PROJECTSTATUSANDCONTROLREPORT NAMEOFPROJECT 2GANTTCHART WBS # Task & Subtask12345678910 1A———— 1.1A1— 1.2A2— 1.3A3— 2B———— 3C——————— — 4D——————————— — 4.1D1————— 4.2D2————— — 5E————— 6F—— 7G— 8H— 3VARIANCEANALYSIS(COSTINTHOUSANDS) Task & Subtask Milestone StatusPVEVAC Variance % ScheduleCost ACompleted10010010000 A1Completed25252500 A2Completed50505000 A3Completed25252500 BCompleted5050550-5 CCompleted505040010 DIn progress7040110-42.86-175 D1Completed3030500-66.67 D2In progress401060-75-500 ENot started9000-1000 FNot started4000-1000 GNot started5000-1000 HNot started500-1000 Task Totals455240305-47.25-56.25 4ESTIMATEATCOMPLETION(EAC) EAC = $539,933.33 The estimated cost of completing the Barwon health project amounts to $539,933.33. This cost estimation is based on the allocated planned value to various activities on weekly basis. The total estimated cost of project is higher than the planned cost of project completion. ENTERYOURNAMEWITHSTUDENTIDPAGE2
PROJECTSTATUSANDCONTROLREPORT NAMEOFPROJECT 5COSTSUMMARY The impact of cost on the project will be that the project will fail to achieve its purpose and earn value for stakeholders of the project. The higher risks having adverse potential impact on the project result in increase in costs of the project. There are various project control techniques such as project crashing, project rationing etc., which can be used to reduce the overall costs of the project. Also the risk management strategies are used to mitigate the impact of risks on the project resulting in non-occurrence of additional costs the estimated cost of Barwon project are higher than the planned costs of completing the project. The reason for this is the impact of risk factors on the project. 6S CURVE The S curve shows that the planned value, earned value as well as actual costs of the project are in alignment and all these values move in the same direction. This means that there is no cost differences involved in variations in project completion. The project is not likely to result higher costs to a large extent as compared to the planned costs. 7FORECASTCOMPLETIONDATE Forecast completion date = End of week 11 On the basis of he earned value of the project and actual costs of the project till the present date of partial completion, it can be forecasted that the project will be completed within 11 weeks out of which 6 weeks have been completed and the remaining project will take 5 weeks to complete. ENTERYOURNAMEWITHSTUDENTIDPAGE3
PROJECTSTATUSANDCONTROLREPORT NAMEOFPROJECT 8MILESTONEREPORT Milestone Task Scheduled Completion Projected Completion Actual CompletionIssues AWeek 2Week 2Week 2 BWeek 4Week 4Week 4 CWeek 5Week 5Week 5 DWeek 7Week 7Week 7 EWeek 8Week 8- FWeek 8Week 9-The delay in this activity of the project is the poor data quality due to which the software was not customised to be compatible with the infrastructure. GWeek 9Week 10-The delay in this activity is due to the inefficiency of the project staff to co-ordinate and organise the project activities. HWeek 10Week 11-The issues in this activity arose due to delay in previous activities. 9EVENTREPORT Current ProblemPotential ImpactCorrective Action The poor quality of the data used in the designing and development of the software requirement plan. Improper designing of software The quality of the input in the project specification document shall be improved The lack of technical skills of the employees Ineffective implementation of project Effective training of employees in accordance with the project requirements Inefficient project management Project delayEstablish co-ordination among the project staff to ensure proper implementation of each activity (Kerzner & Kerzner, 2013) ENTERYOURNAMEWITHSTUDENTIDPAGE4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PROJECTSTATUSANDCONTROLREPORT NAMEOFPROJECT Part B Project Controls Task: Provide a description of how the project will be controlled including its event driven and time driven controllable categories and configuration procedural outputs for each item categorised. The control of project is very essential for ensuring the timely and proper implementation of the project to achieve the project activities (Nasir & Sahibuddin, 2011). There are various control techniques and procedures which can be used to monitor and control the performance of the project and its schedule. The various time-driven controls and event driven controls for the controllable categories of the project and configuration procedural outputs are described as follows: Event driven controls The events in relation to the project include arranging for the procurement of resources for the project, designing the process and systems for project infrastructure through coding and configuration, recording the project status and operations, maintain a daily log of the project activities and use of resources and assessing and dealing with the exceptional and uncertain project activities. In order to monitor these activities and implement controls, the various techniques used include preparation of Project management plan, schedule baseline, cost baseline, defining reporting methods and preparing risk assessment and mitigation plan. The meetings between project stakeholders, conducting technical performance review by the manager and performing risk assessments are the activities used to monitor the events. The work performance reports are submitted to control the performance of the project. Time driven controls These are the control procedures which relate to those factors which result in the extension of the duration of the project leading to the delay of the total project completion. The documents used for monitoring the schedule of the project include the cost baseline, work performance data, monthly progress reports etc. The tools ENTERYOURNAMEWITHSTUDENTIDPAGE5
PROJECTSTATUSANDCONTROLREPORT NAMEOFPROJECT used for the implementation of time driven controls within the project include the variance analysis, trend analysis, EV reports, rescheduling software tools, project crashing, work breakdown structure, etc. The baseline updates, change request updates, EVM reports and forecasts can be used as the methods for racking the performance and schedule of the project. The configuration procedural outputs in relation to the project include mainly five core activities such as planning, identification, controlling, status reporting and verification and audit of risks (Turner & Zolin, 2012). The configuration of the Barwon health project requires the designing and development of infrastructure of health alliance set-up. In this way the activities of configuration procedures can be used for implementing the time driven and event driven controls in the project control process for each of the controllable categories. ENTERYOURNAMEWITHSTUDENTIDPAGE6
PROJECTSTATUSANDCONTROLREPORT NAMEOFPROJECT REFERENCES Turner, R. and Zolin, R., 2012. Forecasting success on large projects: developing reliable scales to predict multiple perspectives by multiple stakeholders over multiple time frames. Project Management Journal,43(5), pp.87-99. Nasir, M.H.N. and Sahibuddin, S., 2011. Critical success factors for software projects: A comparative study.Scientific research and essays,6(10), pp.2174-2186. Kerzner, H. and Kerzner, H.R., 2013.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Taylor, H., Artman, E. and Woelfer, J.P., 2012. Information technology project risk management: bridging the gap between research and practice.Journal of Information Technology,27(1), pp.17-34. Teller, J., Kock, A. and Gemünden, H.G., 2014. Risk management in project portfolios is more than managing project risks: A contingency perspective on risk management.Project Management Journal,45(4), pp.67-80. Zhou, X. and Zong, Z., ZTE Corp, 2015.Method for reselecting bearer binding and event report function. U.S. Patent 8,943,165. ENTERYOURNAMEWITHSTUDENTIDPAGE7