Development of Mobile Based Farmer Support Application

Verified

Added on  2023/01/23

|18
|2752
|60
AI Summary
This report is based on the project plan for the development of the mobile application as proposed by Globex.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running Head: PROJECT MANAGEMENT
Development of Mobile Based Farmer Support Application
Name of the Student
Name of the University

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Table of Contents
Introduction......................................................................................................................................2
Project Description..........................................................................................................................2
Part 1: MOV....................................................................................................................................2
Desired Area of Impact................................................................................................................2
Value for the Project....................................................................................................................3
Metric...........................................................................................................................................3
Timeframe....................................................................................................................................3
MOV Statement...........................................................................................................................3
Part 2: Scope....................................................................................................................................3
Project Scope Definition..............................................................................................................3
Scope Management Plan..............................................................................................................4
Resource List...............................................................................................................................4
MS Project Resource Sheet.........................................................................................................4
Part 3: Work Breakdown Structure..................................................................................................5
Work Breakdown Structure.........................................................................................................5
Part 4: Risk Analysis and Plan.......................................................................................................12
Assumptions..............................................................................................................................12
Risk Identification Framework..................................................................................................12
Risk Analysis.............................................................................................................................12
Document Page
2PROJECT MANAGEMENT
Part 5: Quality Management Plan..................................................................................................13
Project’s Quality Statement.......................................................................................................13
Verification Activities...............................................................................................................13
Validation Activities..................................................................................................................13
Part 6: Closure and Evaluation......................................................................................................14
Closure Checklist.......................................................................................................................14
Project Evaluation......................................................................................................................14
References and Bibliography.........................................................................................................16
Document Page
3PROJECT MANAGEMENT
Introduction
Globex has decided to develop a mobile based farmer support application (MBFSA) that
will allow the target users – local government, wholesalers and farmers to create their own
profiles as well as view and enter specific data regarding crop production and weather. Globex
has hired Virtucon for development of the app that has to be done within six months from the
project initiation. Furthermore, the completion of project pilot and delivery of prototype will
have to be done within two months of initiation.
This report is based on the project plan for the development of the mobile application as
proposed by Globex.
Project Description
In this project, a mobile application will be developed that will have several features
including data entry and analysis for crop production, weather trends and others. There are three
target groups for the project – the government, the wholesalers and the farmers. The application
will be accessible through mobile devices and any of the target users will be able to create their
own personal profile in the app and enter or download data. The project will be conducted in two
phases – pilot project with prototyping and the development of the final version of the
application..
Part 1: MOV
Desired Area of Impact
The desired areas of impact in terms of importance are arranged as follows.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
Strategy > Social > Customer > Financial > Operational
Value for the Project
The value for this particular project is faster rather than better as the data entry and
download will be streamlined much faster and effectively.
Metric
It is expected that 80% of the farmers will download the app within 6 months of app
launch.
Timeframe
The project is expected to be complete within 6 months from initiation.
MOV Statement
The organisation will allow the customers to have a better experience while gathering
data regarding data collection, input and analysis regarding the crop production based on weather
conditions.
Part 2: Scope
Project Scope Definition
The scope of the project includes the development of a mobile application that will allow
the target users – local government, wholesalers and farmers to create their own profiles as well
as view and enter specific data regarding crop production and weather.
Document Page
5PROJECT MANAGEMENT
Scope Management Plan
Scope management plan is required to ensure the required deliverables are fulfilled
without any additional expenditure or scope creep. Accordingly, the pilot project will be first
started in order to develop the system prototype before proceeding with the actual development
process. Meanwhile, monitoring and change management can be implemented to ensure the
project is on the right track.
Resource List
The list of resources used in the project is as follows.
Resource Name Type Max. Units Std. Rate
Project Manager Work 100% $140.00/hr
Finance Manager Work 100% $125.00/hr
Technical Manager Work 100% $120.00/hr
App Developer Work 100% $100.00/hr
App Tester Work 100% $100.00/hr
Hardware Material $3,000.00
Software Material $2,000.00
MS Project Resource Sheet
The MS Project resource sheet screenshot is as follows.
Document Page
6PROJECT MANAGEMENT
Part 3: Work Breakdown Structure
Work Breakdown Structure
The work breakdown structure for the project along with the schedule and task
dependencies is shown in the following table.
WBS Task Name Duration Start Finish Predecessors
0 Mobile Based Farmer Support Application 131 days Mon 8/5/19 Mon 2/3/20
1 Project Pilot and Prototype Development 46 days Mon 8/5/19 Mon 10/7/19
1.1 Discussion Regarding the Proposed Mobile
Application 3 days Mon 8/5/19 Wed 8/7/19
1.2 Identification of Advantages of Mobile App 3 days Thu 8/8/19 Mon 8/12/19 2
1.3 Present Project Proposal and Initiate Pilot Project 3 days Tue 8/13/19 Thu 8/15/19 3
1.4 Deploy App Development Team 3 days Fri 8/16/19 Tue 8/20/19 4
1.5 Discuss the Requirements of the App 5 days Wed 8/21/19 Tue 8/27/19 5
1.6 Develop Initial Prototype 20 days Wed 8/28/19 Tue 9/24/19 6

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
1.7 Testing and Submission of the Prototype 7 days Wed 9/25/19 Thu 10/3/19 7
1.8 Review of Prototype and Provide Approval to
Proceed 2 days Fri 10/4/19 Mon 10/7/19 8
2 Initiate Project Planning 10 days Tue 10/8/19 Mon 10/21/19
2.1 Send Approval to Team to Proceed 2 days Tue 10/8/19 Wed 10/9/19 9
2.2 Develop Project Charter 3 days Thu 10/10/19 Mon 10/14/19
2.2.1 Identify and Determine Project Scope 0.5 days Thu 10/10/19 Thu 10/10/19 11
2.2.2 Specify Objectives for the Project 0.5 days Thu 10/10/19 Thu 10/10/19 13
2.2.3 Determine Schedule for the Project 0.5 days Fri 10/11/19 Fri 10/11/19 14
2.2.4 Design and Develop the Work Breakdown
Structure for the Project 0.5 days Fri 10/11/19 Fri 10/11/19 15
2.2.5 Develop a Network Diagram Specifying the
Schedule Tradeoffs in the Project 0.5 days Mon 10/14/19 Mon 10/14/19 16
2.2.6 Determine Budget for Developing the Final
Version of the Mobile App 0.5 days Mon 10/14/19 Mon 10/14/19 17
2.3 Develop Communication Plan for the Project
Team Members 1 day Tue 10/15/19 Tue 10/15/19 18
2.4 Identify the Risks Associated with the Project 1 day Wed 10/16/19 Wed 10/16/19 19
2.5 Development Risk Management Plan for the
Project 2 days Thu 10/17/19 Fri 10/18/19 20
2.6 Receive Funding and Proceed with the Project 1 day Mon 10/21/19 Mon 10/21/19 21
3 Project Initiation 4 days Tue 10/22/19 Fri 10/25/19
3.1 Develop List of Hardware and Software
Requirements 1 day Tue 10/22/19 Tue 10/22/19 22
3.2 Purchase Hardware and Software 1 day Wed 10/23/19 Wed 10/23/19 24
3.3 Instruct Team to Start Work 1 day Thu 10/24/19 Thu 10/24/19 25
3.4 Assign Development Budget for the Project 1 day Fri 10/25/19 Fri 10/25/19 26
4 Project Execution 63 days Mon 10/28/19 Wed 1/22/20
4.1 Start Development of the Application 1 day Mon 10/28/19 Mon 10/28/19 27
4.2 Installation of Purchased Hardware 2 days Tue 10/29/19 Wed 10/30/19 29
4.3 Install Necessary Support Softwares 2 days Thu 10/31/19 Fri 11/1/19 30
4.4 Application Development Based on the
Prototype Testing 3 days Mon 11/4/19 Wed 11/6/19 31
Document Page
8PROJECT MANAGEMENT
4.5 Implementation of the Features as Required 3 days Thu 11/7/19 Mon 11/11/19 32
4.6 Complete Beta Version of the Application 2 days Tue 11/12/19 Wed 11/13/19 33
4.7 Conduct Beta Testing 3 days Thu 11/14/19 Mon 11/18/19 34
4.8 Identify Application Bugs and Issues 3 days Tue 11/19/19 Thu 11/21/19 35
4.9 Remove Bugs from the App 3 days Fri 11/22/19 Tue 11/26/19 36
4.10 Development of the Final Version of the App 30 days Wed 11/27/19 Tue 1/7/20 37
4.11 Final Testing before Handover 10 days Wed 1/8/20 Tue 1/21/20 38
4.12 Go Live 1 day Wed 1/22/20 Wed 1/22/20 39
5 Sign Off and Complete the Project 8 days Thu 1/23/20 Mon 2/3/20
5.1 Submit Documentation of the Project 4 days Thu 1/23/20 Tue 1/28/20 40
5.2 Review and Appraisal 3 days Wed 1/29/20 Fri 1/31/20 42
5.3 Sign Off 1 day Mon 2/3/20 Mon 2/3/20 43
5.4 Official Closing 0 days Mon 2/3/20 Mon 2/3/20 44
The based on the work breakdown structure and project schedule, the resource allocation
and budget for the project is shown below.
WBS Task Name Duration Resource Names Cost
0 Mobile Based Farmer Support Application 131 days $228,240.00
1 Project Pilot and Prototype Development 46 days $82,680.00
1.1 Discussion Regarding the Proposed Mobile
Application 3 days Technical Manager $2,880.00
1.2 Identification of Advantages of Mobile App 3 days Technical Manager $2,880.00
1.3 Present Project Proposal and Initiate Pilot
Project 3 days Technical Manager $2,880.00
1.4 Deploy App Development Team 3 days Project Manager $3,360.00
1.5 Discuss the Requirements of the App 5 days Project Manager $5,600.00
1.6 Develop Initial Prototype 20 days Technical Manager,
Project Manager $41,600.00
1.7 Testing and Submission of the Prototype 7 days
Finance Manager,
Technical Manager,
Project Manager
$21,560.00
1.8 Review of Prototype and Provide Approval to 2 days Technical Manager $1,920.00
Document Page
9PROJECT MANAGEMENT
Proceed
2 Initiate Project Planning 10 days $18,560.00
2.1 Send Approval to Team to Proceed 2 days Technical Manager $1,920.00
2.2 Develop Project Charter 3 days $6,240.00
2.2.1 Identify and Determine Project Scope 0.5 days Technical Manager,
Project Manager $1,040.00
2.2.2 Specify Objectives for the Project 0.5 days Technical Manager,
Project Manager $1,040.00
2.2.3 Determine Schedule for the Project 0.5 days Technical Manager,
Project Manager $1,040.00
2.2.4 Design and Develop the Work Breakdown
Structure for the Project 0.5 days Technical Manager,
Project Manager $1,040.00
2.2.5 Develop a Network Diagram Specifying the
Schedule Tradeoffs in the Project 0.5 days Technical Manager,
Project Manager $1,040.00
2.2.6 Determine Budget for Developing the Final
Version of the Mobile App 0.5 days Technical Manager,
Project Manager $1,040.00
2.3 Develop Communication Plan for the Project
Team Members 1 day Technical Manager,
Project Manager $2,080.00
2.4 Identify the Risks Associated with the Project 1 day Technical Manager,
Project Manager $2,080.00
2.5 Development Risk Management Plan for the
Project 2 days Technical Manager,
Project Manager $4,160.00
2.6 Receive Funding and Proceed with the Project 1 day Technical Manager,
Project Manager $2,080.00
3 Project Initiation 4 days $8,880.00
3.1 Develop List of Hardware and Software
Requirements 1 day Technical Manager $960.00
3.2 Purchase Hardware and Software 1 day Hardware[1], Technical
Manager, Software[1] $5,960.00
3.3 Instruct Team to Start Work 1 day Technical Manager $960.00
3.4 Assign Development Budget for the Project 1 day Finance Manager $1,000.00
4 Project Execution 63 days $100,800.00
4.1 Start Development of the Application 1 day App Developer, App
Tester $1,600.00
4.2 Installation of Purchased Hardware 2 days App Developer, App
Tester $3,200.00

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT MANAGEMENT
4.3 Install Necessary Support Softwares 2 days App Developer, App
Tester $3,200.00
4.4 Application Development Based on the
Prototype Testing 3 days App Developer, App
Tester $4,800.00
4.5 Implementation of the Features as Required 3 days App Developer, App
Tester $4,800.00
4.6 Complete Beta Version of the Application 2 days App Developer, App
Tester $3,200.00
4.7 Conduct Beta Testing 3 days App Developer, App
Tester $4,800.00
4.8 Identify Application Bugs and Issues 3 days App Developer, App
Tester $4,800.00
4.9 Remove Bugs from the App 3 days App Developer, App
Tester $4,800.00
4.10 Development of the Final Version of the App 30 days App Developer, App
Tester $48,000.00
4.11 Final Testing before Handover 10 days App Developer, App
Tester $16,000.00
4.12 Go Live 1 day App Developer, App
Tester $1,600.00
5 Sign Off and Complete the Project 8 days $17,320.00
5.1 Submit Documentation of the Project 4 days App Developer, App
Tester $6,400.00
5.2 Review and Appraisal 3 days Technical Manager,
Project Manager $6,240.00
5.3 Sign Off 1 day
App Developer, Finance
Manager, Technical
Manager, Project
Manager, App Tester
$4,680.00
5.4 Official Closing 0 days Project Manager $0.00
The screenshot from MS Project file is as follows.
Document Page
11PROJECT MANAGEMENT
Document Page
12PROJECT MANAGEMENT

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13PROJECT MANAGEMENT
Part 4: Risk Analysis and Plan
Assumptions
In this project, it has been assumed that the farmers now have access to smartphones and
they will be able to download and use the application. It has also been assumed that the
government will allow access to some of the specific data required to update the application
database regarding weather and crop production.
Risk Identification Framework
Five risks associated with the project are as follows.
Budget overshoot
Technical risks
Cyber security risks
Government allowance risks
Customer acceptability risks
Risk Analysis
Strategy for managing each risk is as follows.
Risk Stakeholder Strategy
Budget overshoot Finance Manager Avoid scope creep and unwanted
expenses
Technical risks Technical Manager Ensure good quality equipments
are purchased and skilled
technicians are deployed
Cyber security risks App Developer Deploy security firewall
Document Page
14PROJECT MANAGEMENT
Government allowance risk Legal Assistant Apply for access to data required
for updating the app
Customer acceptability risk Marketing Manager Raise awareness regarding the
usefulness of the application
Part 5: Quality Management Plan
Project’s Quality Statement
The quality statement for this project is that – the project must be able to deliver a high
quality mobile application with the necessary features and there should be no technical glitches
and failures. In case of occasional bugs, regular patches should be updated and sent to the
customer.
Verification Activities
The verification activities include testing of the application from both developer end and
user end.
Validation Activities
The validation activities include determining if the app has all the required features and
also testing if the app is downloadable or not.
Document Page
15PROJECT MANAGEMENT
Part 6: Closure and Evaluation
Closure Checklist
The project checklist is as follows.
The pilot project is initiated on time
The prototype is delivered on time
Budget and schedule have been reviewed and approved
The app has been delivered as downloadable content
Testing results have been delivered
Project Evaluation
Annotation 1: According to Kerzner and Kerzner (2017), project evaluation is an
important aspect in project management as it involves understanding of the project end product
for a non-technical member of the team, usually the project manager. The project manager
evaluates the project at the end in order to determine if all the requirements of the project have
been met.
Annotation 2: Larson and Gray (2017) said that project evaluation is necessary for any
project as it is mostly required for validation of the entire project that has been conducted. The
project may be passed without validation but in case of residual issues, complications may arise
later on. Identifying the issues during evaluation will allow solving them on the go before the
project officially closed.
Assignment 3: Authors Schwalbe (2015) have also emphasized the important of project
evaluation in project management. They said that it allows the project manager to have a deep

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16PROJECT MANAGEMENT
insight on the project outcomes and have a clear idea what have been expected and what have
been delivered. Many projects need to restart because the project managers can find various
issues during the project while performing evaluation.
Document Page
17PROJECT MANAGEMENT
References and Bibliography
Crawford, J. K. (2014). Project management maturity model. Auerbach Publications.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Larson, E. W., & Gray, C. F. (2017). Project management: The managerial process. McGraw-
Hill Education.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.