This presentation discusses the CRM system project for McDonald's, including its rationale, planning, resources, implementation, monitoring, issues, outcomes, conclusion, and recommendations. It includes a work breakdown structure, organization breakdown structure, Gantt chart, PERT, critical path analysis, and variance analysis.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
PROJECT DEVELOPMENT AND
IMPLEMENTATION FOR
STRATEGIC MANAGERS
TASK 5.2

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
RATIONALE OF PROJECT
As company like McDonald is growing at an increasing rate thus, it faces
various issues regarding data management of business.
This calls for the need of CRM system for the organization.
It is a kind of technology that assists in keeping database of employees as
well as customers of business.
This would assist in maintaining database of the firm and act as an aid in
increasing the security of data.
Due to such reason, particular product that is CRM has been selected for
McDonald.
Document Page
INTRODUCTION
Introduction: The product for which Nexus hired Management Consultant is
related with CRM system for McDonalds Company.
Objective
To develop system for appropriate management and storing company's
information.
To ensure data security from unauthorized access.
To minimize data redundancy for effective information management.
To enhance the performance for the achievement of objectives.
Cost: £120000.
Time scales: 2 months.
Resources: financial resources, human resources as well as technological
resources.
Document Page
RESOURCES REQUIRED ALONG WITH
ITS ESTIMATED COST
Technological Resources
Human resources
Financial resources

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
CONT.....
Document Page
CONT....
Document Page
CONT....

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PROJECT SPECIFICATION
Document Page
PLANNING
For the purpose of planning, various activities have been developed. This
includes customer research and competitor research. This is followed by
the analysis of market, customers and business so that need determination
can be done effectively. Later planning is done. Here, idea is selected and
its scope is examined. This is followed by the product development,
suppliers and logistics. Further, the launch of product is done which
includes market testing. At last, sales is forecasted and review of plan is
being done. By performing the activities within set time period, Nexus
Ltd. can attain its set target in an effective manner. Customer as well as
competitor research helps in knowing demand, preferences and needs of
people along with the condition that is prevailing in the market. Later,
with the help of this information, product planning and development can
be done. With the completion of activities within decided time frame, expected
outcomes will be achieved .
Document Page
WORK BREAKDOWN
STRUCTURE

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
ORGANIZATION BREAKDOWN
STRUCTURE
Document Page
GANTT CHART
Document Page
CONT....

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONT....
Document Page
PROJECT COST
Document Page
VARIANCE ANALYSIS
This tool assists in setting budget of the product in
accordance with performance.
Project manager determines the variance between planned
and actual through this.
The estimated cost by project manager is £120000.
However, the actual cost after execution of the plan is
£114400.
It can be determined that the resultant outcome is lower
than planned.
This implies that project manager has allocated the
resources in an appropriate manner.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
IMPLEMENTATION OF THE
PROJECT
Gantt Chart
Critical Path Analysis
Network Diagram
Document Page
PERT
Document Page
CRITICAL PATH ANALYSIS
3-4-5-7-8-9-11-12-13-17-19-21-22-23-25-27-29-30-32-33-34-36-37
and the total duration for project completion is 64 days.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
MEASURES TO MONITOR
PROJECT
Monitoring and evaluation before implementation of project
Monitoring and evaluation after implementation of project
Document Page
MONITORING AND EVALUATION AFTER
IMPLEMENTATION OF PROJECT
PERT
Total quality management
Quality control
Running with planned cost
Document Page
ISSUES TO CRM SYSTEM
Technical Department: In a few areas, recording has been
done through manual process. Due to use of manual process,
project manager faced issue in updating the data and delayed
the entire process. The deadline of the project got delayed
and this also depicts inefficacy about time management.
Quality Management: While measuring the quality, it has
been found out that several quality tools are used at a time.
Efficacy of CRM system was not properly measured due to
lack of proper standards determined for quality. Using
multiple tools created confusion because answers vary in
nature.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
CONT....
Scheduling: Improper scheduling is major issue. Due to
improper scheduling, project manager consumed a few
hours extra. It has enhanced completion time period which
leads to resource capability.
Database management: While implementing the process, a
few things were skipped and were not recorded in the
database. A few processes and activities were not recorded;
hence it created misconception while implementation. It
affects the documentation part and several blocks remained
blanked.
Document Page
OUTCOMES
Evaluating the outcomes of the project, it can be said that positive and feasible results have
been derived yet. Project manager of Nexus ltd has evaluated the outcomes by the application of
varied tools and techniques.
However, in terms of comparing actual and expected outcomes, it can be said that both gives
different values. The expected time determined for the project is two months; however it is
completed within 64 days only; thus it is evident that the project is feasible and suitable for
Nexus ltd. The system proved to be beneficial for Nexus ltd because it has facilitated better
team work and along with the same, employees involved in the project management have also
learned many things.
The estimated budget of the project is £120000; however the project took £114400 amount to
get completed. This depicts that resources have been adequately allocated in all the processes.
Document Page
CONCLUSION
It can be concluded from the above study that project management
and strategic management are interrelated with one another.
The advice which is being offered by management consultant has
assisted in attaining desired set of outcomes in an effective manner.
There is existence of several factors such as cost, time, quality
which plays critical role in the project development.
Existence of resources in right amount is important in successful
implementation of project. This includes the resources such as
human, financial and technical.
After monitoring the project it has been gained that CRM system
project has been implemented within estimated cost, time and
available resources.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
RECOMMENDATIONS
Employees training in order to improve knowledge.
It needs to update its techniques for improving performance and
working culture.
Use of quality tools for enhancing performance this includes tools
such as control charts, six sigma, etc.
Scheduling of activities in Proper manner.
Recording of all the activities with their status, problems occurred,
solutions applied for handling, starting time, etc.
Document Page
REFERENCES
Fan, Y., Thomas, M. and Anantatmula, V., 2014. A
Longitudinal Study of the Required Skills of Project
Managers. The Journal of Modern Project
Management. 1(3).
Garton, C. and McCulloch, E., 2012. Fundamentals of
technology project management. MC Press, LLC.
Lehmann, A. and et.al., 2013. Social aspects for
sustainability assessment of technologies—challenges
for social life cycle assessment (SLCA). The
International Journal of Life Cycle Assessment. 18(8).
pp.1581-1592.
Document Page
THANK YOU!!