Prickle Hill Produce Food Ordering Application Development
VerifiedAdded on  2023/01/18
|5
|1257
|56
AI Summary
This document discusses the development of a food ordering application for Prickle Hill Produce. It includes a Gantt chart and a work breakdown structure for the project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT
Prickle Hill Produce Food Ordering Application Development
Name of the Student
Name of the University
Author’s note
Prickle Hill Produce Food Ordering Application Development
Name of the Student
Name of the University
Author’s note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT
Table of Contents
1. The Gantt chart............................................................................................................................2
2. The Work Breakdown Structure for the Project..........................................................................3
Bibliography....................................................................................................................................4
Table of Contents
1. The Gantt chart............................................................................................................................2
2. The Work Breakdown Structure for the Project..........................................................................3
Bibliography....................................................................................................................................4
2PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT
1. The Gantt chart
ID Outline
Number
Task
Mode
Task Name Duration Start Finish Predecessors
0 0 Project Work Out
Plan
52 days Wed
10-04-19
Thu
20-06-19
1 1 Start of the Project 1 day Wed 10-04-19Wed 10-04-19
2 2 Requirements
Gathering Phase
11 days Thu
11-04-19
Thu
25-04-19
3 2.1 Having a meeting
with classmates
4 days Thu
11-04-19
Tue
16-04-19
1
4 2.2 Gathering
requirements
over ideas for a
project
5 days Wed
17-04-19
Tue
23-04-19
3
5 2.3 Understanding of
the case study
2 days Wed
24-04-19
Thu
25-04-19
4
6 2.4 Completion of
the phase
0 days Thu
25-04-19
Thu
25-04-19
5
7 3 Defining the
project plan
16 days Fri 26-04-19 Fri 17-05-19
8 3.1 Managing the
project team
(classmates)
5 days Fri 26-04-19 Thu
02-05-19
6
9 3.2 Making
communications
about project
idea brief
2 days Fri 03-05-19 Mon
06-05-19
8
10 3.3 Documenting the
project plan
9 days Tue
07-05-19
Fri 17-05-19 9
11 3.4 Completion of
the phase
0 days Fri 17-05-19 Fri 17-05-19 10
12 4 Designing of the
Project Plan
3 days Mon
20-05-19
Wed
22-05-19
13 4.1 Defining the
scope of the
project
1 day Mon
20-05-19
Mon
20-05-19
11
14 4.2 Understanding
the problem
statement
1 day Tue
21-05-19
Tue
21-05-19
13
15 4.3 Defining
strategies of
mitigating the
problems
1 day Tue
21-05-19
Tue
21-05-19
13
16 4.4 Defining the
need of the
Information
System as per
the case study
1 day Wed
22-05-19
Wed
22-05-19
15
17 4.5 Completion of
the phase
0 days Wed
22-05-19
Wed
22-05-19
14,16
18 5 Focusing over
Requirements over
the Information
System
13 days Thu
23-05-19
Mon
10-06-19
19 5.1 Gathering
requirements of
the design for
the Information
System
2 days Thu
23-05-19
Fri 24-05-19 17
20 5.2 Documenting the
planning a
narrative/story
board
3 days Mon
27-05-19
Wed
29-05-19
19
21 5.3 Defining
specification of
the Information
System
1 day Thu
30-05-19
Thu
30-05-19
20
22 5.4 Designing a use
case for the
proposed system
5 days Fri 31-05-19 Thu
06-06-19
21
23 5.5 Designing a
logical diagram
of the entire
process
2 days Fri 31-05-19 Mon
03-06-19
21
24 5.6 Focusing over
the data
structure and
drawing of an
ERD Diagram
5 days Fri 31-05-19 Thu
06-06-19
21
25 5.7 Designing a
mockup diagram
for the interface
for the proposed
system
3 days Fri 31-05-19 Tue
04-06-19
21
26 5.8 Suggesting the
architecture of
the entire
system
2 days Fri 07-06-19 Mon
10-06-19
22,23,24,25
27 5.9 Completion of
the phase
0 days Mon
10-06-19
Mon
10-06-19
26
28 6 Defining of Lessons
and further
progress of work
8 days Tue
11-06-19
Thu
20-06-19
29 6.1 Review over the
designed project
plan
2 days Tue
11-06-19
Wed
12-06-19
27
30 6.2 Making
corrections if
necessary
3 days Thu
13-06-19
Mon
17-06-19
29
31 6.3 Designing of a
Presentation that
would be
presented to the
class
2 days Tue
18-06-19
Wed
19-06-19
30
32 6.4 Making a speech
for the report
1 day Thu
20-06-19
Thu
20-06-19
31
33 6.5 Completion of
the phase
0 days Thu
20-06-19
Thu
20-06-19
32
34 7 End Project 0 days Thu
20-06-19
Thu
20-06-19
33
25-04
17-05
22-05
10-06
20-06
20-06
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
08 Apr '19 15 Apr '19 22 Apr '19 29 Apr '19 06 May '19 13 May '19 20 May '19 27 May '19 03 J un '19 10 J un '19 17 J un '19
(Fig 1: The Gantt chart for the Project)
(Source: Created by author)
1. The Gantt chart
ID Outline
Number
Task
Mode
Task Name Duration Start Finish Predecessors
0 0 Project Work Out
Plan
52 days Wed
10-04-19
Thu
20-06-19
1 1 Start of the Project 1 day Wed 10-04-19Wed 10-04-19
2 2 Requirements
Gathering Phase
11 days Thu
11-04-19
Thu
25-04-19
3 2.1 Having a meeting
with classmates
4 days Thu
11-04-19
Tue
16-04-19
1
4 2.2 Gathering
requirements
over ideas for a
project
5 days Wed
17-04-19
Tue
23-04-19
3
5 2.3 Understanding of
the case study
2 days Wed
24-04-19
Thu
25-04-19
4
6 2.4 Completion of
the phase
0 days Thu
25-04-19
Thu
25-04-19
5
7 3 Defining the
project plan
16 days Fri 26-04-19 Fri 17-05-19
8 3.1 Managing the
project team
(classmates)
5 days Fri 26-04-19 Thu
02-05-19
6
9 3.2 Making
communications
about project
idea brief
2 days Fri 03-05-19 Mon
06-05-19
8
10 3.3 Documenting the
project plan
9 days Tue
07-05-19
Fri 17-05-19 9
11 3.4 Completion of
the phase
0 days Fri 17-05-19 Fri 17-05-19 10
12 4 Designing of the
Project Plan
3 days Mon
20-05-19
Wed
22-05-19
13 4.1 Defining the
scope of the
project
1 day Mon
20-05-19
Mon
20-05-19
11
14 4.2 Understanding
the problem
statement
1 day Tue
21-05-19
Tue
21-05-19
13
15 4.3 Defining
strategies of
mitigating the
problems
1 day Tue
21-05-19
Tue
21-05-19
13
16 4.4 Defining the
need of the
Information
System as per
the case study
1 day Wed
22-05-19
Wed
22-05-19
15
17 4.5 Completion of
the phase
0 days Wed
22-05-19
Wed
22-05-19
14,16
18 5 Focusing over
Requirements over
the Information
System
13 days Thu
23-05-19
Mon
10-06-19
19 5.1 Gathering
requirements of
the design for
the Information
System
2 days Thu
23-05-19
Fri 24-05-19 17
20 5.2 Documenting the
planning a
narrative/story
board
3 days Mon
27-05-19
Wed
29-05-19
19
21 5.3 Defining
specification of
the Information
System
1 day Thu
30-05-19
Thu
30-05-19
20
22 5.4 Designing a use
case for the
proposed system
5 days Fri 31-05-19 Thu
06-06-19
21
23 5.5 Designing a
logical diagram
of the entire
process
2 days Fri 31-05-19 Mon
03-06-19
21
24 5.6 Focusing over
the data
structure and
drawing of an
ERD Diagram
5 days Fri 31-05-19 Thu
06-06-19
21
25 5.7 Designing a
mockup diagram
for the interface
for the proposed
system
3 days Fri 31-05-19 Tue
04-06-19
21
26 5.8 Suggesting the
architecture of
the entire
system
2 days Fri 07-06-19 Mon
10-06-19
22,23,24,25
27 5.9 Completion of
the phase
0 days Mon
10-06-19
Mon
10-06-19
26
28 6 Defining of Lessons
and further
progress of work
8 days Tue
11-06-19
Thu
20-06-19
29 6.1 Review over the
designed project
plan
2 days Tue
11-06-19
Wed
12-06-19
27
30 6.2 Making
corrections if
necessary
3 days Thu
13-06-19
Mon
17-06-19
29
31 6.3 Designing of a
Presentation that
would be
presented to the
class
2 days Tue
18-06-19
Wed
19-06-19
30
32 6.4 Making a speech
for the report
1 day Thu
20-06-19
Thu
20-06-19
31
33 6.5 Completion of
the phase
0 days Thu
20-06-19
Thu
20-06-19
32
34 7 End Project 0 days Thu
20-06-19
Thu
20-06-19
33
25-04
17-05
22-05
10-06
20-06
20-06
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
08 Apr '19 15 Apr '19 22 Apr '19 29 Apr '19 06 May '19 13 May '19 20 May '19 27 May '19 03 J un '19 10 J un '19 17 J un '19
(Fig 1: The Gantt chart for the Project)
(Source: Created by author)
3PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT
2. The Work Breakdown Structure for the Project
Project Work Out Plan
Start of the Project Requirements Gathering
Phase
Having a meeting with
classmates
Gathering requirements
over ideas for a project
Understanding of the case
study
Completion of the phase
Defining the project plan
Managing the project
team (classmates)
Making communications
about project idea brief
Documenting the project
plan
Completion of the phase
Designing of the Project
Plan
Defining the scope of the
project
Understanding the
problem statement
Defining strategies of
mitigating the problems
Defining the need of the
Information System as per
the case study
Completion of the phase
Focusing over
Requirements over the
Information System
Gathering requirements of
the design for the
Information System
Documenting the planning
a narrative/story board
Defining specification of
the Information System
Designing a use case for
the proposed system
Designing a logical
diagram of the entire
process
Focusing over the data
structure and drawing of
an ERD Diagram
Designing a mockup
diagram for the interface
for the proposed system
Suggesting the
architecture of the entire
system
Completion of the phase
Defining of Lessons and
further progress of work
Review over the designed
project plan
Making corrections if
necessary
Designing of a
Presentation that would
be presented to the class
Making a speech for the
report
Completion of the phase
End Project
(Fig 2: The WBS for the Project)
(Source: Created by author)
2. The Work Breakdown Structure for the Project
Project Work Out Plan
Start of the Project Requirements Gathering
Phase
Having a meeting with
classmates
Gathering requirements
over ideas for a project
Understanding of the case
study
Completion of the phase
Defining the project plan
Managing the project
team (classmates)
Making communications
about project idea brief
Documenting the project
plan
Completion of the phase
Designing of the Project
Plan
Defining the scope of the
project
Understanding the
problem statement
Defining strategies of
mitigating the problems
Defining the need of the
Information System as per
the case study
Completion of the phase
Focusing over
Requirements over the
Information System
Gathering requirements of
the design for the
Information System
Documenting the planning
a narrative/story board
Defining specification of
the Information System
Designing a use case for
the proposed system
Designing a logical
diagram of the entire
process
Focusing over the data
structure and drawing of
an ERD Diagram
Designing a mockup
diagram for the interface
for the proposed system
Suggesting the
architecture of the entire
system
Completion of the phase
Defining of Lessons and
further progress of work
Review over the designed
project plan
Making corrections if
necessary
Designing of a
Presentation that would
be presented to the class
Making a speech for the
report
Completion of the phase
End Project
(Fig 2: The WBS for the Project)
(Source: Created by author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT
Bibliography
Boulmetis, J. and Dutwin, P., 2014. The ABCs of evaluation: Timeless techniques for program
and project managers (Vol. 56). John Wiley & Sons.
Burns, A.C., Bush, R.F. and Sinha, N., 2014. Marketing research (Vol. 7). Harlow: Pearson.
Douglas, M., 2014. Food in the social order. Routledge.
Pang, Z., Chen, Q., Han, W. and Zheng, L., 2015. Value-centric design of the internet-of-things
solution for food supply chain: Value creation, sensor portfolio and information
fusion. Information Systems Frontiers, 17(2), pp.289-319.
Rubik, F. and Frankl, P., 2017. The future of eco-labelling: making environmental product
information systems effective. Routledge.
Bibliography
Boulmetis, J. and Dutwin, P., 2014. The ABCs of evaluation: Timeless techniques for program
and project managers (Vol. 56). John Wiley & Sons.
Burns, A.C., Bush, R.F. and Sinha, N., 2014. Marketing research (Vol. 7). Harlow: Pearson.
Douglas, M., 2014. Food in the social order. Routledge.
Pang, Z., Chen, Q., Han, W. and Zheng, L., 2015. Value-centric design of the internet-of-things
solution for food supply chain: Value creation, sensor portfolio and information
fusion. Information Systems Frontiers, 17(2), pp.289-319.
Rubik, F. and Frankl, P., 2017. The future of eco-labelling: making environmental product
information systems effective. Routledge.
1 out of 5
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.