University Project: Management Plan for Caffeine Bean Café Shop

Verified

Added on  2022/08/14

|6
|583
|10
Project
AI Summary
This project management assignment presents a detailed plan for establishing a successful coffee shop, the Caffeine Bean Café Shop. The project encompasses various phases, starting with initiation, which includes research, business case development, and defining project vision. The planning phase focuses on site selection, registration, supplier identification, and marketing strategies. The execution phase covers building modifications, equipment installation, and adherence to local regulations. Finally, the project closure phase involves post-project review and stakeholder sign-off. The assignment includes a Work Breakdown Structure (WBS) outlining tasks and a Gantt chart illustrating the project schedule, along with a bibliography of relevant project management resources. The scope statement defines project goals, requirements, and constraints, ensuring a well-defined and profitable coffee shop venture.
Document Page
Running head: PROJECT MANAGEMENT
Project management
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT
1. Work breakdown structure
WBS Task Name
0 Caffeine Bean Café Shop
1 Initiation phase
1.1 Research the coffee business
1.2 Business case development
1.3 Identifying total cost of the project
1.4 Undertaking proper feasibility study
1.5 Establishment of project charter
1.6 Defining the vision of the project
1.7 Appointing team members
1.8 Milestone 1: Completion of initiation phase
2 Planning phase
2.1 Finding the right location for the café
2.2 Registering the business
2.3 Getting licenses
2.4 Finding the best suppliers
2.5 Determining competitors
2.6 Designing the floor plan
2.7 Hiring accountant and other needed team members
2.8 Getting local help for funding
2.9 Identifying suppliers
2.10 Identifying vendors
2.11 Marketing of the shop
2.12 Determining breakeven point
2.13 Milestone 2: Completion of the planning phase
3 Execution phase
3.1 Location determined
3.2 Taking rent in the building
Document Page
2
PROJECT MANAGEMENT
3.3 Interior designing of the buildings
3.4 Using electrical equipment as well as air conditioning
3.5 Using cables for wiring
3.6 Undertaking the work of painting
3.7 Setting freezer
3.8 Creating shelves
3.9 Setting proper utensils in the kitchen
3.10 Equipment for servicing
3.11 Proper backup generator
3.12 Availability of internet connection
3.13 Completion of tenant improvements
3.14 Purchasing coffee makers, mixers, cups etc
3.15 Purchasing signage and menus
3.16 Buying music system
3.17 Ordering supplies for inventory
3.18 Meeting local regulations for commercial establishment, fire safety regulations
as well as code enforcements
3.19 Opening a business account
3.20 Milestone 3: Completion of execution phase
4 Project closure phase
4.1 Post project review
4.2 Stakeholder sign off
4.3 Documentation
4.4 Releasing resources
4.5 Milestone 4: Completion of closure phase
Document Page
3
PROJECT MANAGEMENT
2. Project schedule (Gantt chart)
Figure 1: Gantt chart
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4
PROJECT MANAGEMENT
(Source: Created by Author)
Document Page
5
PROJECT MANAGEMENT
Bibliography
De Carvalho, M. M., Patah, L. A., & de Souza Bido, D. (2015). Project management and its
effects on project success: Cross-country and cross-industry comparisons. International
Journal of Project Management, 33(7), 1509-1522.
Elsye, V., Latief, Y., & Sagita, L. (2018). Development of work breakdown structure (WBS)
standard for producing the risk based structural work safety plan of building. In MATEC
Web of Conferences (Vol. 147, p. 06003). EDP Sciences.
Hu, X., Cui, N., Demeulemeester, E., & Bie, L. (2016). Incorporation of activity sensitivity
measures into buffer management to manage project schedule risk. European Journal of
Operational Research, 249(2), 717-727.
Sequeira, S., & Lopes, E. (2015). Simple Method Proposal for Cost Estimation from Work
Breakdown Structure. Procedia Computer Science, 64, 537-544.
Takey, S. M., & de Carvalho, M. M. (2015). Competency mapping in project management: An
action research study in an engineering company. International Journal of Project
Management, 33(4), 784-796.
Zecheru, V., & Olaru, B. G. (2016). Work Breakdown Structure (WBS) in Project
Management. Review of International Comparative Management/Revista de
Management Comparat International, 17(1).
chevron_up_icon
1 out of 6
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]