Running head: PROJECT ACTIVITY CALCULATION
PROJECT REPORT
Name of the Student:
Student ID:
Name of the University:
Author’s note:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT ACTIVITY CALCULATION
4. Integration of WBS and OBS
The project comprises of the following activities and WBS Ids,
WBS Task Name
0 Project
APIC-A Approval
A10 Draft Proposal
A20 Submit Proposal
A30 Final Details
A40 Milestone
APIC-B Foundations
B10 Level ground
B20 Dig Trenches
B30 Sewage connections
B40 Electrical (to mains)
B50 Gas (to mains)
B60 Pour Concrete
B70 Brick Foundations
APIC-C Walls and Roof
C10 Brick Walls
C20 Wooden Rafter
C30 Windows preparation
C40 Lay roof tiles
C50 Milestone
APIC-D Interior (needs roof)
Document Page
2PROJECT ACTIVITY CALCULATION
D10 Electrical wiring
D20 Pipes and plumbing
D30 Doors
D40 Windows installing
D50 Floor boards
D60 Milestone
APIC-E Bathroom and Kitchen
E10 Walls
E20 Bathroom fitting
E30 Bathroom tiling
E40 Bathroom Flooring
E50 Kitchen fitting
E60 Kitchen slate flooring
E70 Milestone
APIC-F Finish
F10 Plasterboard walls
F20 Painting
F30 Milestone
The integration of the WBS and OBS is shown in the following diagram,
Document Page
3PROJECT ACTIVITY CALCULATION
Figure 1: OBS and WBS integration
(Source: Created by the author)
The project schedule in given in the following table,
WBS Task Name Duration Start Finish
0 Project 273 days Fri 6/1/18 Tue 6/18/19
APIC-
A Approval 10 days Fri 6/1/18 Thu 6/14/18
A10 Draft Proposal 5 days Fri 6/1/18 Thu 6/7/18
A20 Submit Proposal 2 days Fri 6/8/18 Mon 6/11/18
A30 Final Details 3 days Tue 6/12/18 Thu 6/14/18
A40 Milestone 0 days Thu 6/14/18 Thu 6/14/18
APIC-B Foundations 90 days Fri 6/15/18 Thu 10/18/18

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT ACTIVITY CALCULATION
B10 Level ground 15 days Fri 6/15/18 Thu 7/5/18
B20 Dig Trenches 20 days Fri 7/6/18 Thu 8/2/18
B30 Sewage connections 30 days Fri 8/3/18 Thu 9/13/18
B40 Electrical (to mains) 18 days Fri 8/3/18 Tue 8/28/18
B50 Gas (to mains) 18 days Fri 8/3/18 Tue 8/28/18
B60 Pour Concrete 15 days Fri 9/14/18 Thu 10/4/18
B70 Brick Foundations 10 days Fri 10/5/18 Thu 10/18/18
APIC-
C Walls and Roof 50 days Fri 10/19/18 Thu 12/27/18
C10 Brick Walls 25 days Fri 10/19/18 Thu 11/22/18
C20 Wooden Rafter 5 days Fri 11/23/18 Thu 11/29/18
C30 Windows preparation 20 days Fri 11/23/18 Thu 12/20/18
C40 Lay roof tiles 25 days Fri 11/23/18 Thu 12/27/18
C50 Milestone 0 days Thu 12/27/18 Thu 12/27/18
APIC-
D Interior (needs roof) 29 days Fri 12/28/18 Wed 2/6/19
D10 Electrical wiring 14 days Fri 12/28/18 Wed 1/16/19
D20 Pipes and plumbing 14 days Fri 12/28/18 Wed 1/16/19
D30 Doors 8 days Fri 12/28/18 Tue 1/8/19
D40 Windows installing 8 days Fri 12/28/18 Tue 1/8/19
D50 Floor boards 15 days Thu 1/17/19 Wed 2/6/19
D60 Milestone 0 days Wed 2/6/19 Wed 2/6/19
APIC-E Bathroom and Kitchen 69 days Thu 2/7/19 Tue 5/14/19
E10 Walls 10 days Thu 2/7/19 Wed 2/20/19
E20 Bathroom fitting 10 days Thu 2/21/19 Wed 3/6/19
E30 Bathroom tiling 10 days Thu 3/7/19 Wed 3/20/19
Document Page
5PROJECT ACTIVITY CALCULATION
E40 Bathroom Flooring 15 days Thu 3/21/19 Wed 4/10/19
E50 Kitchen fitting 10 days Thu 4/11/19 Wed 4/24/19
E60 Kitchen slate flooring 14 days Thu 4/25/19 Tue 5/14/19
E70 Milestone 0 days Tue 5/14/19 Tue 5/14/19
APIC-F Finish 25 days Wed 5/15/19 Tue 6/18/19
F10 Plasterboard walls 10 days Wed 5/15/19 Tue 5/28/19
F20 Painting 15 days Wed 5/29/19 Tue 6/18/19
F30 Milestone 0 days Tue 6/18/19 Tue 6/18/19
The end date of the project (considering the project started on 1st June, 2018) is 18th June, 2019.
5. Develop Network Plan
The detailed network plan for the project is shown in the following diagrams,
Document Page
6PROJECT ACTIVITY CALCULATION

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT ACTIVITY CALCULATION
Figure 2: Snaps of Project Network Diagram
(Source: Created by the author)
The critical path of the project is shown in the network diagram as the highlighted red boxes are
the critical work package of the project. The project Draft Proposal, Submit Proposal, Final
Details, Milestone, Level ground, Dig Trenches, Sewage connections, Pour Concrete, Brick
Foundations, Brick Walls, Lay roof tiles, Milestone, Electrical wiring, Floor boards, Milestone,
Walls, Bathroom fitting, Bathroom tiling, Bathroom Flooring, Kitchen fitting, Kitchen slate
flooring, Milestone, Plasterboard walls, Painting, and Milestone are the critical path of the
projects.
6. Detail Cost Budget
The detail cost budget is shown below,
Budget
Material Cost Total
Document Page
8PROJECT ACTIVITY CALCULATION
Plumbing material $15,000.0
0
Concrete rods $20,000.0
0
paint $15,000.0
0
Flooring material $25,000.0
0
Electrical equipment $15,000.0
0
Glass windows $15,000.0
0
Woods $15,000.0
0
cement $20,000.0
0
bricks $15,000.0
0
Administration and office work Advertisement, signs and
marketing
$15,500.0
0
Sub total $170,500.00
Human Cost
S. Hodson $1,500.00
P. Smith $1,500.00
M. Williams $1,500.00
Document Page
9PROJECT ACTIVITY CALCULATION
L. Liam $1,200.00
D. Peter $1,200.00
D. Nickolas $1,500.00
E. Michel $900.00
S. Wilson $900.00
D. Peter $900.00
D. Love $900.00
A. Suliman,A. March $2,100.00
A. March $2,400.00
Z. George $900.00
E. Ding $600.00
C. Frank $2,100.00
J. David,F. Lowis $1,500.00
D. Love $1,500.00
A. March,A. Suliman $1,200.00
A. March $1,200.00
A. Suliman $900.00
M. Edward $900.00
M. Edward $1,500.00
M. Edward $1,200.00
M. Edward $900.00
M. Edward $600.00
A. Suliman $1,500.00
Z. George $1,500.00
Sub total $34,500.00

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT ACTIVITY CALCULATION
Total Budget $205,000.00
7. Develop Schedule Resource Plan
The schedule resource plan for the activities of C10 to C40 is given in the table below,
WBS Task Name Duration in hours Resource Names Cost
APIC-
C
Walls and Roof
C10 Brick Walls 200 A. Suliman, A. March $2,100.00
C20 Wooden Rafter 40 A. March $2,400.00
C30 Windows preparation 160 A. Suliman $900.00
C40 Lay roof tiles 120 E. Ding $600.00
C50 Milestone 0 $0.00
Document Page
11PROJECT ACTIVITY CALCULATION
Bibliography
Abrahamsson, P., Salo, O., Ronkainen, J., and Warsta, J. 2017. Agile software development
methods: Review and analysis. arXiv preprint arXiv:1709.08439.
Benner, K. M., Feather, M. S., Johnson, W. L., and Zorman, L. A. 2014. Utilizing scenarios in
the software development process. Information system development process, 30, 117-134.
Braude, E. J., and Bernstein, M. E. 2016. Software engineering: modern approaches. Waveland
Press.
Clarke, P., O’Connor, R. V., and Leavy, B. 2016, May. A complexity theory viewpoint on the
software development process and situational context. In Software and System Processes
(ICSSP), 2016 IEEE/ACM International Conference on (pp. 86-90). IEEE.
Ferreira, T., Gutiérrez-Artacho, J., and Bernardino, J. 2018, March. Freemium Project
Management Tools: Asana, Freedcamp and Ace Project. In World Conference on Information
Systems and Technologies (pp. 1026-1037). Springer, Cham.
Krahn, H., Rumpe, B., and Völkel, S. 2014. Roles in software development using domain
specific modeling languages. arXiv preprint arXiv:1409.6618.
Liu, J., Zhang, S., Kato, N., Ujikawa, H., and Suzuki, K. 2015. Device-to-device
communications for enhancing quality of experience in software defined multi-tier LTE-A
networks. IEEE Network, 29(4), 46-52.
Mc Hugh, M., McCaffery, F., Casey, V., and Pikkarainen, M. 2017. Integrating agile practices
with a medical device software development lifecycle.
1 out of 12
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]