Running head: PROJECT MANAGEMENT Project: Fisher Street Car Park ConstructionName of the StudentName of the UniversityAuthor’s Note
Project Management Assignment - (Doc)_1

PROJECT MANAGEMENT1Table of ContentsQuestion 2........................................................................................................................................3Question 2 (a)..............................................................................................................................31. Defining organization and the project.................................................................................32. Updated business case and revised project charter..............................................................33. Project management plan...................................................................................................11Bibliography..................................................................................................................................27
Project Management Assignment - (Doc)_2

PROJECT MANAGEMENT2Question 2 Question 2 (a)1. Defining organization and the project The paper mainly focusses on the construction of Fisher Street Car Park for FairfieldCity Council by the ADCO Construction Company. It is identified that the company “ADCOConstruction” which is one of the leading construction company in Australia engages inconstructing the Fisher Street Car Park in order to provide proper car parking facility(Adcoconstruct.com.au 2018). The project mainly includes car parking for 180 vehicles over 3-storey building that is split into five different levels. The company also includes some of theenvironmentally sustainable initiatives including 30 kW photovoltaic system that is mainlyinstalled on the top level of the car parking area. In addition to this, the design that is made forthe façade treatment is very much spectacular with various significant black butt timberstenciling in order to provide proper themed mural. 2. Updated business case and revised project charter 2.1 Business caseThe paper mainly focusses on the construction of Fisher Street Car Park, which is mainlylocated in the area of Cabramatta by the ADCO construction company in order to provide properparking facility. The project was mainly funded by the Commonwealth Nation building programso that the people of Cabramatta does not have to face any issues or challenges related withparking. In addition to this, the ADCO construction company utilizes some of the environmentalsustainable features including 180-grid connection array that is mainly accounted for over 35%of the annual energy needs of the parking area (Adcoconstruct.com.au 2018). The entire project
Project Management Assignment - (Doc)_3

PROJECT MANAGEMENT3will be executed successfully within 3 years of its commencement and it is found that an extra 1-month time is provided in order to allow the scope creep. Furthermore, the project needs budgetof around AUD 4,432,400.00 in order to complete the construction of Fisher Street Car Park.2.2 ScopeThe scope of the project is elaborated below.In-scope: The in-scope of the project are as follows:Construction of a 3 Storey car parkCreating drainage as well as landscaping areaDeveloping environmental sustainable initiativesInstallation of photovoltaic systemButt timber stenciling Designing facade treatment80-panel grid connected solar arrayOut-Scope: The out-scope of the project are as follows:Detailed description about the materials that are supplied for the project is notprovidedInformation about external stakeholders of the project are not provided in detail2.3 Duration It is assumed that the company “ADCO construction” generally required 3 years in orderto complete the project successfully. It is found that 1-month extra is provided to the projectmanager in order to allow scope creep thus it is estimated that the entire project will besuccessfully completed by 7/26/22
Project Management Assignment - (Doc)_4

PROJECT MANAGEMENT4WBSTask NameDurationStartFinish0Construction of Fisher Street Car Parkby ADCO 1122 daysMon 4/9/18Tue 7/26/221 Planning phase25 daysMon 4/9/18Fri 5/11/181.1 Development of project plan5 daysMon 4/9/18Fri 4/13/181.2 Creation of resource plan3 daysMon 4/16/18Wed 4/18/181.3 Development of financial plan3 daysThu 4/19/18Mon 4/23/181.4 Development of quality managementplan3 daysTue 4/24/18Thu 4/26/181.5 Development of risk managementplan4 daysFri 4/27/18Wed 5/2/181.6 Development of communicationmanagement plan3 daysThu 5/3/18Mon 5/7/181.7 Development of procurement4 daysTue 5/8/18Fri 5/11/181.8 Milestone 1: Completion of projectplanning phase0 daysFri 5/11/18Fri 5/11/182 Initiation phase of the project15 daysMon 5/14/18Fri 6/1/182.1 Development of business case4 daysMon 5/14/18Thu 5/17/182.2 Undertaking feasibility analysis forthe project3 daysFri 5/18/18Tue 5/22/182.3 Establishment of project charter3 daysWed 5/23/18Fri 5/25/182.4 Appointment of project teammembers4 daysMon 5/28/18Thu 5/31/182.5 Approval of the project1 dayFri 6/1/18Fri 6/1/182.6 Milestone 2: Completion of initiation0 daysFri 6/1/18Fri 6/1/18
Project Management Assignment - (Doc)_5

PROJECT MANAGEMENT5phase of the project3 Execution phase of the project1052 daysMon 6/4/18Tue 6/14/223.1 Soil preparation foundation90 daysMon 6/4/18Fri 10/5/183.2 Raw material procurement120 daysMon 10/8/18Fri 3/22/193.3 Construction of a 3 Storey car park190 daysMon 3/25/19Fri 12/13/193.4 Creating drainage as well aslandscaping area220 daysMon 12/16/19Fri 10/16/203.5 Developing environmentalsustainable initiatives100 daysMon 10/19/20Fri 3/5/213.6 Installation of photo voltaic system120 daysMon 3/8/21Fri 8/20/213.7 Butt timber stenciling 50 daysMon 8/23/21Fri 10/29/213.8 Designing facade treatment80 daysMon 11/1/21Fri 2/18/223.9 80 panel grid connected solar array82 daysMon 2/21/22Tue 6/14/223.10 Milestone 3: Completion ofexecution phase0 daysTue 6/14/22Tue 6/14/224 Closure phase30 daysWed 6/15/22Tue 7/26/224.1 Reviewing project8 daysWed 6/15/22Fri 6/24/224.2 Checking the Fisher car park area9 daysMon 6/27/22Thu 7/7/224.3 Stakeholder sign off8 daysFri 7/8/22Tue 7/19/224.4 Documentation5 daysWed 7/20/22Tue 7/26/224.5 Milestone 4: Completion of closurephase0 daysTue 7/26/22Tue 7/26/222.4 Budget estimateThe ADCO construction company generally required budget of around AUD4,432,400.00 in order to complete the construction of Fisher Street Car Park successfully. The
Project Management Assignment - (Doc)_6

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management Assignment : Fisher Street Car Park Construction
|8
|1443
|54