Running head: PROJECT MANAGEMENT
Project Management
Name of Student-
Name of University-
Author’s Note-

PROJECT MANAGEMENT1
a. AON Diagram
Figure 1: AON Diagram
(Source: Created by Author)

PROJECT MANAGEMENT2
b. Critical Path
Figure 2: AON Diagram showing critical path
(Source: Created by Author)
The red path in the diagram above shows the critical path of the project. There are three
critical paths in the project; A – F – G – D – E, A – F – G – D – H, and A – F – G – D – J
The critical path that is needed to be considered for this project is: A – F – G – D – J
The total length of the project is 194 days.
Explanation:
Activity Duration Early Start Early Finish Late Start Late Finish
A 90 0 90 0 90
B 15 90 105 15 110
C 5 105 110 110 115

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Network for a New Laptop Computer
|7
|1119
|435

Project Network for a New Laptop Computer.
|11
|438
|2

Decision Support Tools for Project Management - Desklib
|8
|1604
|265

Project Management
|8
|928
|284

Project Management for Batman Movie
|16
|848
|296

Assignment on CPM & Crashing 2022
|7
|1067
|26