This document provides a detailed implementation plan for the development and trial of a mobile app for BizOps online shopping. It includes identification and description of the project, key objectives and deliverables, resource and cost plan, risk assessment and control measures, and an implementation plan.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT Project Management: BizOps online shopping app implementation plan Name of the student: Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
3PROJECT MANAGEMENT Table of Contents 1. Identification and description......................................................................................................3 1.1 The purpose of the innovation...............................................................................................3 1.3 The background context for the project.................................................................................3 1.4 Project objectives...................................................................................................................3 1.5 Key deliverables....................................................................................................................4 2. Plan and assign responsibilities for key activities.......................................................................4 3. Prepare a schedule for the development and trial of the app.......................................................5 4. Prepare a resource and cost plan..................................................................................................7 5. Identify and assess risk to the project..........................................................................................8 5.1 Risk categorization table........................................................................................................8 5.2 Risk control/treatment...........................................................................................................9 5.3 Implementation plan............................................................................................................10 6. Determine quality measurement plan for the project................................................................10 7. Develop a communications and reporting plan.........................................................................11 8. Project progress report presentation..........................................................................................11 References......................................................................................................................................12
4PROJECT MANAGEMENT 1. Identification and description Project title: Implementation of Mobile app to increase business efficiency 1.1 The purpose of the innovation BizOpsisfocusesonprovidingveryhighquality,innovativeserviceoutcomes considering their frequently changing requirements also. The purpose of BizOps is to offer innovative green product solution adopting suitable work practices as well. 1.3 The background context for the project Using combines business experiences of Simmon, Devon and Ntushka BizOps has become a very popular retail company in these days. However, due to their product affordability and service efficacy the numbers of consumers of the company is growing rapidly. Staring from a single store front currently the numbers of outlets operating the owners are near about more than 150. In order to obtain structured and measurable revenue from the competitive market and to gain competitive advantages in the market the marketing manager of the company has planned to implement a mobile application for their consumers. 1.4 Project objectives To enhance the revenue of the company by around 15% within the financial year ending To maintain the rate of annual profit by 15% for each and every offered services and products To reinvest a profit rate by75% by the end of the financial year To maintain the marketing position by launching high quality and user friendly products
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
5PROJECT MANAGEMENT To offer timey training to the employees by using needful resources (human, financial etc) 1.5 Key deliverables BizOps is focused to deliver a user friendly mobile app to their consumers to increase the business efficacy and gain a profit margin up to 75% by the end of the financial year. The issues associated to physical stores and organizational operations will be completely resolved with the design and implementation of the mobile app. The aim of BizOps is to deliver a mobile app which will provide a new direction to the retail operations. 2. Plan and assign responsibilities for key activities Task NameDurationResource Names Project schedule for BizOps mobile app development111 days Project initiation phase16 days Developing scope statement for BizOps5 daysRetail operation managing director Assigning project team5 daysHR manager Resource identification3 daysResource manager Gathering requirements4 daysResource manager Requirement analysis4 daysResource manager Milestone 1: Submitting project outline draft0 daysChief Executive officer Project planning phase16 days Risk management plan5 daysmanaging director: Business operation Quality management plan2 daysRetail operation managing director Stakeholder management plan3 daysHR manager Identification of functional and non- functional requirements4 daysManaging director: Finance operation Feasibility study and budget plan2 daysManaging director: Finance operation Milestone 2: Completion of project0 daysChief Executive officer
6PROJECT MANAGEMENT planning phase Design and development of the Mobile app50 days Operating tool and platform selection10 dayssystem designer Designing prototype10 dayssystem developer UML diagram presentation10 dayssystem designer, Application programmer Simulation10 daysApplication programmer Server/database connectivity10 daysRetail operation managing director Milestone 4: Completion of project design and development phase0 daysChief Executive officer Project testing phase14 days Unit testing5 daystester Integrated testing3 daystester Acceptance testing6 daystester Milestone 5: Final Prototype testing0 daysManaging director: Finance operation Closure phase15 days Change management (if required)6 daysmanaging director: Business operation Post maintenance plan2 daysChief Executive officer Promoting the mobile app2 daysmanaging director: Business operation Future business success strategies development3 daysRetail operation managing director Stakeholders signoff2 daysHR manager Milestone 6: Completion of project closure phase0 daysChief Executive officer 3. Prepare a schedule for the development and trial of the app Task NameDuratio nStartFinish Project schedule for BizOps mobile app development111 daysThu 1/3/19Thu 6/6/19 Project initiation phase16 daysThu 1/3/19Thu 1/24/19 Developing scope statement for BizOps5 daysThu 1/3/19Wed 1/9/19 Assigning project team5 daysThu 1/10/19Wed 1/16/19 Resource identification3 daysThu 1/10/19Mon 1/14/19
7PROJECT MANAGEMENT Gathering requirements4 daysMon 1/21/19 Thu 1/24/19 Requirement analysis4 daysTue 1/15/19Fri 1/18/19 Milestone 1: Submitting project outline draft0 daysThu 1/24/19Thu 1/24/19 Project planning phase16 daysFri 1/25/19Fri 2/15/19 Risk management plan5 daysFri 1/25/19Thu 1/31/19 Quality management plan2 daysFri 2/1/19Mon 2/4/19 Stakeholder management plan3 daysTue 2/5/19Thu 2/7/19 Identification of functional and non-functional requirements4 daysFri 2/8/19Wed 2/13/19 Feasibility study and budget plan2 daysThu 2/14/19Fri 2/15/19 Milestone 2: Completion of project planning phase0 daysFri 2/15/19Fri 2/15/19 Design and development of the Mobile app50 daysMon 2/18/19Fri 4/26/19 Operating tool and platform selection10 daysMon 2/18/19Fri 3/1/19 Designing prototype10 daysMon 3/4/19Fri 3/15/19 UML diagram presentation10 daysMon 3/18/19Fri 3/29/19 Simulation10 daysMon 4/1/19Fri 4/12/19 Server/database connectivity10 daysMon 4/15/19Fri 4/26/19 Milestone 4: Completion of project design and development phase0 daysFri 4/26/19Fri 4/26/19 Project testing phase14 daysMon 4/29/19 Thu 5/16/19 Unit testing5 daysMon 4/29/19Fri 5/3/19 Integrated testing3 daysMon 5/6/19Wed 5/8/19 Acceptance testing6 daysThu 5/9/19Thu 5/16/19 Milestone 5: Final Prototype testing0 daysThu 5/16/19Thu 5/16/19 Closure phase15 daysFri 5/17/19Thu 6/6/19 Change management (if required)6 daysFri 5/17/19Fri 5/24/19 Post maintenance plan2 daysMon 5/27/19Tue 5/28/19 Promoting the mobile app2 daysWed 5/29/19 Thu 5/30/19 Future business success strategies development3 daysFri 5/31/19Tue 6/4/19
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
8PROJECT MANAGEMENT Stakeholders signoff2 daysWed 6/5/19Thu 6/6/19 Milestone 6: Completion of project closure phase0 daysThu 6/6/19Thu 6/6/19 4. Prepare a resource and cost plan The net cost assigned for the project is $28,552 and the lists of resources and respective cost assigned for the project are elaborated in the below section: Deliverable/ milestones/phasesResourceCost Project schedule for BizOps mobile app development$28,552.00 Project initiation phase$4,592.00 Developing scope statement for BizOps Retail operation managing director$1,360.00 Assigning project teamHR manager$1,120.00 Resource identificationResource manager$576.00 Gathering requirementsResource manager$768.00 Requirement analysisResource manager$768.00 Milestone 1: Submitting project outline draftChief Executive officer$0.00 Project planning phase$4,056.00 Risk management planmanaging director: Business operation$1,400.00 Quality management planRetail operation managing director$544.00 Stakeholder management planHR manager$672.00 Identification of functional and non-functional requirements Managing director: Finance operation$960.00 Feasibility study and budget planManaging director: Finance operation$480.00 Milestone 2: Completion of project planning phaseChief Executive officer$0.00 Design and development of the Mobile app$12,800.00 Operating tool and platform selectionsystem designer$2,240.00 Designing prototypesystem developer$2,080.00 UML diagram presentationsystem designer, Application programmer$4,000.00 SimulationApplication programmer$1,760.00
9PROJECT MANAGEMENT Server/database connectivityRetail operation managing director$2,720.00 Milestone 4: Completion of project design and development phaseChief Executive officer$0.00 Project testing phase$2,800.00 Unit testingtester$1,000.00 Integrated testingtester$600.00 Acceptance testingtester$1,200.00 Milestone 5: Final Prototype testingManaging director: Finance operation$0.00 Closure phase$4,304.00 Change management (if required)managing director: Business operation$1,680.00 Post maintenance planChief Executive officer$800.00 Promoting the mobile appmanaging director: Business operation$560.00 Future business success strategies development Retail operation managing director$816.00 Stakeholders signoffHR manager$448.00 Milestone 6: Completion of project closure phaseChief Executive officer$0.00 5. Identify and assess risk to the project 5.1 Risk categorization table PriorityRiskLikelihoodImpactLevel of risk R1Lack of technical skills among the project team members LikelyMajorHigh R2Lack of security measures in the Mobile app RareCatastrophicExtreme R3Lack of operational abilities in the newly developed system UnlikelyModerateMedium
10PROJECT MANAGEMENT R4Overrunning costLikelyMinorLow 5.2 Risk control/treatment Risks: 1.Lack of technical skills among the project team members 2.Lack of security measures in the Mobile app 3.Lack of operational abilities in the newly developed system 4.Overrunning cost Control measureStrengthWeakness Control measures/treatment Arrangementofon job technical training Skilloftheteam members will increase Additionalcostis needed Incorporating encryption mechanism Security of the system will become stronger Extra cost is needed Feasibility studyProperbudgetplan will be implemented If accurate budget is n notplannedthenit will exceed the budget ratio Impact of riskThe identified risks can negatively impact the regular success and operational abilities of the mobile app that is going to be implemented for Personnel involvedSean Bamford Nancy Tooket
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
11PROJECT MANAGEMENT Mike Booth Expected outcomes of the risk treatment It will be able to improve the current intranet sustainability It helps to hold the recent workers compensation as well as product liability and business assets 5.3 Implementation plan In order to implement the risk management plan different legal acts, law, policy and regulations must be considered. The supply chain, logistics and elements for green solutions are all considered. 6. Determine quality measurement plan for the project In order to check that whether quality of the mobile application is running according to the company need and consumers demand or not the measurement plan that are developed include the below: Checking operational abilities, user friendliness and functionalities of the newly developed mobile app Providing an accurate user experience Checking performance of the mobile app
12PROJECT MANAGEMENT 7. Develop a communications and reporting plan People involvedPurposeWhenFrequency Projectmanagerand project team members To prepare the project scope statement Attheproject initiation phase Monthly Projectsponsorand finance manager To develop budget of the project Attheproject planning phase Monthly Projectmanager, developerand designer Projectprototype design details Projectplanningand implementation phase Weekly 8. Project progress report presentation Name of the projectImplementation of mobile app for BizOps Project managerPlease Fill Report provided toThe project sponsor Current progress achievementRecentlytheprojectisrunningacrossthe design and development phase Issues experiencedTechnical flaw is the only flaw that has been experienced by this phase Recommended records and reportsProject status report Ongoing management planProject promotional activities Innovation of technical product solutions Undertakingcontinuousproject
13PROJECT MANAGEMENT improvement plans
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
14PROJECT MANAGEMENT References Ahern, T., Leavy, B., and Byrne, P. J. 2014. Complex project management as complex problem solving: A distributed knowledge management perspective.International Journal of Project Management,32(8), 1371-1381. Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., and Wang, Q. 2015. Implementing educational innovations at scale: Transforming researchers into continuous improvement scientists.Educational Policy,29(1), 257-277. Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., and de Almeida, L. F. M. 2014. Can agile project management be adopted by industries other than software development?.Project Management Journal,45(3), 21-34. Conger, S. 2015. Six sigma and business process management. InHandbook on Business Process Management 1(pp. 127-146). Springer, Berlin, Heidelberg. Heldman, K. 2015.PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley and Sons. Hornstein, H. A. 2015. The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298. Joslin, R., and Müller, R. 2015. Relationships between a project management methodology and projectsuccessindifferentprojectgovernancecontexts.InternationalJournalofProject Management,33(6), 1377-1392.
15PROJECT MANAGEMENT Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., and Villanueva, P. 2014. Project riskmanagementmethodologyforsmallfirms.InternationalJournalofProject Management,32(2), 327-340. Mir, F. A., and Pinnington, A. H. 2014. Exploring the value of project management: linking projectmanagementperformanceandprojectsuccess.Internationaljournalofproject management,32(2), 202-217. Sanchez, M. A. 2015. Integrating sustainability issues into project management.Journal of Cleaner Production,96, 319-330. Todorovic, M. L., Petrović, D. Č., Mihic, M. M., Obradovic, V. L., and Bushuyev, S. D. 2015. Projectsuccessanalysisframework:Aknowledge-basedapproachinproject management.International Journal of Project Management,33(4), 772-783.