Project Budget, Schedule and Resources

   

Added on  2023-06-14

22 Pages2559 Words400 Views
Leadership ManagementMaterials Science and Engineering
 | 
 | 
 | 
Running Head: PROJECT MANAGEMENT
Project Budget, Schedule and Resources
Name of the Student
Name of the University
Project Budget, Schedule and Resources_1

1PROJECT MANAGEMENT
1. Project Budget
The estimated project budget as per the deliverables is shown in the following table.
Task Name Cost
Upgradation of Oil Storage Facility $5,163,800.00 [TOTAL BUDGET]
Project Initiation Stage $266,400.00
Survey of the Site $51,000.00
Identification of the Issues and
Problems
$17,000.00
Call Team Meeting $4,000.00
Discuss the Issues $48,000.00
Find Possible Solutions $19,200.00
Discuss Project Feasibility $19,200.00
Prepare Initial Budget Estimate $38,400.00
Make Assumptions Regarding Project $38,400.00
Determine Project Constraints $19,200.00
Review Proposed Plan $4,000.00
Project Budget, Schedule and Resources_2

2PROJECT MANAGEMENT
Approve Project $8,000.00
Project Planning Stage $144,600.00
Develop Business Case $48,000.00
Develop a Detailed Project Charter $14,000.00
Determine Project Scope $14,000.00
Develop Project Objectives $5,600.00
Prepare Project Work Breakdown
Structure
$2,800.00
Develop Gantt Chart $1,400.00
Estimate Project Schedule $1,400.00
Estimate Project Budget $1,400.00
Appoint Roles to Stakeholders $8,000.00
Release Tenders for Contract $10,000.00
Hire Contractors based on Lowest Bid $4,000.00
Contact Sponsor $9,600.00
Procure Project Budget $9,600.00
Provide Project Plan to the Contractor $2,800.00
Project Budget, Schedule and Resources_3

3PROJECT MANAGEMENT
Initiate Project $12,000.00
Project Execution Stage $4,594,000.00
Works on Tank 1 $1,358,000.00
Relocation of Attached Structures
and Equipments
$120,000.00
Install Scaffolding $21,000.00
Install Cranes $46,000.00
Start Repair Work $21,000.00
Add Steel Patches $400,000.00
Add Steel Anchors $500,000.00
Cleaning of Tank $85,000.00
Repaint of the Tank $85,000.00
Remove Cranes $40,000.00
Remove Scaffolds $40,000.00
Works on Tank 2 $1,548,000.00
Relocation of Attached Structures $120,000.00
Project Budget, Schedule and Resources_4

4PROJECT MANAGEMENT
and Equipments
Install Scaffolding $21,000.00
Install Cranes $46,000.00
Start Repair Work $21,000.00
Add Steel Patches $590,000.00
Add Steel Anchors $500,000.00
Cleaning of Tank $85,000.00
Repaint of the Tank $85,000.00
Remove Cranes $40,000.00
Remove Scaffolds $40,000.00
Works on Tank 3 $1,688,000.00
Relocation of Attached Structures
and Equipments
$120,000.00
Install Scaffolding $21,000.00
Install Cranes $46,000.00
Start Repair Work $21,000.00
Add Steel Patches $540,000.00
Project Budget, Schedule and Resources_5

5PROJECT MANAGEMENT
Add Steel Anchors $540,000.00
Replace Main Supply Valve $150,000.00
Cleaning of Tank $85,000.00
Repaint of the Tank $85,000.00
Remove Cranes $40,000.00
Remove Scaffolds $40,000.00
Project Closing Stage $158,800.00
Project Handover $4,000.00
Review of the Entire Project $72,000.00
Project Documentation $14,000.00
Clearing of Payments and Dues $48,000.00
Stakeholder Signoff $16,800.00
Project Closing $4,000.00
While preparing this budget, the assumptions that have been made are as follows
(Kerzner and Kerzner 2017).