documented
The lessons learnt
framework will be
documented by
communicating with
the project lead and
members
I intend to prepare a
10-pager report
capturing the
situations and lessons
(iii) Analyse After successful
documentation of the
lessons learnt, the
analysis of the
lessons learnt will be
The document
analysis will be
undertaken by project
lead and team
members
In order to analyse
the document,
different situational
parameters analysis
will be performed
tmpet5en22b3684211_303445877_1096314.docx4 Page 2 / 7
PPMP20008 Lessons Learnt Assignment_2
PMMP 20008 – Initiating and Planning Projects Assignment 3
initiated
(iv) Store Upon successful
signing by project
team lead, the lessons
learnt document will
be stored
The project lead will
store the data.
The data will be
stores in both hard
and soft formats
(v) Retrieve When starting a new
project of similar
nature or similar
category, I would
retrieve the document
In order to retrieve
the data, I would
contact the project
lead
I will prefer
retrieving the
document in soft
copy format
2.3 Lessons learnt process: What actually happened?
STEPS WHEN WHO HOW
(i) Identify In reality, lessons
learnt from the
project was identified
months after project
completion
The lessons learnt
were identified along
with my project team
members
In order to identify
the lessons, various
project situations
were reviewed
(ii) Document The lessons learnt
was be documented
after successful
identification
The document was be
prepared along with
my project team
members
The document was be
prepared in a report
format covering all
details about the
project
(iii) Analyse After documentation
of all lessons learnt,
analysis was be
undertaken.
The analysis of
lessons learnt was be
undertaken by project
team and key
management
personnel
The analysis of
lessons learnt
document was done
through review of the
document along with
project
(iv) Store Upon successful
signing off the
document, the lesson
learnt document was
stored
The document was
stored by the Team
lead
The document was
stored in soft copy
format along with
hard copy
(v) Retrieve I plan to retrieve the
document when
pursuing new projects
In order to retrieve
this document, one
needs to contact Team
lead
The lesson learnt
document will be
retrieved only in the
soft Copy format
tmpet5en22b3684211_303445877_1096314.docx4 Page 3 / 7
PPMP20008 Lessons Learnt Assignment_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Lessons Learnt in Project Management
|8
|2168
|80

Lessons Learnt Report for Project Management
|7
|1867
|311

A Template for Term 2 ass_3 Lessons Learned
|7
|1865
|415

Lessons Learnt in PPMP20008
|5
|1221
|359

Lessons Learnt in Project Management: Frameworks and Improvement Strategies
|7
|1846
|262

PMP20008-Lessons Learned in Project Planning and Initiation
|7
|1577
|164