Prickle Hill Produce Food Ordering Application Development
Verified
Added on  2023/01/18
|5
|1257
|56
AI Summary
This document discusses the development of a food ordering application for Prickle Hill Produce. It includes a Gantt chart and a work breakdown structure for the project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head:PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT Prickle Hill Produce Food Ordering Application Development Name of the Student Name of the University Author’s note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT Table of Contents 1. The Gantt chart............................................................................................................................2 2. The Work Breakdown Structure for the Project..........................................................................3 Bibliography....................................................................................................................................4
2PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT 1. The Gantt chart IDOutline Number Task Mode Task NameDurationStartFinishPredecessors 00Project Work Out Plan 52 daysWed 10-04-19 Thu 20-06-19 11Start of the Project1 dayWed 10-04-19Wed 10-04-19 22Requirements Gathering Phase 11 daysThu 11-04-19 Thu 25-04-19 32.1Having a meeting with classmates 4 daysThu 11-04-19 Tue 16-04-19 1 42.2Gathering requirements over ideas for a project 5 daysWed 17-04-19 Tue 23-04-19 3 52.3Understanding of the case study 2 daysWed 24-04-19 Thu 25-04-19 4 62.4Completion of the phase 0 daysThu 25-04-19 Thu 25-04-19 5 73Defining the project plan 16 daysFri 26-04-19Fri 17-05-19 83.1Managing the project team (classmates) 5 daysFri 26-04-19Thu 02-05-19 6 93.2Making communications about project idea brief 2 daysFri 03-05-19Mon 06-05-19 8 103.3Documenting the project plan 9 daysTue 07-05-19 Fri 17-05-199 113.4Completion of the phase 0 daysFri 17-05-19Fri 17-05-1910 124Designing of the Project Plan 3 daysMon 20-05-19 Wed 22-05-19 134.1Defining the scope of the project 1 dayMon 20-05-19 Mon 20-05-19 11 144.2Understanding the problem statement 1 dayTue 21-05-19 Tue 21-05-19 13 154.3Defining strategies of mitigating the problems 1 dayTue 21-05-19 Tue 21-05-19 13 164.4Defining the need of the Information System as per the case study 1 dayWed 22-05-19 Wed 22-05-19 15 174.5Completion of the phase 0 daysWed 22-05-19 Wed 22-05-19 14,16 185Focusing over Requirements over the Information System 13 daysThu 23-05-19 Mon 10-06-19 195.1Gathering requirements of the design for the Information System 2 daysThu 23-05-19 Fri 24-05-1917 205.2Documenting the planning a narrative/story board 3 daysMon 27-05-19 Wed 29-05-19 19 215.3Defining specification of the Information System 1 dayThu 30-05-19 Thu 30-05-19 20 225.4Designing a use case for the proposed system 5 daysFri 31-05-19Thu 06-06-19 21 235.5Designing a logical diagram of the entire process 2 daysFri 31-05-19Mon 03-06-19 21 245.6Focusing over the data structure and drawing of an ERD Diagram 5 daysFri 31-05-19Thu 06-06-19 21 255.7Designing a mockup diagram for the interface for the proposed system 3 daysFri 31-05-19Tue 04-06-19 21 265.8Suggesting the architecture of the entire system 2 daysFri 07-06-19Mon 10-06-19 22,23,24,25 275.9Completion of the phase 0 daysMon 10-06-19 Mon 10-06-19 26 286Defining of Lessons and further progress of work 8 daysTue 11-06-19 Thu 20-06-19 296.1Review over the designed project plan 2 daysTue 11-06-19 Wed 12-06-19 27 306.2Making corrections if necessary 3 daysThu 13-06-19 Mon 17-06-19 29 316.3Designing of a Presentation that would be presented to the class 2 daysTue 18-06-19 Wed 19-06-19 30 326.4Making a speech for the report 1 dayThu 20-06-19 Thu 20-06-19 31 336.5Completion of the phase 0 daysThu 20-06-19 Thu 20-06-19 32 347End Project0 daysThu 20-06-19 Thu 20-06-19 33 25-04 17-05 22-05 10-06 20-06 20-06 MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFS 08 Apr '1915 Apr '1922 Apr '1929 Apr '1906 May '1913 May '1920 May '1927 May '1903 J un '1910 J un '1917 J un '19 (Fig 1: The Gantt chart for the Project) (Source: Created by author)
3PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT 2. The Work Breakdown Structure for the Project Project Work Out Plan Start of the ProjectRequirements Gathering Phase Having a meeting with classmates Gathering requirements over ideas for a project Understanding of the case study Completion of the phase Defining the project plan Managing the project team (classmates) Making communications about project idea brief Documenting the project plan Completion of the phase Designing of the Project Plan Defining the scope of the project Understanding the problem statement Defining strategies of mitigating the problems Defining the need of the Information System as per the case study Completion of the phase Focusing over Requirements over the Information System Gathering requirements of the design for the Information System Documenting the planning a narrative/story board Defining specification of the Information System Designing a use case for the proposed system Designing a logical diagram of the entire process Focusing over the data structure and drawing of an ERD Diagram Designing a mockup diagram for the interface for the proposed system Suggesting the architecture of the entire system Completion of the phase Defining of Lessons and further progress of work Review over the designed project plan Making corrections if necessary Designing of a Presentation that would be presented to the class Making a speech for the report Completion of the phase End Project (Fig 2: The WBS for the Project) (Source: Created by author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PRICKLE HILL PRODUCE FOOD ORDERING APPLICATION DEVELOPMENT Bibliography Boulmetis, J. and Dutwin, P., 2014.The ABCs of evaluation: Timeless techniques for program and project managers(Vol. 56). John Wiley & Sons. Burns, A.C., Bush, R.F. and Sinha, N., 2014.Marketing research(Vol. 7). Harlow: Pearson. Douglas, M., 2014.Food in the social order. Routledge. Pang, Z., Chen, Q., Han, W. and Zheng, L., 2015. Value-centric design of the internet-of-things solutionforfoodsupplychain:Valuecreation,sensorportfolioandinformation fusion.Information Systems Frontiers,17(2), pp.289-319. Rubik, F. and Frankl, P., 2017.The future of eco-labelling: making environmental product information systems effective. Routledge.