Project Evaluation Report on Cinnamon Spices Australia

   

Added on  2022-08-11

3 Pages815 Words22 Views
 | 
 | 
 | 
BSBPMG522 Undertake project work Project Evaluation Report template
Cinnamon Spices Australia
Project Evaluation Report
Reason for Closing the Project
The project that undertakes website development work gets closed as the project achieves
its aims. The website that is developed includes all the important features that are required
for attracting customers. In addition to this, the developed website will be helpful in
enhancing sales as well as assists in expanding the market of the organization. As the work
of the project gets completed therefore the project manger signs off the project and releases
the resources by effectively closing the project.
Highlights and Innovations
The innovations that are mainly done while developing the website for Cinnamon Spices
Australia are listed below:
The design of the website is done with Kultur that is mainly helpful in creating
different types of innovative graphics and the use of impressive portfolio helps the
website in looking dazzling.
Continuously creating new types of work in order to make improvement and for
meeting different types of user needs as well as requirements.
Summary of Recommendations.
The entire project must be tracked on a regular basis for making sure that the project
objectives can be successfully achieved. In addition to this, the operations manager needs to
check the performance of the project properly in order to analyze the completion date of the
project so that the project can be closed effectively on time. Furthermore, it is necessary to
hire experienced project managers as well as team members for effectively completing the
work of the project.
Performance against Objectives
It is found that the actual performance of the project generally varies against the planned
performance of the project which is mainly shown in the below table.
Project activities Planned completion date Actual completion date
Coding 08-04-2020 12-04-2020
Validation of code 13-04-2020 17-04-2020
Database development 21-04-2020 24-04-2020
Testing 24-04-2020 30-04-2020
The above tables reflect that the time that is estimated for the completion of the activities is
not properly estimated and as a result the completion date of the project varies. In addition to
this, the budget that is necessary for website development can get increased.
© 2017 J&S Learning Work and Eduworks Resources 1
Project Evaluation Report on Cinnamon Spices Australia_1

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Cinnamon Spices Australia Project Evaluation Report 2022
|3
|775
|13

Project Scope of Cinnamon Spices Australia
|4
|913
|20

BSBPMG522 Undertake Project Work
|3
|476
|20

Development of Website for Cinnamon Spices Australia
|3
|460
|51

Project Management Plan of Cinnamon Spices Australia
|5
|991
|25

Website Development Project for Native Bush Spices Australia
|5
|799
|123