Question 1
Job Work Center/Machine Hours
Due Date (days)
1 A/3, B/2, C/2 3
2 C/2, A/4 2
3 B/6, A/1, C/3 4
4 C/4, A/1, B/2 3
a. Gantt chart using finite capacity scheduling
Mahchine/Hr 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
A 1 1 1 2 2 2 2 4 3
B 1 1 3 3 3 3 3 3 4 4
C 2 2 4 4 4 4 1 1 3 3 3
b. Makespan = 18 hour
c. Machine idle time:
For machine A= 9 hrs, B= 10 hrs and C= 11 hrs.
Total Idle Time = 30 hrs.
d. Waiting time for each job:
Job 1 = 2 hrs.
Project Management | Assignment-2_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Research on Industrial Engineering
|10
|823
|16

Operations Management Project
|5
|669
|51

Industrial Engineering Assignment
|7
|1253
|94

Project Network Analysis for Desklib Online Library
|6
|820
|407

Project Management: Network Diagram Question Answer 2022
|18
|3026
|16

Business Process Design Assignment 2022
|11
|1948
|32