Produce Labour and Material Schedules for Ordering | Report

Verified

Added on  2022/08/25

|6
|1051
|23
AI Summary
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Produce Labour and Material Schedules for Ordering 1
PRODUCE LABOUR AND MATERIAL SCHEDULES FOR ORDERING
Student’s Name
Institutional Affiliation
Course
Professor’s Name
City
Date
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Produce Labour and Material Schedules for Ordering 2
Part B
Kings Plan Garage - Resource Schedule Student Name: Note: item = as per contractors estimate
Resource Week 1 Week 2 Week 3 Week 4 Week 5
A Specific Task Labour man
hours
Mat / Equip
quantity
Mo
n Tue Wed Thur Fri Mon Tue Wed Thur Fri Mon Tue Wed Thur Fri Mon Tue Wed Thur Fri Mon Tue Wed Thur Fri
1 Earthworks
1.1 Labour 6 x 8hrs
1.2 Roadbase material - 100mm thick 4.2 m³
1.3 Skid Steer Loader 2
2 Concrete Slab
2.1 Labour 3 x 8hrs 1 concrete
mixer
2.2 Formwork material (150 x 50) 30 m
2.3 Reinforcement material 44 x 8hrs
2.4 concrete material/curing of concrete 13745.5 kg
3 Services
3.1 Pre Slab (independent contractor -
Lab&Mat) 5 x 8hrs 14 m electric
pipes
3.2 Finishing stages (independent
contractor - Lab&Mat) 5 x 8hrs
4 Framing
4.1 wall Framing (independent
contractor - Lab&Mat) 5 x 8hrs 91.6m steel
4.2 Roof Framing (independent
contractor - Lab&Mat) 5 x 8hrs 38 m steel
5 Cladding
5.1 Wall clad (independent contractor -
Lab&Mat) 4 x 8hrs
5.2 Roof clad (independent contractor -
Lab&Mat) 4 x 8hrs
6 Joinery
6.1 Windows (independent contractor -
Lab&Mat) 2 x 8hrs
6.2 Doors (independent contractor -
Lab&Mat) 2 x 8hrs
6.3 Roller doors (independent
contractor - Lab&Mat) 4 x 8hrs
7 Clean up
7.1 Labour 4 x 8hrs
7.2 Bin or truck 2 trucks
= Labour = Material or Equipment = independent contractors labour and material combined
Document Page
Part C
(i).
For new or refurbishment developments, it is a requirement by the building regulations to
have a complete set of approved documentation to ensure the works go on smoothly and
undisrupted (Cass 2018). The documentation should be submitted to the local authority such as a
municipality for review and approval. In this scenario, a double garage and workshop area to be
erected on a residential development on Plot number FFL 625.995. The area dedicated to the
garage measures 6 metres by 10 metres hence an area of 60 square metres. The site is relatively
flat and hence deep excavations shall not be necessary.
Important documents that would be required to undertake the project include Plot Title,
Permits, and Project Specifications (Ching and Winkel 2018). The plot title is a document that
shall define the property boundaries, distances and compass bearings. In this case, it will show
the plot owner, the plot geographical location amongst neighboring plots, and any roads and
access to the plot. Finally, the title shall be stamped by the registrar of titles to be a legal
document (Foo and Shen 2018).
Permits are other documents necessary for the project to kick off. They show approvals
received from the council or a quantity surveyor (Karamujic 2020). These permits aim to show
that building regulations have been adhered to as per the Building Codes of Australia and other
international codes. Some of these permits include the asset protection permit that covers repair
to council assets such as water and electricity lines. The roads opening permit is necessary to
show any roads that have been created to access the development (Lilienthal and Ahmad 2019).
In this case, the proprietor should obtain a new permit even though there is no new road to the
garage needed.
Document Page
The final documents needed are the project specifications documents. These are
important documents as they show job description, site description, proprietors, and other parties
including their contacts address, and their physical locations such as a municipality (Saunders
and Tulip 2019). There is a need for a trade section in this document that shows the applied
standards and quality of work expected. Finally, a schedule of fittings shall be necessary.
Schedules include windows, doors, finishes, and ironmonger to be used on the doors. Other
services such as preliminary site works and foundations, electrical, plumbing and stormwater and
sewer drainage are necessary to be included in the project specifications. The documents should
be pinned on an accessible area on site where a council inspector can access it. The law dictates
that the site can be closed in case of such documents are missing.
(ii).
The hand sketch attached shows the garage on the proposed location of the erection. The
dimensional of the proposed garage is 6 metres by 7 metres hence leaves some access of 3
metres on the longest side. This is important for providing a working area and ease of access.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Overlay Drawing
Document Page
Reference List
Cass, S., 2018. The garage fab [Resources]. IEEE Spectrum, 55(1), pp.17-18.
Ching, F.D. and Winkel, S.R., 2018. Building Codes Illustrated: A Guide to Understanding the
2018 International Building Code. John Wiley & Sons.
Foo, G.S.E. and Shen, D., 2018. Australian Commercial Buildings Window to Wall Ratios.
In International Conference of the Architectural Science Association (pp. 231-240).
Karamujic, H.M., 2020. Building approvals as a leading indicator of property sector
investment. International Journal of Banking and Finance, 9(2), pp.44-58.
Lilienthal, G. and Ahmad, N., 2019. Colonial land title in Australia: a meta-legal critical
inquiry. Commonwealth Law Bulletin, pp.1-26.
Saunders, T. and Tulip, P., 2019. A Model of the Australian Housing Market. Reserve Bank of
Australia Discussion Paper Series, 1.
chevron_up_icon
1 out of 6
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]