This Project Closure Report provides an overview of the Downtown Project in Las Vegas, including its performance summary, cost, scope, and timeline. It discusses the reasons for the project's failure and the challenges faced. The report also includes insights from the project sponsor and project manager.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Project Closure Report
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents Section 1.....................................................................................................................................3 Section 2.....................................................................................................................................5 Section 3.....................................................................................................................................9 References................................................................................................................................13
Section 1 Project Overview- The Downtown Project was started in 2012 planned to be completed within 5 years. Zappos CEO Tony Hsieh is the founder of the DTP project. The projects of Downtown Las Vegas Nevada focused on transforming a part of Las Vegas in a vibrant community full of opportunities related to employment for young professionals. Previously, Downtown wasfull of bankruptcy,foreclosureand unemployment.Thebaselinecost allocated to the Downtown project was $350 million obtained from personal capital of sale of Amazon in 2009. The project focused on providing detailed information related to DTP, whichwasconsidered as a revitalizingprojectwith investmentsin real estate,small businesses, start-up, technology, education, art, culture, and healthcare. Project Performance Summary- The project is not yet completed because of inappropriate estimation of time for such a huge project. The project was associated with number of risks which involved cost risks, design risks and schedule risks. DTP Las Vegas is a failed project based on Triple constraints i.e. Time, Cost and Scope. The project has exceeded both costs and time of completion. Few of the various reasons behind failure of project are business shattering, layoffs and shuttering of businesses. The DTP project aimed at achieving Utopian vision but there was lack of expertise and enough resources. DTP selected an inappropriate location for community development program as Nevada is a poor city with people having conservative perception along with community facing unemployment, bankruptcy, poverty and crime. All these issues resulted in failure of project. The project is a complete failure from the perspective of project sponsor as well as project manager. From the perspective of project sponsor, lack of enough time for a project to start from scratch, lack of resources leading to delay in operations and in overall project delay. The scope of the project should have reduced if the project was to be completed on time estimated for its completion. The issues such as employees lay off and negative perception of locals for DTP project also
resulted in failure of project. From the perspective of project manager also, the DTP project was a failed project on all the three important measures which is time, cost and scope. The delay in scheduling of activities and ineffective allocation of projects led to the failure of project. The time allotted for completion of project that included development of shopping mall, fire capital, shipping container capital along with HealthCare facility, stores etc in an undeveloped region required a long time period. The investments were also not enough leading to failure of project. Lack of effective utilization of resources resulted in non- addressal of the quality issues involved with project. The estimated cost for completion of project was $350 million but it rose to $500 million due to lay offs and lack of affordable housing projects. The scope of project has not been defined effectively as it was wide that included development of various aspects. So, project sponsor and project manager would not have taken this project considering all these aspects. Cost- The costs of the project was estimated to be completed in $350 million but the actual cost increased to $500 million but the project is still not yet completed. The costs exceeded because of the wider scope of the project that included buildings, parks, schools, malls and all other facilities for community development. Furthermore, the community has already been less developed, and the people are uneducated and unemployed. The development of a vibrant community required huge investment for starting the construction process from scratch. The costs exceeded with increasing time in the completion of the project because more resources are required to be purchased. All these aspects led to the increase in costs of the project. The sponsors would not have considered it to be a profitable project if prior planning would have been conducted. Scope- The scope of the project has been wide that led to increase in costs of project and increase in time of the project. The project has been an entire failure because it involved wide scope including real estate, construction, art and culture. The project with such a large scope
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
requires a structured approach, expertise and knowledge but there has been lack of expertise and structured approach. The Downtown project was started with the intention of creating a shipping container, fire capital and co working capital within 5 years. Even after 5 years, the project was not complete because of its utopian mission to create an ideal society. So, scope of the project also resulted in failure of project. Section 2 The projects of Downtown Las Vegas Nevada is a transforming project that focuses on transformingoneofthepartsofLasVegasinavibrantcommunitythatisfullof opportunities related to employment for the young professionals. The project will offer foundation to new companies and provide income and job to the city. The Downtown before the project was full of bankruptcy, foreclosure and unemployment by the CEO of Zappos realized the potential of the Downtown. From here the idea of DTP evolved. In the year 2012 the idea of accelerating growth, connectedness , innovation, happiness and growth feel into place and the project started in the same year. The project was started with a compelling vision of creating a large city that is community focused. The planned baseline cost allocated to the Downtown project was $350 million that was obtained from the personal capital of Amazon’s sale in the year 2009.This project will focus on providing detailed information related to DTP that was one of the most popular revitalizing project with investments in areas such as real estate and development, small businesses, start up and technology, education, art, culture and healthcare. In order to provide full details of the project focus will be on defining the cost, time, scope and variances etc. related to a project. Cost of the project The DTP was started with mission of revitalization of Downtown of Las Vegas with the 3 C’s - Collision, Co learning and connectedness.
The DTP was a large scale project that involved huge costs as funds have to be allocated in different areas.The base line costs allocated for each of the area in DTP are discussed below: Baseline CostActual Cost TotalcostRevitalizationof Downtown $ 350 Million$500 Million (Approx.) Real Estate and development$200 MillionN.a Tech start up$ 50 MillionN.a Small businesses$ 50 MillionN.a Art , culture, education and healthcare$ 50 MillionN.a (Gorth, 2018) Real Estate and Development - The highest percentage of cost has been invested in area of Real Estate and development ($200 Million). The developments were done is around 45 Acres of the land for operations of 11 businesses. Small businesses – The small businesses in the project included restaurants, stores, bars, recording studios, toy stores, microbreweries, application based laundry businesses and a business for dry cleaning.(DTPLV, 2019) Time (2012 – till present) The Downtown Project Las Vegas was started in the year 2012 with a mission of completing the same within next five years.The project DTP is not yet completed and its mission of creating a real city is also not accomplished. The report of Groth (2017) indicates that the Downtown project was started with the intention of creating a shipping container, fire capital
and co working capital in 5 or less than 5 years. Even after the five the DTP was not complete because of its utopian mission. In other words, a mission of creating an ideal society that is best is every way.(Gorth, 2018). The expected timeline of the project is given below: YearTask Year 1 (2012)Acquiring and assembling technology, businesses and investments Year 2 (2013)Funding/investments in different areas Year 3 (2014)Focus on resource optimization and streamlining of processes Year 4 (2015)Scaling and streamlining the processes Year 5 (2016)Getting positive cash flow and sustainability The expected timeline of DTP is not achieved yet. This is possible because of the short time of period of 5 years was estimated for a big project like DTP that involved number of tasks and activities. DTP has fallen short of its ideal mission as it has also denied some of the important pieces for making a city.(Evernote, 2019) Project Scope Project scope can be defined as the part of project planning that determines as well as documents the specific goals, deliverables, goals, deadlines, tasks, costs, etc. A project scope needs to be defined in the most effective form so that project goals and objectives can be achieved. Project scope also helps project managers in allocating the organisational resources and achieve project goals and objectives within a budget.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Name – Downtown Project Las Vegas The project was founded in the year 2012 with an objective of reinventing the Nevada city with help of a community development plan in a budget of 350 Million. The project included the reinvention of the city with an investments in areas such a technology, small business, real estate, culture, education, healthcare and technology. The time allocated to the project was of 5 years.Zappos CEO Tony Hsieh is the founder of DTP project.(reviewjournal, 2018) The DTP was starter with a view that the community development program will offer number of advantages in terms innovation, inspiration, energy, creativity, mobility and discovery with help of co learning, collision and connectedness is a sustainable manner.(dtplv, 2019)The project also includes construction projects, investments and the revenue from the visitors. (dtplv, 2018). The DTP also helps in offering opportunities related to employment, salaries and the economic outputs.The DTP was also associated with number of risks such as the cost risk, design risks and schedule risks. The cost risks are may lead to an increase in the overall budget of project, the design risks may lead to modifications in design that is both time and resource consuming, and scheduling risk may lead to delay in the overall project. DTP has a wide range of stakeholders including employees, architectures, authorities, shareholders, government, tourists and all other people involved in project(DPTLV, 2019). The time scope and cost are the three major measures of project success. The measures together are also known as the ‘triple constraints’. DTP Las Vegas is a failed project on the
basis of Triple Constraints.(projectsmart, 2011). The project has exceeded both its cost and time of completion.The project was scheduled to be completed after 5 years from 2012 but the project is not completed yet. The outcomes of project are mixed in nature with few successes and more failures. For example: the project has seen some businesses shattering, layoffs and shuttering of businesses(CNBC, 2018). The overall community development project of DTP failed on the dimensions ion of cost , scope and time. The time estimated for project completion was exceeded, the cost estimated was also exceeded and scope was utopian in nature i.e. ideal in nature that was hard to achieve in duration of 5 years. Instead DTP should have been started with a smaller and clearly defined scope. The DTP was started with a scope of reinventing or transforming a poor country that lacked basic resources required for a project(Southern Naveda Strong, 2014).Variance in a project can be defined as the difference between the standard value or baseline and actual results. High variance in a project indicates the failure of a project in terms of time, cost and scope. There were also variances in DTP were high as the project took more than 5 years for completion and the budget is also estimated to exceed by 2 Million. Section 3 As a project sponsor I consider the DTP as a failed project.The project aimed at achieving utopian vision that is hard to achieve without experience, expertise and resources. According to me DTP has chosen a wrong location for a community development program. The location that was chosen by DTP was Nevada that is a poor city with people having conservative perception. The region is associated with issues such as unemployment, bankruptcy, poverty and crime.(Harris, 2014)These issues collectively lead to failure of a project.The underdevelopment of Nevada led to an increase in the dependency of Nevada on investment
but companies were not much interested in investing in a backward region.In addition the future ofthe city was also uncertain because of underdevelopment(lasvegasnevada., 2019). As a Project SponsorI would have neverapproved a project like DTP with a vision that is hard to achieve in just 5 years. Timeliness The time allotted for the project was 5 years that was short enough for a project like DTP that had to be started from a scratch. The time required for the development of city like Nevada is itself very high. Lack of resources led to delays in operations that further leads to a delay in overall project. The time of the project also increased because project managers and leaders of DTP also had to wait for the investments in the community.(Inc, 2018). The DPT is complete failure on the measure of timeliness as it failed to deliver the project on time. The project should have been allotted more time or the scope of the project should have been reduced. The time of the project would have also increased because of the issues such as employeeslay off and negative perception of locals for the DTP project. The project by Zappos CEOTony Hsieh with a compelling vision was started in the year 2012 with an investments as high as 350 Million. With a perspective of a project manager I consider DTP as a failed project.The project is failed on the three important measures of project management – time , cost and scope. The time , cost and scope are the foundation of a successful project. Time The time assigned for the project was 5 year but it was not completed on time.The delays might be in the scheduling of activities involved in community development program. The project included number of tasks and activities as it was a large scale project of community development with huge investments. The resources were however not allocated effectively. The project could have been completed in part rather than with an utopoian vision of creating
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
an ideal city out of an undeveloped city.The time allotted for the completion of a large project like DTP that included activities such as creation of shopping mall, fire capital , shipping container capital along with HealthCare facility, stores etc. was very short.A community development program like DTP requires at least 10- 8 years. This is because the vision was of reinventing an undeveloped region into a place that is full of opportunities. The 5 years’ time for project completion was also not optimum considering the scope of project. The DTP was much dependent on the investments ofdifferent parties that again requires a huge amount of time. DTP was not able much of the investments leading to a failure. (Schoenmann, 2017). The resources in project were not utilized properly that led to shortage of resources. The project managers hence could not address the quality issues in the community development program. The project in Las Vegas was also launched in Nevada where people expected that the company is doing a work of charity but project was heavily dependent on investments and small businesses(vegasinc.lasvegassun., 2019). Cost The project management triangle is a highly valuable tool that is used for prioritizing the decision making by project managers. This tools can however be used by competent leaders and managers(Caccamese & Bragantini, 2012). In estimated cost of the project was 350 million but by the DTP project was on its journey of completion the cost of project rose to 500 million. The cost of project would have further increased because of future development.The cost estimation of DTP project was not done accurately(Gorth, 2018)The cost of DTP also increased because of the layoffs that were done in the project. The cost of the project also increased because focus was not on offering affordable housing in Nevada but on the costly houses. The affordable housing projects would have helped DTP in attracting investments(Segall, 2018).
Scope As a project manager I believe that the scope of DTP was not defined effectively. The scope of DTP was wide including real estate, construction, art and culture etc. A project with such a large scope requires a structured approach, expertise and knowledge.(Lasvegasweekly, 2018) The scope of project in addition also did not match with the location chosen for the project – Naveda. People in Naveda are not so rich and inspired by a tribal culture. The things seemed to be expensive for community people. The location of the project is one of the important factors that decides success and failure of a project.(Buchanan, 2017).Thescopeof project was as large as revitalizing the city by creating employment opportunities, business opportunities, real estate, technology start-ups, sustainability, innovation mobility etc. This indicates that the project should have been given more time and cost(Archdaily, 2018). Lessons Learned In essence, I can say that as a project manager I would have not preferred to join a disorganized project with such a large scope less time and resources. The DTP project offers number of learning to the present and future project managers and sponsors. Firstly, time and cost of the project should be based on the scope of the project. A project with a large scope like DTP requires more time and resources. Secondly the location of project should be chosen considering the opportunities, development and resources present in the region. Third, scope of the project should not be vague but real that can be achieved in reality. A large project should be managed by an experienced project team. References
Archdaily,2018.ProjectManagementKnowledge.[Online]Availableat: https://www.archdaily.com/286967/downtown-project-a-community-driven-urban-plan-for- las-vegas[Accessed 31 May 2019]. Buchanan, 2017.How Tony Hsieh's $350 Million Bet on Las Vegas Went Down. [Online] Available at:https://www.inc.com/leigh-buchanan/kingdom-of-happiness.html[Accessed 31 May 2019]. Caccamese, A. & Bragantini, D., 2012. Beyond the iron triangle: year zero. InGlobal Congress. 2012—EMEA, Marsailles, France. Newtown Square, PA: Project Management Institute. CNBC, 2018.Zappos CEO Tony Hsieh shares what he would have changed about his $350M downtownLasVegasproject.[Online]Availableat: https://www.cnbc.com/2016/08/09/zappos-ceo-tony-hsieh-what-i-regret-about-pouring-350- million-into-las-vegas.html[Accessed 31 May 2019]. DPTLV, 2019.Welcome to DTP. [Online] Available at:https://dtplv.com/[Accessed 31 May 2019]. dtplv, 2018.Economic Impact Report 2017 – Applied Analysis. [Online] Available at: https://dtplv.com/economic-impact/[Accessed 31 May 2019]. DTPLV, 2019.$350M INVESTMENT. [Online] Available at:https://dtplv.com/breakdown/ [Accessed 31 May 2019]. dtplv, 2019.Core Values. [Online] Available at:https://dtplv.com/culture/[Accessed 31 May 2019]. Evernote,2019.Tony'sDTPPriorities.[Online]Availableat: https://www.evernote.com/shard/s16/client/snv?noteGuid=95ba4292-a2b1-4032-8104- 0673f2fa2f8a¬eKey=e724cb9bbe62c61a&sn=https%3A%2F%2Fwww.evernote.com
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
%2Fshard%2Fs16%2Fsh%2F95ba4292-a2b1-4032-8104-0673f2fa2f8a %2Fe724cb9bbe62c61a&title=Tony%2527s%2BDTP%2BPr[Accessed 31 May 2019]. Gorth, A., 2018.Five years in, Tony Hsieh’s Downtown Project is hardly any closer to being arealcity.[Online]Availableat:https://qz.com/875086/five-years-in-tony-hsiehs- downtown-project-is-hardly-any-closer-to-being-a-real-city/[Accessed 31 May 2019]. Harris, 2014.Joe Downtown: Hsieh says Downtown Project not a charity, can’t solve every communityproblem.[Online]Availableat: https://vegasinc.lasvegassun.com/business/2014/feb/07/joe-downtown-hsieh-says-downtown- project-not-chari/[Accessed 31 May 2019]. Inc, 2018.The Downtown Project: Tony Hsieh's Dream to Revitalize Downtown Las Vegas. [Online]Availableat:https://www.inc.com/trep-life/tony-hsieh-dream-to-revitalize- downtown-las-vegas.html[Accessed 31 May 2019]. lasvegasnevada., 2019.Downtown Las Vegas Open Space & Trails. [Online] Available at: https://www.facebook.com/events/321491151761374 [Accessed 31 May 2019]. Lasvegasweekly, 2018.Joe Downtown: Is Dtp’s Sudden Severing Of Ties With Factorli A SignOf.[Online]Availableat: https://lasvegasweekly.com/column/joe-downtown/2014/aug/13/downtown-project-severs- ties-factorli-larger-issue/[Accessed 31 May 2019]. projectsmart,2011.Understandingtheprojectmanagementtripleconstraint.[Online] Availableat:https://www.projectsmart.co.uk/understanding-the-project-management-triple- constraint.php[Accessed 31 May 2019]. reviewjournal, 2018.Zappos CEO Tony Hsieh’s Downtown Project has new name. [Online] Availableat:https://www.reviewjournal.com/local/local-las-vegas/downtown/zappos-ceo- tony-hsiehs-downtown-project-has-new-name/[Accessed 31 May 2019].
Schoenmann, J., 2017.Tony Hsieh's Downtown Project: A Utopia For Some?[Online] Availableat:https://knpr.org/knpr/2017-02/tony-hsiehs-downtown-project-utopia-some [Accessed 31 May 2019]. Segall, E., 2018.Zappos CEO Tony Hsieh’s Downtown Project has new name. [Online] Availableat:https://www.reviewjournal.com/local/local-las-vegas/downtown/zappos-ceo- tony-hsiehs-downtown-project-has-new-name/[Accessed 31 May 2019]. Southern Naveda Strong, 2014.Downtown North Las Vegas Implemenation Staratgeey Report.[Online]Availableat: http://sns.rtcsnv.com/wp-content/uploads/2016/04/NorthLasVegas_Implementation_Strategie s_Report_120314.pdf [Accessed 31 May 2019]. Vegasinc.lasvegassun., 2019.Joe Downtown: Hsieh says Downtown Project not a charity, can’tsolveeverycommunityproblem.[Online]Availableat: https://vegasinc.lasvegassun.com/business/2014/feb/07/joe-downtown-hsieh-says-downtown- project-not-chari/[Accessed 31 May 2019].