Project Management: Camden Sickle Cell and Thalassaemia Service Group

   

Added on  2023-01-05

18 Pages2279 Words1 Views
Project Management

EXECUTIVE SUMMARY
The project report summarizes about all steps of completing a project. The task or project is
related to Camden Sickle Cell and Thalassaemia Service Group. In the report different aspects of
project management are summarized in detailed manner including network diagram, matrix of
stakeholders, analysis of risk and many more. The objective of report is to get an overview about
futuristic aspect is relation to project.

Contents
EXECUTIVE SUMMARY.........................................................................................................................2
INTRODUCTION.......................................................................................................................................4
MAIN BODY..............................................................................................................................................4
Task 1 Network Diagram.........................................................................................................................4
TASK 2 Stakeholder Matrix....................................................................................................................8
TASK 3 Work Breakdown Structure.......................................................................................................9
TASK 4 Risk Analysis............................................................................................................................9
TASK 5 determined the measurement to control the event....................................................................11
TASK 6 critically analyze the methodology which would be appropriate for project............................12
CONCLUSION.........................................................................................................................................13
REFERENCES..........................................................................................................................................14

INTRODUCTION
Project management is the method of directing the team's efforts in achieving the targets and
meeting the requirements for performance at a prescribed period. The primary task in project
management is to meet all the aims of the project within the limits set. The report is based on
Camden Sickle Cell and Thalassaemia Service Group’s project. In the report different kinds of
elements of project management are described including network diagram, risk analysis, work
break down structure etc.
MAIN BODY
Task 1 Network Diagram
A network chart illustrates graphically all activities, tasks and workflows for a project. The plan
and flow of activities for the plan are plotted and its progress is monitored by every phase and
completed (Kerzner, 2019). The Thalassemia Service Group and Camden Sickle Cell are
organizations that procure funds to arrange music concerts and inform people. The Sickle Cell
and Thalassemia Treatment Network is one of the key aims of this initiative to collect money for
sustained growth. The network diagram following gives clearer explanation of product start-and-
end day and guarantees the project leader is able to function appropriately. The following lists all
the tasks and timescales used by the project leader to finish the project successfully.
Activities:
Activities Duration (In days) Predecessor
Budget approval 1 -
Hire publicity director 14 1
Hire Set Designer 14 1
Hire Place for Audition 7 2
Advertising to hire Crew and Cast 7 2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management for Camden Sickle Cell and Thalassaemia Service Group
|13
|2019
|40

Project Management: Camden Sickle Cell and Thalassaemia Service Group Case
|12
|1919
|1

Project Management: Desklib Online Library
|12
|2228
|60

Project Management: Stakeholder Analysis, Risk Analysis, and Quality Control
|10
|2311
|276

Project Management: Network Diagram, Stakeholder Analysis, Work Breakdown Structure, Risk Analysis, Quality Expectations
|13
|2211
|51

Project Management: Camden Sickle Cell and Thalassaemia Music Festival
|12
|1984
|1