Project Development & Implementation for Strategic Managers: Wedding Project
VerifiedAdded on 2023/04/21
|12
|3941
|239
AI Summary
This document provides a comprehensive guide on project development and implementation for strategic managers, focusing on a wedding project. It covers factors for project selection, project specifications, project planning, project implementation, project evaluation, and project closure.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT DEVELOPMENT & IMPLEMENTATION
Project Development & Implementation for Strategic Managers:
Wedding Project
<<Name of the Student>>
<<Student ID>>
<<Name of the University>>
Author’s note:
Project Development & Implementation for Strategic Managers:
Wedding Project
<<Name of the Student>>
<<Student ID>>
<<Name of the University>>
Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT DEVELOPMENT & IMPLEMENTATION
Table of Contents
Introduction......................................................................................................................................2
1. Project Information......................................................................................................................2
1.1 Factors for selection of project..............................................................................................2
1.2 Project Specifications............................................................................................................2
1.3 Agreed project quality...........................................................................................................3
2. Project Planning...........................................................................................................................3
2.1 Project Plan............................................................................................................................3
2.2 Project Resources...................................................................................................................5
2.3 Cost Estimation......................................................................................................................5
2.4 Agreed Timescale..................................................................................................................6
2.5 Project Implementation Strategy...........................................................................................7
3. Project Implementation................................................................................................................7
3.1 Implementation......................................................................................................................7
3.2 Appropriate Measure Identification.......................................................................................8
3.3 Project Monitoring.................................................................................................................8
4. Project Evaluation........................................................................................................................8
4.1 Project Outcomes...................................................................................................................8
4.2 Evaluation of the project outcomes.......................................................................................8
4.3 Recommendations..................................................................................................................9
5. Project Closure.............................................................................................................................9
5.1 Project Procedures.................................................................................................................9
5.2 Project Checklist....................................................................................................................9
Conclusion.......................................................................................................................................9
Bibliography..................................................................................................................................10
Table of Contents
Introduction......................................................................................................................................2
1. Project Information......................................................................................................................2
1.1 Factors for selection of project..............................................................................................2
1.2 Project Specifications............................................................................................................2
1.3 Agreed project quality...........................................................................................................3
2. Project Planning...........................................................................................................................3
2.1 Project Plan............................................................................................................................3
2.2 Project Resources...................................................................................................................5
2.3 Cost Estimation......................................................................................................................5
2.4 Agreed Timescale..................................................................................................................6
2.5 Project Implementation Strategy...........................................................................................7
3. Project Implementation................................................................................................................7
3.1 Implementation......................................................................................................................7
3.2 Appropriate Measure Identification.......................................................................................8
3.3 Project Monitoring.................................................................................................................8
4. Project Evaluation........................................................................................................................8
4.1 Project Outcomes...................................................................................................................8
4.2 Evaluation of the project outcomes.......................................................................................8
4.3 Recommendations..................................................................................................................9
5. Project Closure.............................................................................................................................9
5.1 Project Procedures.................................................................................................................9
5.2 Project Checklist....................................................................................................................9
Conclusion.......................................................................................................................................9
Bibliography..................................................................................................................................10
2PROJECT DEVELOPMENT & IMPLEMENTATION
Introduction
The project of wedding ceremony was formed with the consideration of the innovative
process implication and the implication of the identification of the project issues. The wedding
ceremony project was formed with the modification of the implication and the usage of the
project management tools and options. The completion of the assignment would help in
collecting initial implication required by the stakeholders for understanding the requirements of
the project.
1. Project Inimplication
1.1 Factors for selection of project
The selection of the project is implied with the help of different methods of net present
value, payback period, discounted cash flow, and internal rate of return, benefit to cost ratio,
linear programming, integer programming, dynamic programming, and multiple objective
programming. The economic and technical benefits of the project was accounted for the selection
of the project. The net present value for the project is calculated by the subtraction of the overall
income and expenses of the project. The annual income from the benefit was subtracted by the
annual expenses for estimating the final value of the project. The selection of the project was
estimated by the value of the NPV that means, if the NPV comes to be positive, the project was
selected. The negative value of the NPV would result in the rejection of the project. The payback
period shows the time required for the achievement of the final deliverable for the project. The
time required for the project income to be equal to the project expense. The completion of the
project was marked by the analysis of the time required for the net income and net expense
(considering the discounting factor) was same. The discounted cash flow is the net income and
net expense minus the discounting factor. The net cash flow was helpful for managing the
annualized flow of cash for the project. The internal rate of return was used for the analysis of
the rate required for the returns of the investment. The returns of the rate of the investment was
used for calculating the rate by which the investment of the projects was returned. The
programming part deals with the technical projects and the success of executing the activities for
the project. The linear, integer, and dynamic programming are helpful for the evaluation of the
program management. It is helpful for integrating the successful completion of the project using
the programming facility for estimating the outcome of the projects.
1.2 Project Specifications
The project is formed for the execution of the wedding ceremony of Tony and Peggy Sue
on the date of the 30th June. The wedding ceremony would require planning and use of the
project management tools for the successful modification of the activities. The wedding
ceremony would involve the fixing of the budget, searching for the venue, dress shopping, and
execution of the work for the project. The wedding was implied with the implication of the
efficient modification for the activities. The wedding ceremony was supported by the implication
collection and usage of the improved activities. The involvement of the project specification
formed was formed with the compilation of the successive process implication. The modification
of the improved project work can be implied with the improvement of the innovative activities of
the project. The involvement of the project management activities was helpful for planning
Introduction
The project of wedding ceremony was formed with the consideration of the innovative
process implication and the implication of the identification of the project issues. The wedding
ceremony project was formed with the modification of the implication and the usage of the
project management tools and options. The completion of the assignment would help in
collecting initial implication required by the stakeholders for understanding the requirements of
the project.
1. Project Inimplication
1.1 Factors for selection of project
The selection of the project is implied with the help of different methods of net present
value, payback period, discounted cash flow, and internal rate of return, benefit to cost ratio,
linear programming, integer programming, dynamic programming, and multiple objective
programming. The economic and technical benefits of the project was accounted for the selection
of the project. The net present value for the project is calculated by the subtraction of the overall
income and expenses of the project. The annual income from the benefit was subtracted by the
annual expenses for estimating the final value of the project. The selection of the project was
estimated by the value of the NPV that means, if the NPV comes to be positive, the project was
selected. The negative value of the NPV would result in the rejection of the project. The payback
period shows the time required for the achievement of the final deliverable for the project. The
time required for the project income to be equal to the project expense. The completion of the
project was marked by the analysis of the time required for the net income and net expense
(considering the discounting factor) was same. The discounted cash flow is the net income and
net expense minus the discounting factor. The net cash flow was helpful for managing the
annualized flow of cash for the project. The internal rate of return was used for the analysis of
the rate required for the returns of the investment. The returns of the rate of the investment was
used for calculating the rate by which the investment of the projects was returned. The
programming part deals with the technical projects and the success of executing the activities for
the project. The linear, integer, and dynamic programming are helpful for the evaluation of the
program management. It is helpful for integrating the successful completion of the project using
the programming facility for estimating the outcome of the projects.
1.2 Project Specifications
The project is formed for the execution of the wedding ceremony of Tony and Peggy Sue
on the date of the 30th June. The wedding ceremony would require planning and use of the
project management tools for the successful modification of the activities. The wedding
ceremony would involve the fixing of the budget, searching for the venue, dress shopping, and
execution of the work for the project. The wedding was implied with the implication of the
efficient modification for the activities. The wedding ceremony was supported by the implication
collection and usage of the improved activities. The involvement of the project specification
formed was formed with the compilation of the successive process implication. The modification
of the improved project work can be implied with the improvement of the innovative activities of
the project. The involvement of the project management activities was helpful for planning
3PROJECT DEVELOPMENT & IMPLEMENTATION
project and decoration of the venue. The execution of the wedding was done as an outdoor
wedding with music, food, ceremony, and dance.
1.3 Agreed project quality
The wedding plan was evaluated with the concern time, budget, and event quality for
Tony and Peggy. The time is a major factor as the planning, collection of the resources, and
ceremony execution was helpful for aligning the management of the project completion. The
project was required for being completed on time as the event was held on 30th June. The project
planning and other activities must be completed on time so that the execution of the project was
done in the estimated time. The wedding plan was implied with the inclusion of the improved
work implication. The project quality was analyzed with the consideration that the work was
completed in the estimated time. The couple has an estimated budget that must be considered for
their outdoor wedding. The project quality has been defined with the consideration for the
affective work function modification. The cost of the project is a major concern for the
involvement of the ceremony execution. The project quality management was efficiently implied
with the consideration of the innovative process imlication and formment. The project quality
modification was formed with the compilation of the improved improved and formment.
2. Project Planning
2.1 Project Plan
The project plan for the wedding ceremony has been formed with the modification of the
traditional adaptive process imlication and it was successfully implied with the management of
the activities for the project. The project plan would include the listing of the wedding planning
and ceremony activities as it would incorporate the implication of the smart implementation
activities. The project plan is shown in the table below,
WBS Task Name Duration Start Finish
0 Wedding Ceremony and Reception 181
days Tue 1/1/19 Sun 6/30/19
1 Initial Planning 13 days Tue 1/1/19 Sun 1/13/19
1.1 Selection of the wedding date 1 day Tue 1/1/19 Tue 1/1/19
1.2 Consulting with parents and family members 5 days Wed 1/2/19 Sun 1/6/19
1.3 Fixing budget for the wedding 4 days Mon 1/7/19 Thu 1/10/19
1.4 Hiring a wedding planner 3 days Fri 1/11/19 Sun 1/13/19
1.5 Planning done 0 days Sun 1/13/19 Sun 1/13/19
2 Bookings and Selection 22 days Fri 3/15/19 Fri 4/5/19
2.1 Searching for wedding venue 3 days Fri 3/15/19 Sun 3/17/19
2.2 Booking outdoor wedding venue 3 days Mon 3/18/19 Wed 3/20/19
2.3 Dress Shopping for groom and bride 7 days Thu 3/21/19 Wed 3/27/19
2.4 Booking band for the wedding 4 days Thu 3/28/19 Sun 3/31/19
2.5 Food vendors are hired 5 days Mon 4/1/19 Fri 4/5/19
2.6 Wedding Preparation 0 days Fri 4/5/19 Fri 4/5/19
3 Pre-wedding 40 days Tue 5/21/19 Sat 6/29/19
project and decoration of the venue. The execution of the wedding was done as an outdoor
wedding with music, food, ceremony, and dance.
1.3 Agreed project quality
The wedding plan was evaluated with the concern time, budget, and event quality for
Tony and Peggy. The time is a major factor as the planning, collection of the resources, and
ceremony execution was helpful for aligning the management of the project completion. The
project was required for being completed on time as the event was held on 30th June. The project
planning and other activities must be completed on time so that the execution of the project was
done in the estimated time. The wedding plan was implied with the inclusion of the improved
work implication. The project quality was analyzed with the consideration that the work was
completed in the estimated time. The couple has an estimated budget that must be considered for
their outdoor wedding. The project quality has been defined with the consideration for the
affective work function modification. The cost of the project is a major concern for the
involvement of the ceremony execution. The project quality management was efficiently implied
with the consideration of the innovative process imlication and formment. The project quality
modification was formed with the compilation of the improved improved and formment.
2. Project Planning
2.1 Project Plan
The project plan for the wedding ceremony has been formed with the modification of the
traditional adaptive process imlication and it was successfully implied with the management of
the activities for the project. The project plan would include the listing of the wedding planning
and ceremony activities as it would incorporate the implication of the smart implementation
activities. The project plan is shown in the table below,
WBS Task Name Duration Start Finish
0 Wedding Ceremony and Reception 181
days Tue 1/1/19 Sun 6/30/19
1 Initial Planning 13 days Tue 1/1/19 Sun 1/13/19
1.1 Selection of the wedding date 1 day Tue 1/1/19 Tue 1/1/19
1.2 Consulting with parents and family members 5 days Wed 1/2/19 Sun 1/6/19
1.3 Fixing budget for the wedding 4 days Mon 1/7/19 Thu 1/10/19
1.4 Hiring a wedding planner 3 days Fri 1/11/19 Sun 1/13/19
1.5 Planning done 0 days Sun 1/13/19 Sun 1/13/19
2 Bookings and Selection 22 days Fri 3/15/19 Fri 4/5/19
2.1 Searching for wedding venue 3 days Fri 3/15/19 Sun 3/17/19
2.2 Booking outdoor wedding venue 3 days Mon 3/18/19 Wed 3/20/19
2.3 Dress Shopping for groom and bride 7 days Thu 3/21/19 Wed 3/27/19
2.4 Booking band for the wedding 4 days Thu 3/28/19 Sun 3/31/19
2.5 Food vendors are hired 5 days Mon 4/1/19 Fri 4/5/19
2.6 Wedding Preparation 0 days Fri 4/5/19 Fri 4/5/19
3 Pre-wedding 40 days Tue 5/21/19 Sat 6/29/19
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT DEVELOPMENT & IMPLEMENTATION
3.1 Contacting Cameraman and Video shooter 3 days Tue 5/21/19 Thu 5/23/19
3.2 Sending Invitations to guests 5 days Fri 5/24/19 Tue 5/28/19
3.3 Hiring Solemniser 2 days Wed 5/29/19 Thu 5/30/19
3.4 Making Seating arrangements 8 days Tue 6/11/19 Tue 6/18/19
3.5 Decoration of the venue 5 days Wed 6/19/19 Sun 6/23/19
3.6 Food Arrangements 4 days Mon 6/24/19 Thu 6/27/19
3.7 Cake Booking 2 days Fri 6/28/19 Sat 6/29/19
3.8 Wedding Ceremony Prepared 0 days Sat 6/29/19 Sat 6/29/19
4 Wedding Ceremony 1 day Sun 6/30/19 Sun 6/30/19
4.1 Receiving guests 1 hr Sun 6/30/19 Sun 6/30/19
4.2 Wedding Ceremony including cake cutting 6 hrs Sun 6/30/19 Sun 6/30/19
4.3 Receiving gifts 1 hr Sun 6/30/19 Sun 6/30/19
4.4 Wedding Completion 0 days Sun 6/30/19 Sun 6/30/19
The following is the Gantt chart that can be used for understanding the timeline for the
project schedule,
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Wedding Ceremony and Reception181 days Tue 1/1/19Sun 6/30/19
1 1 Initial Planning 13 days Tue 1/1/19Sun 1/13/19
2 1.1 Selection of the wedding date1 day Tue 1/1/19Tue 1/1/19
3 1.2 Consulting with parents and
family members
5 days Wed
1/2/19
Sun 1/6/19
4 1.3 Fixing budget for the wedding4 days Mon 1/7/19Thu 1/10/19
5 1.4 Hiring a wedding planner 3 days Fri 1/11/19Sun 1/13/19
6 1.5 Planning done 0 days Sun 1/13/19Sun 1/13/19
7 2 Bookings and Selection 22 days Fri 3/15/19Fri 4/5/19
8 2.1 Searching for wedding venue 3 days Fri 3/15/19Sun 3/17/19
9 2.2 Booking outdoor wedding venue3 days Mon 3/18/19Wed 3/20/19
10 2.3 Dress Shopping for groom and bride7 days Thu 3/21/19Wed 3/27/19
11 2.4 Booking band for the wedding4 days Thu 3/28/19Sun 3/31/19
12 2.5 Food vendors are hired 5 days Mon 4/1/19Fri 4/5/19
13 2.6 Wedding Preparation 0 days Fri 4/5/19 Fri 4/5/19
14 3 Pre-wedding 40 days Tue 5/21/19Sat 6/29/19
15 3.1 Contacting Cameraman and
Video shooter
3 days Tue
5/21/19
Thu 5/23/19
16 3.2 Sending Invitations to guests 5 days Fri 5/24/19Tue 5/28/19
17 3.3 Hiring Solemniser 2 days Wed 5/29/19Thu 5/30/19
18 3.4 Making Seating arrangements8 days Tue 6/11/19Tue 6/18/19
19 3.5 Decoration of the venue 5 days Wed 6/19/19Sun 6/23/19
20 3.6 Food Arrangements 4 days Mon 6/24/19Thu 6/27/19
21 3.7 Cake Booking 2 days Fri 6/28/19Sat 6/29/19
22 3.8 Wedding Ceremony Prepared0 days Sat 6/29/19Sat 6/29/19
23 4 Wedding Ceremony 1 day Sun 6/30/19Sun 6/30/19
24 4.1 Receiving guests 1 hr Sun 6/30/19Sun 6/30/19
25 4.2 Wedding Ceremony
including cake cutting
6 hrs Sun
6/30/19
Sun 6/30/19
26 4.3 Receiving gifts 1 hr Sun 6/30/19Sun 6/30/19
27 4.4 Wedding Completion 0 days Sun 6/30/19Sun 6/30/19
Tony and Peggy
Tony and Peggy
Tony and Peggy
Tony and Peggy
1/13
Event Planner,Tony and Peggy
Event Planner
Tony and Peggy,Dress Cost[1]
Band Cost[1]
Food Cost[1]
4/5
Event Planner
Tony and Peggy
Event Planner
Contractor
Contractor
Food Vendor
Cake Cost[1]
6/29
Family & Friends
Solemniser,Camera man,Video Shooter,Ev
Tony and Peggy
6/30
S T M F T S W S T M F T S W S T M F
Dec 16, '18 Jan 13, '19 Feb 10, '19 Mar 10, '19 Apr 7, '19 May 5, '19 Jun 2, '19 Jun 30, '19
3.1 Contacting Cameraman and Video shooter 3 days Tue 5/21/19 Thu 5/23/19
3.2 Sending Invitations to guests 5 days Fri 5/24/19 Tue 5/28/19
3.3 Hiring Solemniser 2 days Wed 5/29/19 Thu 5/30/19
3.4 Making Seating arrangements 8 days Tue 6/11/19 Tue 6/18/19
3.5 Decoration of the venue 5 days Wed 6/19/19 Sun 6/23/19
3.6 Food Arrangements 4 days Mon 6/24/19 Thu 6/27/19
3.7 Cake Booking 2 days Fri 6/28/19 Sat 6/29/19
3.8 Wedding Ceremony Prepared 0 days Sat 6/29/19 Sat 6/29/19
4 Wedding Ceremony 1 day Sun 6/30/19 Sun 6/30/19
4.1 Receiving guests 1 hr Sun 6/30/19 Sun 6/30/19
4.2 Wedding Ceremony including cake cutting 6 hrs Sun 6/30/19 Sun 6/30/19
4.3 Receiving gifts 1 hr Sun 6/30/19 Sun 6/30/19
4.4 Wedding Completion 0 days Sun 6/30/19 Sun 6/30/19
The following is the Gantt chart that can be used for understanding the timeline for the
project schedule,
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Wedding Ceremony and Reception181 days Tue 1/1/19Sun 6/30/19
1 1 Initial Planning 13 days Tue 1/1/19Sun 1/13/19
2 1.1 Selection of the wedding date1 day Tue 1/1/19Tue 1/1/19
3 1.2 Consulting with parents and
family members
5 days Wed
1/2/19
Sun 1/6/19
4 1.3 Fixing budget for the wedding4 days Mon 1/7/19Thu 1/10/19
5 1.4 Hiring a wedding planner 3 days Fri 1/11/19Sun 1/13/19
6 1.5 Planning done 0 days Sun 1/13/19Sun 1/13/19
7 2 Bookings and Selection 22 days Fri 3/15/19Fri 4/5/19
8 2.1 Searching for wedding venue 3 days Fri 3/15/19Sun 3/17/19
9 2.2 Booking outdoor wedding venue3 days Mon 3/18/19Wed 3/20/19
10 2.3 Dress Shopping for groom and bride7 days Thu 3/21/19Wed 3/27/19
11 2.4 Booking band for the wedding4 days Thu 3/28/19Sun 3/31/19
12 2.5 Food vendors are hired 5 days Mon 4/1/19Fri 4/5/19
13 2.6 Wedding Preparation 0 days Fri 4/5/19 Fri 4/5/19
14 3 Pre-wedding 40 days Tue 5/21/19Sat 6/29/19
15 3.1 Contacting Cameraman and
Video shooter
3 days Tue
5/21/19
Thu 5/23/19
16 3.2 Sending Invitations to guests 5 days Fri 5/24/19Tue 5/28/19
17 3.3 Hiring Solemniser 2 days Wed 5/29/19Thu 5/30/19
18 3.4 Making Seating arrangements8 days Tue 6/11/19Tue 6/18/19
19 3.5 Decoration of the venue 5 days Wed 6/19/19Sun 6/23/19
20 3.6 Food Arrangements 4 days Mon 6/24/19Thu 6/27/19
21 3.7 Cake Booking 2 days Fri 6/28/19Sat 6/29/19
22 3.8 Wedding Ceremony Prepared0 days Sat 6/29/19Sat 6/29/19
23 4 Wedding Ceremony 1 day Sun 6/30/19Sun 6/30/19
24 4.1 Receiving guests 1 hr Sun 6/30/19Sun 6/30/19
25 4.2 Wedding Ceremony
including cake cutting
6 hrs Sun
6/30/19
Sun 6/30/19
26 4.3 Receiving gifts 1 hr Sun 6/30/19Sun 6/30/19
27 4.4 Wedding Completion 0 days Sun 6/30/19Sun 6/30/19
Tony and Peggy
Tony and Peggy
Tony and Peggy
Tony and Peggy
1/13
Event Planner,Tony and Peggy
Event Planner
Tony and Peggy,Dress Cost[1]
Band Cost[1]
Food Cost[1]
4/5
Event Planner
Tony and Peggy
Event Planner
Contractor
Contractor
Food Vendor
Cake Cost[1]
6/29
Family & Friends
Solemniser,Camera man,Video Shooter,Ev
Tony and Peggy
6/30
S T M F T S W S T M F T S W S T M F
Dec 16, '18 Jan 13, '19 Feb 10, '19 Mar 10, '19 Apr 7, '19 May 5, '19 Jun 2, '19 Jun 30, '19
5PROJECT DEVELOPMENT & IMPLEMENTATION
2.2 Project Resources
The project of Wedding Ceremony would include the use of the human and material
resources for the project. The combination of the human and material resources was helpful for
the achievement of the efficient process imlication. The project resources required for the
completion of the wedding ceremony were,
Resource Name Type Initials Max. Units Std. Rate
Event Planner Human EP 100% RM140.00/hr
Contractor Human C 100% RM120.00/hr
Food Vendor Human FV 100% RM110.00/hr
Solemniser Human S 100% RM100.00/hr
Camera man Human CM 100% RM80.00/hr
Video Shooter Human VS 100% RM90.00/hr
Dress Cost Material DC RM1,250.00
Band Cost Material BC RM2,000.00
Food Cost Material FC RM5,500.00
Cake Cost Material CC RM470.00
The use of the human and material resources was responsible for the modification of the
efficient and implied improved management. The human resources would take care of the work
required for planning and execution of the project activities and the material resources would
deploy the tool required for the completion of the project activities. The wedding ceremony
would require these resources for planning, operations, decorations, and ceremony execution for
the project.
2.3 Cost Estimation
The cost estimation for the project of wedding ceremony was done on behalf of the
efficient modification of the activities and the usage of the resources. The bottom up estimation
has been done for aligning the implication of the innovative and successive work. The estimation
of the project costs was formed with the help of the estimation using usage and standard rates.
The calculation would sum the money required for the budget by calculating the usage of each of
the resources and multiplying it with the standard costs for the project.
Resource Name Type Work Standard Rate Cost
Event Planner Work 94 hrs RM140.00/hr RM13,160.00
Contractor Work 104 hrs RM120.00/hr RM12,480.00
2.2 Project Resources
The project of Wedding Ceremony would include the use of the human and material
resources for the project. The combination of the human and material resources was helpful for
the achievement of the efficient process imlication. The project resources required for the
completion of the wedding ceremony were,
Resource Name Type Initials Max. Units Std. Rate
Event Planner Human EP 100% RM140.00/hr
Contractor Human C 100% RM120.00/hr
Food Vendor Human FV 100% RM110.00/hr
Solemniser Human S 100% RM100.00/hr
Camera man Human CM 100% RM80.00/hr
Video Shooter Human VS 100% RM90.00/hr
Dress Cost Material DC RM1,250.00
Band Cost Material BC RM2,000.00
Food Cost Material FC RM5,500.00
Cake Cost Material CC RM470.00
The use of the human and material resources was responsible for the modification of the
efficient and implied improved management. The human resources would take care of the work
required for planning and execution of the project activities and the material resources would
deploy the tool required for the completion of the project activities. The wedding ceremony
would require these resources for planning, operations, decorations, and ceremony execution for
the project.
2.3 Cost Estimation
The cost estimation for the project of wedding ceremony was done on behalf of the
efficient modification of the activities and the usage of the resources. The bottom up estimation
has been done for aligning the implication of the innovative and successive work. The estimation
of the project costs was formed with the help of the estimation using usage and standard rates.
The calculation would sum the money required for the budget by calculating the usage of each of
the resources and multiplying it with the standard costs for the project.
Resource Name Type Work Standard Rate Cost
Event Planner Work 94 hrs RM140.00/hr RM13,160.00
Contractor Work 104 hrs RM120.00/hr RM12,480.00
6PROJECT DEVELOPMENT & IMPLEMENTATION
Food Vendor Work 32 hrs RM110.00/hr RM3,520.00
Solemniser Work 6 hrs RM100.00/hr RM600.00
Camera man Work 6 hrs RM80.00/hr RM480.00
Video Shooter Work 6 hrs RM90.00/hr RM540.00
Dress Cost Material 1 RM1,250.00 RM1,250.00
Band Cost Material 1 RM2,000.00 RM2,000.00
Food Cost Material 1 RM5,500.00 RM5,500.00
Cake Cost Material 1 RM470.00 RM470.00
2.4 Agreed Timescale
The agreed timescale for the project of wedding ceremony would include the following
project schedule and the time duration show,
WBS Task Name Duration Start Finish
0 Wedding Ceremony and Reception 181 days Tue 1/1/19 Sun 6/30/19
1 Initial Planning 13 days Tue 1/1/19 Sun 1/13/19
1.1 Selection of the wedding date 1 day Tue 1/1/19 Tue 1/1/19
1.2 Consulting with parents and family
members 5 days Wed 1/2/19 Sun 1/6/19
1.3 Fixing budget for the wedding 4 days Mon 1/7/19 Thu 1/10/19
1.4 Hiring a wedding planner 3 days Fri 1/11/19 Sun 1/13/19
1.5 Planning done 0 days Sun 1/13/19 Sun 1/13/19
2 Bookings and Selection 22 days Fri 3/15/19 Fri 4/5/19
2.1 Searching for wedding venue 3 days Fri 3/15/19 Sun 3/17/19
2.2 Booking outdoor wedding venue 3 days Mon
3/18/19 Wed 3/20/19
2.3 Dress Shopping for groom and bride 7 days Thu 3/21/19 Wed 3/27/19
2.4 Booking band for the wedding 4 days Thu 3/28/19 Sun 3/31/19
2.5 Food vendors are hired 5 days Mon 4/1/19 Fri 4/5/19
2.6 Wedding Preparation 0 days Fri 4/5/19 Fri 4/5/19
3 Pre-wedding 40 days Tue 5/21/19 Sat 6/29/19
3.1 Contacting Cameraman and Video shooter 3 days Tue 5/21/19 Thu 5/23/19
3.2 Sending Invitations to guests 5 days Fri 5/24/19 Tue 5/28/19
3.3 Hiring Solemniser 2 days Wed
5/29/19 Thu 5/30/19
3.4 Making Seating arrangements 8 days Tue 6/11/19 Tue 6/18/19
3.5 Decoration of the venue 5 days Wed Sun 6/23/19
Food Vendor Work 32 hrs RM110.00/hr RM3,520.00
Solemniser Work 6 hrs RM100.00/hr RM600.00
Camera man Work 6 hrs RM80.00/hr RM480.00
Video Shooter Work 6 hrs RM90.00/hr RM540.00
Dress Cost Material 1 RM1,250.00 RM1,250.00
Band Cost Material 1 RM2,000.00 RM2,000.00
Food Cost Material 1 RM5,500.00 RM5,500.00
Cake Cost Material 1 RM470.00 RM470.00
2.4 Agreed Timescale
The agreed timescale for the project of wedding ceremony would include the following
project schedule and the time duration show,
WBS Task Name Duration Start Finish
0 Wedding Ceremony and Reception 181 days Tue 1/1/19 Sun 6/30/19
1 Initial Planning 13 days Tue 1/1/19 Sun 1/13/19
1.1 Selection of the wedding date 1 day Tue 1/1/19 Tue 1/1/19
1.2 Consulting with parents and family
members 5 days Wed 1/2/19 Sun 1/6/19
1.3 Fixing budget for the wedding 4 days Mon 1/7/19 Thu 1/10/19
1.4 Hiring a wedding planner 3 days Fri 1/11/19 Sun 1/13/19
1.5 Planning done 0 days Sun 1/13/19 Sun 1/13/19
2 Bookings and Selection 22 days Fri 3/15/19 Fri 4/5/19
2.1 Searching for wedding venue 3 days Fri 3/15/19 Sun 3/17/19
2.2 Booking outdoor wedding venue 3 days Mon
3/18/19 Wed 3/20/19
2.3 Dress Shopping for groom and bride 7 days Thu 3/21/19 Wed 3/27/19
2.4 Booking band for the wedding 4 days Thu 3/28/19 Sun 3/31/19
2.5 Food vendors are hired 5 days Mon 4/1/19 Fri 4/5/19
2.6 Wedding Preparation 0 days Fri 4/5/19 Fri 4/5/19
3 Pre-wedding 40 days Tue 5/21/19 Sat 6/29/19
3.1 Contacting Cameraman and Video shooter 3 days Tue 5/21/19 Thu 5/23/19
3.2 Sending Invitations to guests 5 days Fri 5/24/19 Tue 5/28/19
3.3 Hiring Solemniser 2 days Wed
5/29/19 Thu 5/30/19
3.4 Making Seating arrangements 8 days Tue 6/11/19 Tue 6/18/19
3.5 Decoration of the venue 5 days Wed Sun 6/23/19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT DEVELOPMENT & IMPLEMENTATION
6/19/19
3.6 Food Arrangements 4 days Mon
6/24/19 Thu 6/27/19
3.7 Cake Booking 2 days Fri 6/28/19 Sat 6/29/19
3.8 Wedding Ceremony Prepared 0 days Sat 6/29/19 Sat 6/29/19
4 Wedding Ceremony 1 day Sun 6/30/19 Sun 6/30/19
4.1 Receiving guests 1 hr Sun 6/30/19 Sun 6/30/19
4.2 Wedding Ceremony including cake cutting 6 hrs Sun 6/30/19 Sun 6/30/19
4.3 Receiving gifts 1 hr Sun 6/30/19 Sun 6/30/19
4.4 Wedding Completion 0 days Sun 6/30/19 Sun 6/30/19
January 2019 February 2019 March 2019 April 2019 May 2019 June 2019
0 hrs
100 hrs
200 hrs
300 hrs
400 hrs
500 hrs
600 hrs
104 hrs 104 hrs
232 hrs
232 hrs
312 hrs
486 hrs
Cumulative Work Remaining Cumulative Work
2.5 Project Implementation Strategy
The project implementation strategy would involve the usage of the efficient and smart
work formment along with the implication of the improved improved formment. The
implementation of the project was formed with the usage of the adaptive process imlication and
the implication of the improved improved and formment. The implementation of the activities
for the project was supported by the use of the adaptive project management methodology. The
implementation of the project activities was aligned with the usage of the innovative and
efficient process imlication. The project implementation strategy was formed with the
implication of the efficient strategy modification. The project has been divided into 4 phases
namely initiation, resource accumulation, formment, and execution. The initiation phase would
involve the analysis of the requirements for the project. The implementation of the project
activities had successfully formed with the implication of the implied formment management.
The implementation strategy was formed with the implication formment for the activities. The
usage of the implementation strategy is formed with the implication of the successive
management.
6/19/19
3.6 Food Arrangements 4 days Mon
6/24/19 Thu 6/27/19
3.7 Cake Booking 2 days Fri 6/28/19 Sat 6/29/19
3.8 Wedding Ceremony Prepared 0 days Sat 6/29/19 Sat 6/29/19
4 Wedding Ceremony 1 day Sun 6/30/19 Sun 6/30/19
4.1 Receiving guests 1 hr Sun 6/30/19 Sun 6/30/19
4.2 Wedding Ceremony including cake cutting 6 hrs Sun 6/30/19 Sun 6/30/19
4.3 Receiving gifts 1 hr Sun 6/30/19 Sun 6/30/19
4.4 Wedding Completion 0 days Sun 6/30/19 Sun 6/30/19
January 2019 February 2019 March 2019 April 2019 May 2019 June 2019
0 hrs
100 hrs
200 hrs
300 hrs
400 hrs
500 hrs
600 hrs
104 hrs 104 hrs
232 hrs
232 hrs
312 hrs
486 hrs
Cumulative Work Remaining Cumulative Work
2.5 Project Implementation Strategy
The project implementation strategy would involve the usage of the efficient and smart
work formment along with the implication of the improved improved formment. The
implementation of the project was formed with the usage of the adaptive process imlication and
the implication of the improved improved and formment. The implementation of the activities
for the project was supported by the use of the adaptive project management methodology. The
implementation of the project activities was aligned with the usage of the innovative and
efficient process imlication. The project implementation strategy was formed with the
implication of the efficient strategy modification. The project has been divided into 4 phases
namely initiation, resource accumulation, formment, and execution. The initiation phase would
involve the analysis of the requirements for the project. The implementation of the project
activities had successfully formed with the implication of the implied formment management.
The implementation strategy was formed with the implication formment for the activities. The
usage of the implementation strategy is formed with the implication of the successive
management.
8PROJECT DEVELOPMENT & IMPLEMENTATION
3. Project Implementation
3.1 Implementation
The implementation of the wedding ceremony project would involve the implication of
the wedding activities and activities. The project of wedding ceremony would ensure that the
operations for the project is completed and there is no option for implying the activities. The
implementation using the adaptive work can imply the implication of the activities. The
implementation of the project was formed with the usage of the adaptive process imlication and
the implication of the improved improved and formment. The implementation of the activities
for the project was supported by the use of the adaptive project management methodology. The
implementation of the project activities was aligned with the usage of the innovative and
efficient process imlication. The project implementation strategy was formed with the
implication of the efficient strategy modification. The project has been divided into 4 phases
namely initiation, resource accumulation, formment, and execution. The initiation phase would
involve the analysis of the requirements for the project. The implementation of the project
activities had successfully formed with the implication of the implied formment management.
The implementation strategy was formed with the implication formment for the activities
3.2 Appropriate Measure Identification
The appropriate project measure was implied with the concern time, budget, and event
quality for the client. The time is a major factor as the planning, collection of the resources, and
ceremony execution was helpful for aligning the management of the project completion. The cost
of the project is a major concern for the involvement of the ceremony execution. The project
quality management was efficiently implied with the consideration of the innovative process
imlication and formment.
3.3 Project Monitoring
The monitoring of the project was done by using efficient and improved word
modification using the tools like checklist, status reporting, and progress analysis. The project of
wedding ceremony would ensure that the operations for the project is completed and there is no
option for implying the activities. The project implementation strategy was formed with the
implication of the efficient strategy modification. The project has been divided into 4 phases
namely initiation, resource accumulation, formment, and execution. The milestone achievement
for each of the phases was marked for understanding the progress of the project.
4. Project Evaluation
4.1 Project Outcomes
The completion of the project would result in forming the execution of the wedding
ceremony for Tony and Peggy. It was the final outcome of the project.
4.2 Evaluation of the project outcomes
The wedding plan was evaluated with the concern time, budget, and event quality for
Tony and Peggy. The time is a major factor as the planning, collection of the resources, and
ceremony execution was helpful for aligning the management of the project completion. The
3. Project Implementation
3.1 Implementation
The implementation of the wedding ceremony project would involve the implication of
the wedding activities and activities. The project of wedding ceremony would ensure that the
operations for the project is completed and there is no option for implying the activities. The
implementation using the adaptive work can imply the implication of the activities. The
implementation of the project was formed with the usage of the adaptive process imlication and
the implication of the improved improved and formment. The implementation of the activities
for the project was supported by the use of the adaptive project management methodology. The
implementation of the project activities was aligned with the usage of the innovative and
efficient process imlication. The project implementation strategy was formed with the
implication of the efficient strategy modification. The project has been divided into 4 phases
namely initiation, resource accumulation, formment, and execution. The initiation phase would
involve the analysis of the requirements for the project. The implementation of the project
activities had successfully formed with the implication of the implied formment management.
The implementation strategy was formed with the implication formment for the activities
3.2 Appropriate Measure Identification
The appropriate project measure was implied with the concern time, budget, and event
quality for the client. The time is a major factor as the planning, collection of the resources, and
ceremony execution was helpful for aligning the management of the project completion. The cost
of the project is a major concern for the involvement of the ceremony execution. The project
quality management was efficiently implied with the consideration of the innovative process
imlication and formment.
3.3 Project Monitoring
The monitoring of the project was done by using efficient and improved word
modification using the tools like checklist, status reporting, and progress analysis. The project of
wedding ceremony would ensure that the operations for the project is completed and there is no
option for implying the activities. The project implementation strategy was formed with the
implication of the efficient strategy modification. The project has been divided into 4 phases
namely initiation, resource accumulation, formment, and execution. The milestone achievement
for each of the phases was marked for understanding the progress of the project.
4. Project Evaluation
4.1 Project Outcomes
The completion of the project would result in forming the execution of the wedding
ceremony for Tony and Peggy. It was the final outcome of the project.
4.2 Evaluation of the project outcomes
The wedding plan was evaluated with the concern time, budget, and event quality for
Tony and Peggy. The time is a major factor as the planning, collection of the resources, and
ceremony execution was helpful for aligning the management of the project completion. The
9PROJECT DEVELOPMENT & IMPLEMENTATION
project was required for being completed on time as the event was held on 30th June. The project
planning and other activities must be completed on time so that the execution of the project was
done in the estimated time. The wedding plan was implied with the inclusion of the improved
work implication. The project outcomes was analyzed with the consideration that the work was
completed in the estimated time. The couple has an estimated budget that must be considered for
their outdoor wedding. The project outcomes has been defined with the consideration for the
affective work function modification. The cost of the project is a major concern for the
involvement of the ceremony execution. The project outcomes management was efficiently
implied with the consideration of the innovative process imlication and formment. The project
outcomes modification was formed with the compilation of the improved improved and
formment.
4.3 Recommendations
The usage of the appropriate project management methodology like SDLC, risk
assessment processes, cost estimation, and implication of the processes was helpful for making
the work completed. The tools can be helpful for ensuring that the work was implied with the
usage of the innovative work completion.
5. Project Closure
5.1 Project Procedures
The project procedures would include the activities of Selection of the wedding date,
Consulting with parents and family members, Fixing budget for the wedding, Hiring a wedding
planner, Searching for wedding venue, Booking outdoor wedding venue, Dress Shopping for
groom and bride, Booking band for the wedding, Food vendors are hired, Contacting
Cameraman and Video shooter, Sending Invitations to guests, Hiring Solemniser, Making
Seating arrangements, Decoration of the venue, Food Arrangements, Cake Booking, Receiving
guests, Wedding Ceremony including cake cutting, and Receiving gifts.
5.2 Project Checklist
Checklist Item Check
Project plan made ✓
Cost estimation
done
✓
Work division ✓
Resources analyzed ✓
Project completed ✓
Conclusion
It can be concluded from the report that the implication of the project management
techniques and tools had been helpful for the execution of the Wedding Ceremony. The use of
the project management activities and implication of the innovative work implication had helped
in forming the management of the project. The use of the MS-Project for forming the schedule,
cost estimation, and risk management had aligned the implication of the efficient and innovative
project was required for being completed on time as the event was held on 30th June. The project
planning and other activities must be completed on time so that the execution of the project was
done in the estimated time. The wedding plan was implied with the inclusion of the improved
work implication. The project outcomes was analyzed with the consideration that the work was
completed in the estimated time. The couple has an estimated budget that must be considered for
their outdoor wedding. The project outcomes has been defined with the consideration for the
affective work function modification. The cost of the project is a major concern for the
involvement of the ceremony execution. The project outcomes management was efficiently
implied with the consideration of the innovative process imlication and formment. The project
outcomes modification was formed with the compilation of the improved improved and
formment.
4.3 Recommendations
The usage of the appropriate project management methodology like SDLC, risk
assessment processes, cost estimation, and implication of the processes was helpful for making
the work completed. The tools can be helpful for ensuring that the work was implied with the
usage of the innovative work completion.
5. Project Closure
5.1 Project Procedures
The project procedures would include the activities of Selection of the wedding date,
Consulting with parents and family members, Fixing budget for the wedding, Hiring a wedding
planner, Searching for wedding venue, Booking outdoor wedding venue, Dress Shopping for
groom and bride, Booking band for the wedding, Food vendors are hired, Contacting
Cameraman and Video shooter, Sending Invitations to guests, Hiring Solemniser, Making
Seating arrangements, Decoration of the venue, Food Arrangements, Cake Booking, Receiving
guests, Wedding Ceremony including cake cutting, and Receiving gifts.
5.2 Project Checklist
Checklist Item Check
Project plan made ✓
Cost estimation
done
✓
Work division ✓
Resources analyzed ✓
Project completed ✓
Conclusion
It can be concluded from the report that the implication of the project management
techniques and tools had been helpful for the execution of the Wedding Ceremony. The use of
the project management activities and implication of the innovative work implication had helped
in forming the management of the project. The use of the MS-Project for forming the schedule,
cost estimation, and risk management had aligned the implication of the efficient and innovative
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT DEVELOPMENT & IMPLEMENTATION
work listing. The use of the project implementation plan would support the modification of the
activities and forming the formment of the successive work implementation plan.
work listing. The use of the project implementation plan would support the modification of the
activities and forming the formment of the successive work implementation plan.
11PROJECT DEVELOPMENT & IMPLEMENTATION
Bibliography
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project
Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and
technology. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Bibliography
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project
Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and
technology. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.