Running head: PROJECT MANAGEMENT Project management Name of the Student Name of the University Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 PROJECT MANAGEMENT 1.Business document WBSTask NameDurationStartFinishPredecessorsComment 1Deck Project56 days Thu 20- 12-18 Fri 08- 03-19 1.1 Project Planning and Prepping 10 days Thu 20- 12-18 Thu 03- 01-19 1.1.1Designing4 days Thu 20- 12-18 Wed 26- 12-18 1.1.1.1Surveying2 days Thu 20- 12-18 Fri 21- 12-18 1.1.1.2Deck permit2 days Mon 24- 12-18 Wed 26- 12-18 4 1.1.2Purchase Materials6 days Thu 27- 12-18 Thu 03- 01-19 1.1.2.1 Measurements and Material Selection 3 days Thu 27- 12-18 Mon 31- 12-18 5 1.1.2.2Site clearing3 days Tue 01- 01-19 Thu 03- 01-19 4,7 1.2Structural Work9 days Thu 27- 12-18 Tue 08- 01-19 1.2.1Foundation3 days Thu 27- 12-18 Mon 31- 12-18
2 PROJECT MANAGEMENT 1.2.1.1 Space limiting Marking foundation holes 3 days Thu 27- 12-18 Mon 31- 12-18 5,4 1.2.1.2Digging Post Holes2 days Fri 28-12- 18 Mon 31- 12-18 11FS-2 days The space limiting marking foundation holes get delayed by 2 days 1.2.2 Securing Posts and Beams 8 days Fri 28- 12-18 Tue 08- 01-19 1.2.2.1 Pour Concrete and set Posts 5 days Fri 28-12- 18 Thu 03- 01-19 12SS Pour concrete and set posts activity cannot be started unless digging post holes get completed 1.2.2.2Install Footings3 days Fri 04-01- 19 Tue 08- 01-19 14 1.3Framing and stairs7 days Fri 04- 01-19 Mon 14- 01-19
3 PROJECT MANAGEMENT 1.3.1Laying the joists4 days Fri 04- 01-19 Wed 09- 01-19 1.3.1.1 Measure and cut, rim, floor joists and stringers 2 days Fri 04-01- 19 Mon 07- 01-19 8 1.3.1.2 Install rim, floor joists, stringers and framing 2 days Tue 08- 01-19 Wed 09- 01-19 14,18 1.3.2Decking and Ramp3 days Thu 10- 01-19 Mon 14- 01-19 1.3.2.1Install deck planks3 days Thu 10- 01-19 Mon 14- 01-19 19 1.3.2.2Install ramp2 days Fri 11-01- 19 Mon 14- 01-19 21FF Installation of ramp cannot get completed unless installation of deck plans get completed 1.4Utilities10 days Wed 09- 01-19 Tue 22- 01-19 1.4.1HVAC4 daysWed 09-Mon 14-
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4 PROJECT MANAGEMENT 01-1901-19 1.4.1.1 Subcontract HVAC Installer for Gas line work 2 days Wed 09- 01-19 Thu 10- 01-19 15 1.4.1.2 Supervise and inspect sub- contractor work 3 days Thu 10- 01-19 Mon 14- 01-19 25FS-1 day Subcontract HVAC installer for gas line work get delayed by 1 day 1.4.2Electrical6 days Tue 15- 01-19 Tue 22- 01-19 1.4.2.1 Subcontract electrician 2 days Tue 15- 01-19 Wed 16- 01-19 25,26. 1.4.2.2 Supervise and inspect electrician’s work 2 days Mon 21- 01-19 Tue 22- 01-19 28FS+2 days Subcontract electrician work can be led by 2 days and therefore the work will be completed 2 days earlier.
5 PROJECT MANAGEMENT 1.5Finishing work11 days Wed 23- 01-19 Wed 06- 02-19 1.5.1Railings7 days Wed 23- 01-19 Thu 31- 01-19 1.5.1.1Install Railing Posts4 days Wed 23- 01-19 Mon 28- 01-19 29,22 1.5.1.2 Install Railings, Balusters and top rail 2 days Tue 29- 01-19 Wed 30- 01-19 32 1.5.1.3 Install Glass Panels in Hand rails 3 days Tue 29- 01-19 Thu 31- 01-19 32 1.5.2Skirting6 days Wed 30- 01-19 Wed 06- 02-19 1.5.2.1 Skirting measurements and cuttings 4 days Wed 30- 01-19 Mon 04- 02-19 32FS+1 day Installation of glass panels in hand rails can be ledby 1 day 1.5.2.2Lattice install2 days Tue 05- 02-19 Wed 06- 02-19 34,36 1.6Closing22 days Thu 07- 02-19 Fri 08- 03-19 1.6.1Electrical and Heater8 daysThu 07-Mon 18-
6 PROJECT MANAGEMENT – Phase 202-1902-19 1.6.1.1 Electrical Final work and Fixtures 4 days Thu 07- 02-19 Tue 12- 02-19 37 1.6.1.2 Stone fire table installation 4 days Wed 13- 02-19 Mon 18- 02-19 40 1.6.2Bench and Screening14 days Tue 19- 02-19 Fri 08- 03-19 1.6.2.1 Privacy Screen Installation 4 days Tue 19- 02-19 Fri 22- 02-19 41 1.6.2.2 Bench seats Installation 5 days Mon 25- 02-19 Fri 01- 03-19 43 1.6.2.3 Perform final cleaning and remove all scrap material from work site 5 days Mon 04- 03-19 Fri 08- 03-19 44
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7 PROJECT MANAGEMENT 2. Gantt chart reflecting critical path Figure 1: Critical path in Tracking Gantt chart view (Source: Created by Author)
8 PROJECT MANAGEMENT Bibliography Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practicesonprojectsuccess:Towardsdevelopingaprojectbenefitsgovernance framework.International Journal of Project Management,34(4), 761-778. Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298. Papke-Shields, K. E., & Boyer-Wright, K. M. (2017). Strategic planning characteristics applied to project management.International Journal of Project Management,35(2), 169-179. Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature reviewwithacriticallookatthebravenewworld.InternationalJournalofProject Management,33(2), 278-290.