Running Head: PROJECT MANAGEMENT
Project Management Assignment 3: OSFMS
Name of the Student
Name of the University

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Table of Contents
Part One: MOV – Measurable Organizational Value......................................................................2
Part Two: Scope Management Plan.................................................................................................2
Part Three: Work Breakdown Structure and Budget.......................................................................4
Part Four: Risk Analysis and Plan.................................................................................................13
Part Five: Quality Management Plan.............................................................................................14
Part Six: Closure and Evaluation...................................................................................................14
Bibliography..................................................................................................................................17
Appendix........................................................................................................................................18
Document Page
2PROJECT MANAGEMENT
Part One: MOV – Measurable Organizational Value
MOV or Measurable Organizational Value is used to list a set of parameters related to the
goal of the project.
Desired Area of Impact – There are a number of desired areas in the project but based on
the analysis, it can be said that the main desired area is the customer. The entire project has been
designed to fulfill the needs of the stud farm managers although Globex also desires to make a
significant impact in finance by preparing a sustainable stud farm management system business.
Value – The main values of the project are faster and better. The OSFMS is faster and
also much more efficient than the manually managed stud farm systems.
Metric – Some of the appropriate metrics based on which the project will be evaluated
are the cost benefit and business sustainability in terms of annual profit.
Timeframe – The estimated time frame is approximately 6 months.
Summary of MOV – In this project, within the 6 months time, an online stud farm
management system will be delivered that will solve the problems faced by the stud farm
managers.
Part Two: Scope Management Plan
The development of the online stud farm management system (OSFMS) is within the
scope of the project. In order to control the scope, the MOV of the project is to be defined
accurately and the stakeholders need to be aware of scope creep. Regular reporting to project
manager is also recommended to prevent scope creep.
Document Page
3PROJECT MANAGEMENT
Resource Name Type
Max.
Units
Std. Rate Ovt. Rate Cost/Use
Accrue
At
Base
Calendar
Project Manager Work 100% $140.00/hr $0.00/hr $0.00 Prorated Standard
Finance
Manager
Work 100% $85.00/hr $0.00/hr $0.00 Prorated Standard
Human
Resource
Recruiter
Work 100% $90.00/hr $0.00/hr $0.00 Prorated Standard
Project
Supervisor
Work 100% $115.00/hr $0.00/hr $0.00 Prorated Standard
Development
Technologist
Work 100% $55.00/hr $0.00/hr $0.00 Prorated Standard
Software Testing
Specialist
Work 100% $50.00/hr $0.00/hr $0.00 Prorated Standard
Hardware Material $12,500.00 $0.00 Prorated
Software Material $5,500.00 $0.00 Prorated
Facilities and
Others
Material $2,000.00 $0.00 Prorated

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
Part Three: Work Breakdown Structure and Budget
The work breakdown structure is as follows.
WBS Task Name Duration Start Finish
0 Development of OSFMS 136 days Tue 6/5/18 Tue 12/11/18
1 Survey, Discuss, Plan 11 days Tue 6/5/18 Tue 6/19/18
1.1
Meet with stud farm
managers
4 days Tue 6/5/18 Fri 6/8/18
1.2
Discuss Issues and
Problems
2 days Mon 6/11/18 Tue 6/12/18
1.3 Survey in Stud Farms 1 day Wed 6/13/18 Wed 6/13/18
1.4
Present Proposal for
OSFMS
2 days Thu 6/14/18 Fri 6/15/18
1.5 Feasibility Testing 2 days Mon 6/18/18 Tue 6/19/18
1.6 M1: End of Discussions 0 days Tue 6/19/18 Tue 6/19/18
2 Estimate, Plan 18 days Wed 6/20/18 Fri 7/13/18
2.1
Allocate Members to
Teams
1 day Wed 6/20/18 Wed 6/20/18
2.2 Primary Plan 8 days Thu 6/21/18 Mon 7/2/18
Document Page
5PROJECT MANAGEMENT
2.2.1 Setting project goals 2 days Thu 6/21/18 Fri 6/22/18
2.2.2 Determination of scope 1 day Mon 6/25/18 Mon 6/25/18
2.2.3
Determine suitable
methodology for execution
2 days Tue 6/26/18 Wed 6/27/18
2.2.4
Project charter
development
0.5 days Thu 6/28/18 Thu 6/28/18
2.2.5 Schedue estimation 0.5 days Thu 6/28/18 Thu 6/28/18
2.2.6 Budget estimation 2 days Fri 6/29/18 Mon 7/2/18
2.3 Secondary Plan 9 days Tue 7/3/18 Fri 7/13/18
2.3.1
Risk register
development
3 days Tue 7/3/18 Thu 7/5/18
2.3.2 Identify risk 1 day Fri 7/6/18 Fri 7/6/18
2.3.3 Identify mitigation plan 1 day Mon 7/9/18 Mon 7/9/18
2.3.4
Analyze Measurable
Organizational Value
2 days Tue 7/10/18 Wed 7/11/18
2.3.5 Develop management
plan for quality and
2 days Thu 7/12/18 Fri 7/13/18
Document Page
6PROJECT MANAGEMENT
evaluation
2.4 M2: End of planning 0 days Fri 7/13/18 Fri 7/13/18
3 Initiate and Prepare 15 days Mon 7/16/18 Fri 8/3/18
3.1
Receive budget from
authority
4 days Mon 7/16/18 Thu 7/19/18
3.2 Hire system experts 4 days Fri 7/20/18 Wed 7/25/18
3.3
Allocate Duties to Team
Members
1 day Thu 7/26/18 Thu 7/26/18
3.4 Purchase Hardware 4 days Fri 7/27/18 Wed 8/1/18
3.5 Purchase Software 2 days Thu 8/2/18 Fri 8/3/18
3.6 M3: Proceed to Project 0 days Fri 8/3/18 Fri 8/3/18
4 Execute 85 days Mon 8/6/18 Fri 11/30/18
4.1 Technical Upgrade 4 days Mon 8/6/18 Thu 8/9/18
4.2 Install Software Platform 2 days Fri 8/10/18 Mon 8/13/18
4.3 System Development 67 days Tue 8/14/18 Wed 11/14/18
4.3.1
Start designing of
website
20 days Tue 8/14/18 Mon 9/10/18

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
4.3.2 Initial Testing 6 days Tue 9/11/18 Tue 9/18/18
4.3.3 Add features required 15 days Wed 9/19/18 Tue 10/9/18
4.3.4
Coding and
programming
10 days Wed 10/10/18 Tue 10/23/18
4.3.5 Second testing 6 days Wed 10/24/18 Wed 10/31/18
4.3.6
Complete the overall
website system
10 days Thu 11/1/18 Wed 11/14/18
4.4 Testing the system 12 days Thu 11/15/18 Fri 11/30/18
4.4.1
Connect with main
server
4 days Thu 11/15/18 Tue 11/20/18
4.4.2
Test the running of
website features
3 days Wed 11/21/18 Fri 11/23/18
4.4.3
Remove bugs and
glitches
5 days Mon 11/26/18 Fri 11/30/18
4.5 M4: Handover 0 days Fri 11/30/18 Fri 11/30/18
5 Review and Close 7 days Mon 12/3/18 Tue 12/11/18
5.1 Post project review 2 days Mon 12/3/18 Tue 12/4/18
5.2 Perform project appraisal 1 day Wed 12/5/18 Wed 12/5/18
Document Page
8PROJECT MANAGEMENT
5.3 Submit project report 4 days Thu 12/6/18 Tue 12/11/18
5.4 M5: Complete signoff 0 days Tue 12/11/18 Tue 12/11/18
Figure 1: WBS of the Project
(Source: Created by Author)
Bottom up technique is used for cost estimation as follows.
Task Name Resource Names Cost
Development of OSFMS $131,920.00
Survey, Discuss, Plan $22,440.00
Meet with stud farm
managers
Project Manager, Project Supervisor $8,160.00
Document Page
9PROJECT MANAGEMENT
Discuss Issues and
Problems
Project Manager, Project Supervisor $4,080.00
Survey in Stud Farms Project Manager, Project Supervisor $2,040.00
Present Proposal for
OSFMS
Project Manager, Project Supervisor $4,080.00
Feasibility Testing Project Manager, Project Supervisor $4,080.00
M1: End of Discussions Project Manager, Project Supervisor $0.00
Estimate, Plan $35,400.00
Allocate Members to
Teams
Human Resource Recruiter $720.00
Primary Plan $16,320.00
Setting project goals Project Manager, Project Supervisor $4,080.00
Determination of
scope
Project Manager, Project Supervisor $2,040.00
Determine suitable
methodology for execution
Project Manager, Project Supervisor $4,080.00
Project charter
development
Project Manager, Project Supervisor $1,020.00

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT MANAGEMENT
Schedue estimation Project Manager, Project Supervisor $1,020.00
Budget estimation Project Manager, Project Supervisor $4,080.00
Secondary Plan $18,360.00
Risk register
development
Project Manager, Project Supervisor $6,120.00
Identify risk Project Manager, Project Supervisor $2,040.00
Identify mitigation
plan
Project Manager, Project Supervisor $2,040.00
Analyze Measurable
Organizational Value
Project Manager, Project Supervisor $4,080.00
Develop management
plan for quality and
evaluation
Project Manager, Project Supervisor $4,080.00
M2: End of planning Project Manager, Project Supervisor $0.00
Initiate and Prepare $32,040.00
Receive budget from
authority
Finance Manager $2,720.00
Hire system experts Human Resource Recruiter, Facilities and $4,880.00
Document Page
11PROJECT MANAGEMENT
Others[1]
Allocate Duties to Team
Members
Project Supervisor $920.00
Purchase Hardware Project Supervisor, Hardware[1] $16,180.00
Purchase Software Project Supervisor, Software[1] $7,340.00
M3: Proceed to Project Development Technologist $0.00
Execute $36,920.00
Technical Upgrade Development Technologist $1,760.00
Install Software
Platform
Development Technologist $880.00
System Development $29,480.00
Start designing of
website
Development Technologist $8,800.00
Initial Testing Development Technologist $2,640.00
Add features required Development Technologist $6,600.00
Coding and
programming
Development Technologist $4,400.00
Second testing Development Technologist $2,640.00
Document Page
12PROJECT MANAGEMENT
Complete the overall
website system
Development Technologist $4,400.00
Testing the system $4,800.00
Connect with main
server
Software Testing Specialist $1,600.00
Test the running of
website features
Software Testing Specialist $1,200.00
Remove bugs and
glitches
Software Testing Specialist $2,000.00
M4: Handover Project Supervisor $0.00
Review and Close $5,120.00
Post project review Project Manager $2,240.00
Perform project
appraisal
Project Manager $1,120.00
Submit project report Development Technologist $1,760.00
M5: Complete signoff Human Resource Recruiter, Finance
Manager, Project Manager, Project
Supervisor, Development Technologist,
$0.00

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13PROJECT MANAGEMENT
Software Testing Specialist
2 3 4
$0.00
$10,000.00
$20,000.00
$30,000.00
$40,000.00
$50,000.00
$60,000.00
$70,000.00
$80,000.00
$0.00
$20,000.00
$40,000.00
$60,000.00
$80,000.00
$100,000.00
$120,000.00
$140,000.00
Cost Cumulative Cost
Figure 2: Time Phased Budget
(Source: Created by Author)
Assumption: The market change will not be significant during the entire course of the
project execution.
Constraint: Stakeholders may not be happy with the allocated standard rates of resource
usage.
Part Four: Risk Analysis and Plan
Risk Name Responsible Stakeholder Mitigation Strategy
Out of Scope Project Manager Analyze all requirements before
determining scope
Document Page
14PROJECT MANAGEMENT
Budget Overshoot Finance Manager Use suitable tools for accurate
budget estimation
Schedule Overshoot Project Manager Use suitable tools for accurate
time estimation
Massive Market Change Finance Manager Consider market changes during
budget estimation
Poor Performance from
Stakeholders
Project Manager Monitoring and control of
stakeholders during project
Part Five: Quality Management Plan
The verification and validation activities in the project are listed in the following table.
Verification Activities Meet with team members and Globex authority, verify project charter and
project report
Validation Activities Validation of project plan, validation of project report by project manager
Part Six: Closure and Evaluation
Article 1 – Haimes, Y. Y. (2015). Risk modeling, assessment, and management. John
Wiley & Sons.
The authors have discussed all aspects and phases of a project including project
evaluation and closing. According to them, project evaluation is basically a review in order to
determine whether the requirements have been met or not.
Document Page
15PROJECT MANAGEMENT
Article 2 – Joslin, R., & Müller, R. (2015). Relationships between a project management
methodology and project success in different project governance contexts. International Journal
of Project Management, 33(6), 1377-1392.
The authors said that the project review process consists of a number of sub-phases –
review of project report document, demonstration of the developed system and checking of a
closure list. If any of these is not successful, the project manager can reopen the project for
further development and execution.
Article 3 – Hornstein, H. A. (2015). The integration of project management and
organizational change management is now a necessity. International Journal of Project
Management, 33(2), 291-298.
According to the author, all the stakeholders should participate in project closing in order
to determine whether all requirements have been made as well as reflect on their own duties and
activities. The final power is on the project manager who will perform the final review and close
off the project.
Closure Checklist
Item Check
System developed as per plan
Features included as per plan
Project did not exceed budget
Project did not exceed schedule
Signature

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16PROJECT MANAGEMENT
Project Evaluation Outline
Project evaluation will be done on the outcomes generated at the end of the project. The
stakeholders will perform primary project evaluation in which they will review whether all their
duties are fulfilled. The project manager will perform the final project review and validate the
project.
Document Page
17PROJECT MANAGEMENT
Bibliography
Haimes, Y. Y. (2015). Risk modeling, assessment, and management. John Wiley & Sons.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), 1377-1392.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Muller, R. (2017). Project governance. Routledge.
Špundak, M. (2014). Mixed agile/traditional project management methodology–reality or
illusion?. Procedia-Social and Behavioral Sciences, 119, 939-948.
Document Page
18PROJECT MANAGEMENT
Appendix
Figure: Project Schedule Using MS Project

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19PROJECT MANAGEMENT
Figure: Project Resources Using MS Project