Running Head: PROJECT MANAGEMENT
Project Management
Name of the Student
Name of the University

1PROJECT MANAGEMENT
Table of Contents
A. Project Initiation Document........................................................................................................2
1. Project Background.................................................................................................................2
2. Budgetary Information.............................................................................................................2
3. Timescales...............................................................................................................................4
4. Objectives................................................................................................................................6
5. Approach..................................................................................................................................6
6. Key Staff..................................................................................................................................6
7. Stakeholder Analysis...............................................................................................................7
B. Work Breakdown Structure........................................................................................................7
Bibliography..................................................................................................................................11

2PROJECT MANAGEMENT
A. Project Initiation Document
1. Project Background
The project involves preparation for hosting an inter-university games (like Olympics) in
which 10 Higher Education Universities (HEIs) are expected to take part. QAHE has decided to
offer a budget of £20k for conducting the entire preparations for the event along with one
academic year time. The event will be hosted in a selected indoor stadium in Manchester.
2. Budgetary Information
The main budget requirements include the wages of the project stakeholders and team
members as well as fixed costs for resources. The unit costs are shown in the following table.
Resource Name Type Max. Units Std. Rate
Project Manager Work 100% £5.00/hr
Project Supervisor Work 100% £3.00/hr
Marketing Manager Work 100% £3.00/hr
Contractor Work 100% £2.00/hr
Workers Work 100% £10.00/hr
Decorations and Other Material Resources Material £4,000.00
Allocating these resources in the work breakdown structure, the total cost breakdown and
the budget can be determined as shown in the following table.
WB
S Task Name Duration Resource Names Cost
0 Preparing and Hosting HEI Games 268 days £17,624.0
0
1 Requirement Analysis and Discussions 33 days £904.00
1.1 Team Meeting 7 days £280.00

3PROJECT MANAGEMENT
1.1.1 Call meeting among team members 1 day Project Manager £40.00
1.1.2 Discuss the goals and objectives of the project 1 day Project Manager £40.00
1.1.3 Discuss budget requirements and time for preparation 1 day Project Manager £40.00
1.1.4 Discuss various requirements to fulfil while working for the
project 1 day Project Manager £40.00
1.1.5 Make various considerations for the project 2 days Project Manager £80.00
1.1.6 Discuss stakeholder roles in the project 1 day Project Manager £40.00
1.2 Feasibility Analysis 15 days £360.00
1.2.1 Analysis of Requirements 2 days Project Supervisor £48.00
1.2.2 Conduct feasibility test on the project 4 days Project Supervisor £96.00
1.2.3 Conduct cost benefit analysis 4 days Project Supervisor £96.00
1.2.4 Submit feasibility report 5 days Project Supervisor £120.00
1.3 Prepare project proposal 10 days Project Supervisor £240.00
1.4 Submit proposal to supervisor 1 day Project Supervisor £24.00
1.5 Receive approval for proceeding with the plan 0 days £0.00
2 Project Planning 35 days £1,080.00
2.1 Project Charter Development 15 days £600.00
2.1.1 Defining project scope 4 days Project Manager £160.00
2.1.2 Determine aims and objectives of the project 4 days Project Manager £160.00
2.1.3 Specify project timeline 3 days Project Manager £120.00
2.1.4 Estimate project budget 4 days Project Manager £160.00
2.2 Risk Management 20 days £480.00
2.2.1 Identify risks in the project 10 days Project Supervisor £240.00
2.2.2 Develop risk management plan 10 days Project Supervisor £240.00
2.3 Finalise the project plan 0 days £0.00
3 Project Execution 165 days £14,480.0
0
3.1 Invitations 35 days £840.00
3.1.1 Prepare invitation cards 15 days Marketing Manager £360.00
3.1.2 Send invitations to universities 5 days Marketing Manager £120.00

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Cost Management Assignment: Construction Project
|8
|1130
|56

Project Management Assignment 3: OSFMS
|20
|2287
|409

Installation of Assembly Line of Packaging Machines - Work Breakdown Structure, Dependency Matrix, AOA Network, and Gantt Chart Plan
|16
|2119
|313

Inventory Management System for Clothing Store
|14
|1833
|402

Construction of Entertainment Venue at Viharamahadevi Park - Project Management
|19
|2893
|328

Project Management - Desklib
|20
|3477
|163