Running Head: PROJECT MANAGEMENT Project Management Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT Answer to 1 In order to remove resource over-allocation, some of the resources were changed in a number of activities. After removing over-allocated resources, alternative resources were added in the activities who will be able to do the work as the previous resource. For example, one of the activities was found that could be done by project analyst and hence, project manager was replaced by analyst in the activity. In one task, one new resource was added – risk manager. This is because the allocated resource could not be replaced by any other resource and hence, a new and necessary resource was added. Answer to 2 The critical path did not change as the durations of the work packages were kept intact. Answer to 3 The following series of has the highest cost in the project. Task NameDurationResource NamesCost Planning98 days$118,080.00 Scope Planning51 days$38,320.00 Requirements40 days$30,320.00 Develop/finalize16 daysSeniorSystemsTest$10,240.00
4PROJECT MANAGEMENT Finalize communications management plan 3 daysProject Analyst$1,800.00 Finalizeprocurement management plan 9 daysContracts Analyst$3,240.00 Finalizestakeholder management plan 2 daysProject Manager$1,600.00 Finalizeproject schedule/cost baseline 10 daysProject Analyst$6,000.00 Finalize project plan6 daysProject Manager$4,800.00 Obtain approval for project plan 5 daysProject Manager$4,000.00 Answer to 4 The total project cost is $253,480. The detailed breakdown is shown in the following table. Task NameCost TECHNOLOGY REFRESH PROJECT$253,480.00 Initiating$22,160.00
7PROJECT MANAGEMENT Finalize communications management plan$1,800.00 Finalize procurement management plan$3,240.00 Finalize stakeholder management plan$1,600.00 Finalize project schedule/cost baseline$6,000.00 Finalize project plan$4,800.00 Obtain approval for project plan$4,000.00 Executing$68,760.00 Hardware$5,280.00 Procure hardware from suppliers$5,280.00 Software$12,960.00 Obtain software OS licenses$5,280.00 Obtain software application licenses$7,680.00 Pilot Testing$4,640.00 Setup test area$1,320.00 Load software onto pilot machines$1,320.00 Validate functionality$2,000.00
8PROJECT MANAGEMENT Deployment$23,800.00 Configure production hardware$8,640.00 Deploy production hardware$7,680.00 Load software to deployed hardware$7,480.00 Testing$10,880.00 Validate startup on deployed hardware$2,400.00 Perform OS testing$3,200.00 Perform application testing$5,280.00 Obtain formal sign-off from users$11,200.00 Monitoring and Controlling$22,400.00 Formal Customer Review 1$6,400.00 Hold formal customer review after project plan approval $1,600.00 Update project plan$4,800.00 Formal Customer Review 2$16,000.00
9PROJECT MANAGEMENT Obtain updates regarding key deliverables from project team $9,600.00 Hold formal customer review after pilot testing$1,600.00 Update project plan$4,800.00 Closing$22,080.00 External$17,080.00 Finalize procurement with suppliers$4,680.00 Customer Approval$12,400.00 Hold final customer review$1,600.00 Prepare/submit final customer report$3,600.00 Audit against contractual deliverables$4,800.00 Obtain final customer approval$2,400.00 Internal$5,000.00 Hold lessons learned meeting$600.00 Update final internal report$3,600.00 Hold project team celebration event$800.00