Findings on Vella Office Fitouts
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Introduction Project management plan is the process or guideline level of type of information that should be defined in the early stage of the project in the form of a project management plan. This would help to control the effective management plan. Present plan would be based on ProCon services Australia, it is the project management consultancy. This company already exist with Vella IT office Fitouts of a medium rise office building in a Sydney suburb. The project manager of the company Tony Faultier suddenly left the Fitouts and engage with another overseas company.
Scope of the Project This present project will help to stimulate proper planning, strategical options, costing and recover all risks for the big events. This conference would help to make coordination. It also includes delegations, technicians, media experts and number of interested people in IT.
Aims of the Project Project Tracking and Reporting Presentation skills Team behaviour and team building Learning and Reflection
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
On the basis of investigation process and observation goals it has been investigated that, I observed so many things that affect the business goals more challenging. I observed that project management is the essential process or channel to discover the best source of channel. Vella Office Fitouts is required to hire the best possible action and growth. As per the observation, it has been analysed that employees have not fulfilled the exact project plan because of proper coordination level between persons. As per the situation observed, there are so many reasons behind project failures such as poorly defined project scope, inadequate risk management, failure to identify key assumptions, lack of effective communications at all levels, poor management of expectations, ineffective leadership.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Organisation behaviour •This work will not be good at deciding goals, moreover it takes time to rethink the goals and market into more effective manner.ManagerofVellaOffice Fitouts are always being autocratic and not involved anyone into the decision making process. •VellaOfficeFitoutsalsoneedsto increase positive interdependence level between people.
To be Continued •For example, positive interdependence can be found in jigsaw tasks scheme for specifying groups that gets its helps to fulfil the longer time scale. This would help to control longer term goals. •Company also needs to focus on cost balance to ensure the best rate of return as well as for its goodwill.Besides, employeesrequiremakingthebest sourcefullleadingsourcesandmake good environment for the employees. •Overall,tomakeprojectsuccessful, companyrequiredtoinvestgoodon employeesinordertoenhancetheir motivation level or growth.
Current status of project It has been evaluated that the current status of project is impacted. By investigating the schedule, it can be identified that ground floor work must get completed but only 75% is done, second and first floor is 25% done. But the terrace part is ahead of schedule; that is, 50% complete. So, there is only minor impact on project. On contrary, budget has not been utilized properly because of improper working of staff apart from schedule. Furthermore, it has beenidentifiedthat previous manager did not allocated resources properly. Due to this, there has been an impact on budget of project.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Schedule variance Here, it can be identified that due to delay in project start, there can be an impact on schedule. It has enforced project manager to develop a new schedule so that project can be completed in given time period. Besides this, it is the stage where project has to be completed in two months as it is lacking behind the timeline. It has also impacted on the behaviour of staff. Due to this, there has been impact on budget of project.
Cost variance Due to impact on schedule, the cost will also be affected. A new manager is hired to take over the project. From the budget allocated, only $675k has been used in two months. But as per schedule, almost half of budget must have been utilized. This might be due to ineffective planning or distribution of resources. Therefore, it is essential to allocate resources as per schedule so that budget is utilized in proper way. This will also ensure with completion of each stage, resources must be distributed.
Additional information- For new manager, it is essential to know what is current status of project so that further planning can be done. Without this it will be very difficult to develop plan to complete project on time. The additional information requirements are previous schedule plan developed, cost incurred in each activity. By analysing these information, it will be easy for manager to produce regular detailed status of project. With the help of report ,manager will be able to allocate resources and develop time scale for each floor. Moreover, manager will get an insight whether project is moving in right direction or not. Then, accordingly further activities can be decided and plan is developed.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Recommendations Inordertocompleteprojectinspecifiedtime,managercanfollowserval recommendations that are as follows :- Proper policies should be developed regarding environment so that problems can be solved and team work can be established. Risk assessment plan can be developed by manager. It will help in taking effective measures at critical time and reducing risk. Problems can be identified and solved by developing effective strategies. This will ensure smooth flow of work between team members.
Cost Structure sheet
Delivery and Post implemented review
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
References Sears, S. K., and et.al., 2015.Construction project management. John Wiley & Sons. Silvius, A. J. and Schipper, R. P., 2014. Sustainability in project management: A literature review and impact analysis.Social Business.4(1). pp.63-96. Špundak, M., 2014. Mixed agile/traditional project management methodology– reality or illusion?.Procedia-Social and Behavioral Sciences.119.pp.939- 948. Turner, R., 2016.Gower handbook of project management. Routledge. Verzuh, E., 2015.The fast forward MBA in project management. John Wiley & Sons. Walker, A., 2015.Project management in construction. John Wiley & Sons.