This document provides an overview of project management, including AON diagram, critical path, and crashing. It discusses the concept of project success and benefits management. The document also includes a bibliography for further reading.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT Project management Name of the Student Name of the University Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 PROJECT MANAGEMENT Table of Contents 1. AON Diagram........................................................................................................................2 2. Critical path...........................................................................................................................3 3. Crashing.................................................................................................................................4 Bibliography...............................................................................................................................7
2 PROJECT MANAGEMENT 1. AON Diagram ActivityDescriptionEstimated completion time (weeks) Immediate Predecessors A B C D E F G H Design/Test product Hire workers Train workers Order/receive materials Reconfigure machinery/setup Advertise product Production Pay purchase orders 6 3 3 2 7 8 8 3 - A B A D B, D C, E D The AON diagram that is provided below showcases on early start, late start, early finish, late finish, duration and name of the activity. Figure 1: AON Diagram (Source: Created by Author)
3 PROJECT MANAGEMENT 2. Critical path ActivityDurationPredecessorEarly start Early finish Late start Late finish A6--0606 B3A69912 C3B9121215 D2A6868 E7D815815 F8B, D917412 G8C, E15231523 H3D81158 Figure 2: Diagram reflecting ES, EF, LS, LF (Source: Created by Author) From the above diagram, the path that are identified are generally listed below: A>D>E>G =6+2+7+8=23 A>B>C>G=6+3+3+8=20
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 PROJECT MANAGEMENT Therefore, the critical path of the schedule isA>D>E>G 3. Crashing The table that is provided below reflects the difference in crash time, crash cost. ActivityNormal Time (weeks) Normal Cost Crash time (weeks) Crash Cost DtDcDc/Dt A6$1,200,0004$2,200,0002$1,000,000500,000 B3$400,0002$500,0001$100,000100,000 C3$500,0003$500,0000$00 D2$1,000,0001$1,200,0001$200,000200,000 E7$1,000,0005$1,900,0002$900,000450,000 F8$2,000,0005$3,200,0003$1,200,00040,000 G8$1,200,0004$2,600,0004$1,400,00035,000 H3$100,0002$200,0001$100,000100,000 After calculating Dc, Dt and Dc/Dt, critical path of project is mainly identified A>D>E>G =6+2+7+8=23 A>B>C>G=6+3+3+8=20 As,A>D>E>G is the critical path,the activities that will be crashed are generally highlighted in red in the table that is generally provided below:
5 PROJECT MANAGEMENT ActivityNormal Time (weeks) Normal Cost Crash time (weeks) Crash Cost DtDcDc/Dt A6$1,200,0004$2,200,0002$1,000,000500,000 B3$400,0002$500,0001$100,000100,000 C3$500,0003$500,0000$00 D2$1,000,0001$1,200,0001$200,000200,000 E7$1,000,0005$1,900,0002$900,000450,000 F8$2,000,0005$3,200,0003$1,200,00040,000 G8$1,200,0006$2,600,0002$1,400,000130,000 H3$100,0002$200,0001$100,000100,000 As per the critical path, the required time= 6+2+7+8= 23wks Management wants to bring the product 7 wks. earlier than scheduled Therefore, the required time = (23-7) wks.= 16 wks. It is identified that the entire project will be completed within 16weeks that is 7 weeks earlier as per the schedule. It is found that the critical path of the project does not change and it remains the same. The addition cost that is needed for finishing the entire project successfully will be =500,000+ 200,000+ 450,000+ 130,000
6 PROJECT MANAGEMENT =$1,163,000 Thus, it is analyzed that $1,163,000 is required in order to complete the project successfully before seven weeks.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 PROJECT MANAGEMENT Bibliography Badewi, A., 2016. The impact of project management (PM) and benefits management (BM) practicesonprojectsuccess:Towardsdevelopingaprojectbenefitsgovernance framework.International Journal of Project Management,34(4), pp.761-778. Conforto, E.C., Salum, F., Amaral, D.C., da Silva, S.L. and de Almeida, L.F.M., 2014. Can agileprojectmanagementbeadoptedbyindustriesotherthansoftware development?.Project Management Journal,45(3), pp.21-34. De Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its effectson project success: Cross-country and cross-industry comparisons.International Journal of Project Management,33(7), pp.1509-1522. Hornstein, H.A., 2015. The integration of project management and organizational change managementisnowanecessity.InternationalJournalofProjectManagement,33(2), pp.291-298. Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts.International Journal of Project Management,33(6), pp.1377-1392.