3 PROJECT MANAGEMENT 1. Title The title of the project is “development of CRM system” within the organization “Tier One Suppliers Insurance Group”. 2. Scope Overview The scope of the project is mainly categorized into in-scope and out-scope. In-scope:The in-scope of the project includes: Up gradation of information system of the organization “Tier One Supplier Insurance Group” Developing CRM system within the organization Issuing tablets to the workers of the organization Integration of laptop and tablets with the TOSIG system Out scope:The out scope of the project includes: Proper training facility is not provided to the workers of the organization Information about the suppliers are not elaborated 3. Business case The organization “Tier One Suppliers Insurance Group” offers insurance service for improving stockyards, fencing, storage silos, building as well as machinery. The main aim of the organization is to maintain its customers and to enhance the number of insurance products that is delivered to the customer of the organization. The staffs of the organization needs to re-enter information within the TOSIG system at the end of the day and after then they generally receives
4 PROJECT MANAGEMENT a report. However, one of the major concern that is rising is that the organization is missing opportunities for selling insurance, as their agents does not have the ability of receiving report in the field. Another factor that is reducing the sale of insurance is that the organizational staff spend much time in the office in entering information into the system for visiting the site. One of the major threat that the organization is getting is due to the entrance of other insurance companies within Australia. In order to resolve all the issues and challenges, the organization wants to upgrade their information system into CRM system. The organization provides tablets as well as laptop to the agents and integrate them with the TOSIG system so that the data will directly move to the cloud thus reducing the time that the argents generally spend on entering data. 4. Background The organization “Tier one supplier insurance group” generally helps in offering insurance to the tier one suppliers for improving buildings, fencing, stockyards, machinery as well as storage silos. The organization is operating from the last 65 years and they generally pride themselves on traditional values in order to maintain long-term relationships with the clients of the organization. They generally underwrite insurance on 6.7 billion dollar and have 150 agents on the field who mainly involves in maintaining offices for enhancing the number of insurance products that is mainly offered to the clients. The organization also want to enhance the sales of insurance within medium as well as small size organizations in various regional areas. 5. Milestone schedule Task NameDurationStartFinish
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
8 PROJECT MANAGEMENT Milestone 4: Completion of project closure phase 0 days Tue 31-07- 18 Tue 31-07- 18 6. Risks, assumptions and constraints 6.1 Project risk RiskDescriptionImpactProbabilityMitigation process Schedule slippage Iftheproject scheduleisnot tracked properly then the project managerfaces challengesin finishingthe projectwithin theexpected deadline SignificantVery LikelyInorderto resolvethe issues the project managermust trackthe scheduleofthe projectregular for making sure thattheproject isgoinginthe right direction. Budget shortfallIf the budget of the project is not managed appropriately then the project SignificantLikelyInorderto mitigatethe issueitis necessary to use earnedvalue
9 PROJECT MANAGEMENT faceschallenges dueto shortage of project budget analysisfor making sure that properamount budget is utilized on the project. Inexperienced project manager Iftheproject managers are not experienced then they faces lot of issuesand challengesin finishingthe project. ModeratePossibleThe problem can beavoidedby hiring experienced project managers withinthe project. Improper integration If the system is notintegrated properly,inthe cloudthenthe datathatis entered will not store within the cloudandasa result,thedata aswellas SignificantLikelyItcanbe mitigated by the checkingthe problembythe systemengineer whogenerally fixesthe problem.
10 PROJECT MANAGEMENT informationcan get lost. Improper management If the project is notmanaged properlywithin the project then itwillbequite difficult to finish theprojecton expectedtime and budget. ModeratePossibleProper management strategiesmust beutilizedby the staffs of the organizationfor managingthe projectineach of the phase of the project. 6.2 Assumption The assumptions that are made within the project are as follows: The entire project will get finished within the budget of around$10 000. It is expected that the project of CRM development will get finished within 58 days. It is assumed that the project will follow the project scope during the entire progress phase. 6.3 Constraints The constraints of the project are as follows:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
11 PROJECT MANAGEMENT Time:The development of CRM system must be finished within 58 days otherwise the budget that is associated with project development will increase. Budget:The entire project should be finished within the budget $10 000. Scope:The project must follow the scope in order execute the entire project within the expected budget and time. 7. Stakeholder list The stakeholders who are involved within the project are listed in the table below: StakeholdersResponsibilities Project managerThe project manager mainly engages within the project in order to manage, monitor as well as execute the project from the initiation until the closure phase of the project. Project plannerTheprojectplannermainlyengagesin estimating the resources as well as time that is needed in finishing the project effectively. They also monitors as well as determines the effectiveness of the project with the help of proper qualitative and quantitative tools. Human resource managerThe human resource manager is the person whomainlyengagesinhiringtheteam members for the project. Financial managerThe financial managers plays a great role in
12 PROJECT MANAGEMENT managingthebudgetoftheproject successfully. Application engineerThe application engineers are responsible for developing,designingaswellas implementing various applications as well as programs. They are generally able to create applicationsthatgenerallyrespondtothe needsaswellasrequirementsofthe customers.Inadditiontothis,theyalso provide technical support. Database administratorThe database administrator is responsible for softwareinstallation,maintenance,data extraction,loading,transformation, specialized handling of data, proper database backupandrecovery.Thedatabase administratoralsoplaysagreatrolein minimizing the risks that is associated with the database software. Technical analystThe technical analyst are the person who are mainlyresponsibleforadministeringIT systems for recommending proper efficient modifications for improving the efficiency as wellasforreducingtheoperationsby