Project Analysis: Wembley Stadium and Berlin Brandenburg Airport

Submit a short write-up with observations on two papers discussing lessons learned from project management.

4 Pages895 Words100 Views
   

Added on  2022-10-04

About This Document

This article discusses the project management scenarios of the construction of Wembley Stadium and Berlin Brandenburg Airport, highlighting the failures and observations. It emphasizes on the importance of proper procurement processes, cost estimation, time scheduling, risk management, and communication with stakeholders.

Project Analysis: Wembley Stadium and Berlin Brandenburg Airport

Submit a short write-up with observations on two papers discussing lessons learned from project management.

   Added on 2022-10-04

ShareRelated Documents
Running Head: PROJECT ANALYSIS
Project Analysis
Name of the Student
Name of the University
Author Note
Project Analysis: Wembley Stadium and Berlin Brandenburg Airport_1
PROJECT ANALYSIS
1
Wembley Stadium Project Analysis
This article discuss about the project management scenario of the construction of the
Wembley stadium that is suitable for organising several sports tournaments like rugby, football,
and several athletics, also it has the capacity to accommodate around 90,000 people at once.
The requirements of some stakeholders were failed in prioritizing which resulted in huge
payments to the stake holders and filing of lawsuit against the management team. The sharing of
information among stakeholders and team members were not properly done.
The proper disclosure of information and adequate involvement of stakeholders in the
project is necessary. The unfair bidding process occurred by awarding contractor quickly. The
information related to the bidding process must be shared to the public as £161 million public
funding was involved and eventually it had raised to £798 million. Therefore, proper
procurement processes must be followed.
As the project consists of unique design of stadium, so fixed price contract was not
favourable for this project. The adjustment of the changes resulted in over budget and operations
of the project were behind the original schedule. Therefore, cost estimation and time scheduling
must be done to maintain the positive relationship between the contractor and the client.
This article discusses about the changed design in 1999 from 1994 thus, £20 million had
to be returned to the Sport England as the athletics was removed from the previous design.
Football Association delayed the first payment and again the athletic platform design was
restored. All this events eventually resulted in the restructuring of the project scope. Thus the
budget fluctuated and resulted in increase overall cost.
The quality of the overall project was lower than everybody’s expectation, the concrete
quality for the stadium was not good, the football pitch was slippery etc..
Project Analysis: Wembley Stadium and Berlin Brandenburg Airport_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Report on Construction of Wembley stadium | Effective Management
|17
|5010
|312

Risk Management and Procurement Strategy for Wembley Stadium Project
|18
|3990
|89

Project Planning and Management: Lessons Learned from Successful and Failed Football Stadium Projects
|14
|3743
|128

Berlin Brandenburg Assignment Report
|14
|3412
|35

Failure of Berlin Brandenburg Airport
|20
|942
|331

Risk and Due Diligence in Construction Projects: A Case Study of Perth Stadium
|13
|2822
|262