Project Closure Report Project Name:Planning Sessions Based On Collaboration Department:Project Planning and Event Management Focus Area:Managing an event design for OPAIC Product/Process:2 Day Event Design Prepared By Document Owner(s)Project/Organization Role Project ManagerManaging the entire process of the project Event ManagerResponsible for planning for the design of event Site managerResponsible for sanctioning of project plan Confidential 10901379055363883059.docx Last printed on6/1/2004 1:22:00 PM
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Closure Report 1PROJECT CLOSURE REPORT PURPOSE Project Closure Report Purpose The project closure report intends to discuss on the successful achievements of each of the objectives of the project. It would also assure the stakeholders of the project that the project has been able to meet according to the needs of the event. 2PROJECT CLOSURE REPORT GOALS Project Closure Report Goals The project closure report is being created for the following purposes: Review the entire project and validate the accomplishment of milestones. Confirm of outstanding risks, issues and recommendations. Outlining of activities and tasks required for project closure. Identification of future outcomes from the project. 3PROJECT CLOSURE REPORT SUMMARY 3.1Project Background Overview Project Background Overview The project is based on designing a plan for a 2-day event that would be organized at the Dunedin site of OPAIC. On several discussions, it has been discussed that collaboration is one of the most important aspect within the OPAIC philosophy. Hence, each of the academic staffs at all campuses would collaborate for the 2019 term. The event sessions would help in enabling schools to develop separate sessions on planning. They would also discuss about best practices to be incorporated within the Iwi/Maori Corporation. 3.2Project Highlights and Best Practices Project Highlights and Best Practices ConfidentialPage38/30/2024
Project Closure Report Project Highlights: Design a project plan for the 2 day event Determination of cost-benefit and risk analysis Identification of limitations and exclusions from the project Stakeholder Analysis from the project Best Practices: Identification of best standards for event management and food safety standards Ensure a cost-benefit analysis for future outcomes from the project 3.3Project Closure Synopsis Project Closure Synopsis Each of the desired deliverables and objectives have been successfully met The standards of safe work practices and healthy food had been met The cost-benefit analysis had been designed suitably as per the requirements The entire event planning and execution had been successful as per the desired plan ConfidentialPage48/30/2024
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Project Closure Report 4PROJECT METRICS PERFORMANCE 4.1Goals and Objectives Performance Goals and Objectives Performance The goal of the project was to design an event management project that would be able to cover the 2-day event. Each of the project objectives had been defined in order to reach to the successful completion of the project. However, the defined schedules and costs were suitable for the completion of the project. The resources and stakeholders were properly defined and the objectives were met as per defined by the project manager. 4.2Success Criteria Performance Success Criteria Performance The criteria based on meeting the success of the event from the project had met successfully The project manager would be responsible for the continuous evaluation of the project The project sponsor would ensure that each of the necessities of the project should be met properly in order to ensure a successful delivery as per project standards 4.3Milestone and Deliverables Performance Milestones and Deliverables Performance The deliverables of the project were met as per the needed standards The milestones were the defining factors of the successful achievement of each stage of the project. 4.4Schedule Performance Schedule Performance ConfidentialPage58/30/2024
Project Closure Report Project Schedule Overview: The schedule of the project has been designed in order to integrate the plan for the 2 day of events. This schedule defines the costs required at each stage and also discusses the workflow of the project. Project Schedule Control Process: The project schedule would mainly be controlled by the project manager. Any form of discrepancies would be handled by the project manager and thus the necessary steps would be rescheduled within the project. Project Schedule Corrective Actions: The corrective actions based within the project would be handled by the project manager. They would list down the entire changes that would be required for the project and then the needed changes would be performed accordingly. Project Schedule Integration with Managing Project: The integration of the schedule within the project would be helpful for the management of activities concerning the project. 4.5Budget Performance Budget Performance Project Budget Overview: The budget for the project has been set at $63,920. Project Budget Corrective Actions: All the necessary activities for the project had been completed within the estimated budget. 4.6Metrics Performance Recommendations Metrics Performance Recommendations Each of the necessary metrics for the performances within the project have been set as per the criteria of the project. However, there should have been a set metric for each of the steps. This would thus have a massive effect over the performance of the project. ConfidentialPage68/30/2024
Project Closure Report 5PROJECT CLOSURE TASKS 5.1Resource Management Resource Management There were no changes in the needs of the resource within the project. The project resources were allocated their responsibilities for handling of each of their tasks. This was planned during the project planning and scheduling of the project. The Project Knowledge gained from the team members would help during performing of similar projects in the future. This knowledge would help the project managers in underlying of the necessary activities and the set objectives in future project prospects. 5.2Issue Management Issue Management Each of the raised issues would be reported to the senior management level or to the project manager. They would be responsible for understanding the issues and thus resolve them. The issues at each stage would be reported by the team members to the project manager. This would ensure a successful communication between the project team. 5.3Risk Management Risk Management Project Risks Mitigated: The risks based on activity scheduling and finding of proper event management team had been mitigated. Outstanding Project Risks: There were no outstanding risks that might have occurred within the project. 5.4Quality Management Quality Management Quality management had been the topmost priority at every step of the concerning project. There were quality checks at every step of the project. On the achievement of proper quality standards of the project, the project was provided a clear pass to progress on the next steps. The project manager was responsible for handling the quality assurance of each steps of the project. 5.5Communication Management Communication Management ConfidentialPage78/30/2024
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Closure Report There was a high level of communication between the project team and stakeholders involved within the project. The project manager had maintained communication with each of the concerned team members. 5.6Customer Expectation Management Customer Expectation Management The project schedule was defined as per the needs of OPAIC. The project manager had manager the different project steps in order to ensure that the management team at OPAIC were satisfied with the successful delivery of the project. 5.7Asset Management Asset Management Each of the assets such as the items needed during the design of stage, the crockery items for the dinner event would be returned with proper care to the event management team and caterer team. Other project assets would be safely handled and kept securely 5.8Lessons Learned Lessons Learned The scheduling of project activities were proper and as per the needed standards. There should had been a better system for handling of the risks. An agile methodology for project development could had been used. 5.9Postproject Tasks Postproject Tasks The payments to each of the stakeholders and resources should be cleared. The stage should be properly cleaned and each of the materials should be handled with proper care. The project manager should ensure a complete check after the entire place has been cleared and set properly. 5.10Project Closure Recommendations Project Closure Recommendations The project sponsor should ensure that the project has been successfully completed. They should also ensure that the project would fulfills the success criteria’s. They should also collect a feedback from the guests and project stakeholders regarding the project outcomes and future prospects. The documentation of the entire project should be submitted to the Management team at OPAIC and thus the payments to each resource should be cleared accordingly. ConfidentialPage88/30/2024